A construction company requires the following activities for a project
(Not rated)
(Not rated)
A construction company requires the following activities for a project:
Activity | Immediate Predecessor | Activity time |
A | None | 5 |
B | None | 2 |
C | B | 7 |
D | A, C | 2 |
E | B | 6 |
F | D | 6 |
G | E | 5 |
a. Draw a Gantt chart for this project
b. What is the project completion time?
c. Draw a activity on node network for this project
d. Make a forward pass and a backward pass to determine ES, LS, EF and LF for all activities
e. What is the critical path?
f. Propose a plan to reduce the project duration by 2 days.