c4
Part I
Calculate the expected time (hours, days, weeks, or whatever) for the following tasks. Report the time to the next highest whole number.
| Task | Optimistic (shortest) Time | Most Likely Time | Pessimistic (longest) Time | Expected Time (answer) |
| A | 3 | 5 | 7 | |
| B | 10 | 15 | 20 | |
| C | 4 | 5 | 6 | |
| D | 27 | 45 | 90 | |
| E | 8 | 9 | 12 | |
| F | 81 | 93 | 98 |
Part II
Each of these CPM diagrams corresponds to one of the task lists given below. Match them. Ex. A:#, B:#, etc. START END | A.
| B.
|
C.
| D.
| E.
|

Part III

Part IV

Estimated and crash costs for each task are shown in the table below.
Answer the questions below the table.
| Version 1 | Original Estimates | Crash Estimates | Crash Differentials | ||||
Task
(T) | CP
* | Est. Time, weeks (ET) | Est. cost, $1000, (EC) | Crash Time, weeks (CT) | Crash Cost, $1000 (CC) | Time saved
(ET-CT) | Extra cost
(CC-EC) |
| A | * | 5 | 10 | 4 | 12 | ||
| B | * | 7 | 15 | 5 | 17 | ||
| C | 5 | 8 | 3 | 12 | |||
| D | * | 6 | 6 | 5 | 8 | ||
| E | * | 9 | 12 | 8 | 15 | ||
| F | 4 | 16 | 2 | 20 | |||
| G | * | 5 | 20 | 2 | 21 | ||
| (End) | - | ||||||
CP=Critical Path. If task is on CP, then *; otherwise blank.
- Fill in the blank cells under Crash Differentials.
- Instead of the scheduled 7 weeks, Task B took 9 weeks. Which task or tasks should be crashed to make up the lost time, at minimum cost? Explain.
Assignment Expectations
- There are no page limits. Write what you need to write, neither more nor less. Make each sentence count! (Having said that; it’s unlikely that one page would be enough, and very likely that eight pages would be too much.)
- Ensure that your answer reflects your detailed understanding of the theory and techniques taught in this module.
- References and citations are required. This requirement can be satisfied by citing the module Home page.
9 years ago
20
Answer(1)![blurred-text]()
![]()
Purchase the answer to view it

NOT RATED
- c4.doc
Bids(1)
other Questions(10)
- MED 199: Medical Administrative Assisting Module 2 Homework Assignment
- Using Math to Make a Decision
- MOS 5525 WK 7 Essay 2
- Assignment 6 -- P9-17 P9-19 P9-26 P10-20 P10-21 P10-22 -- Examples: P9-20, P9-24, C9-29, P10-23.
- HLT 310V Module 3 DQ 1
- this was the name of arleys band
- Audit Exercise Paper One
- Exam 5
- Criminal Justice-Importance of the law
- Research Paper