BADM 425 -- Problem Assignment #4

Line Balancing  (20 pts.)

Due:  by 11:59 (CT) 09/30/13

 

 

Complete the following problem and submit the file to the appropriate D2L drop box for this assignment.  You must show me your work (computations) in this document in order to earn the credit – using Word’s equation editor might be best.  Handwriting on the screen or uploading a photo of handwritten work is unacceptable.  I expect you to use the editing capabilities of MS Word to complete this problem.  You may copy and paste any work done using other software into this document.  Simply listing a couple of numbers is not acceptable --  I must be able to evaluate your responses.  Balance the line using the editable worksheet on page 2.  Do not change the filename (425Problem4.docx) when you save or submit the file to the dropbox, D2L will add your name to the filename when I download it.

 

 

Consider a production line that is to be used for 10 hours per day in order to meet forecasted demand of 900 units per day.  The following precedence diagram with times in seconds describes the tasks necessary to produce this product:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

For output equal to forecasted demand, what is the % idle time and efficiency of this line if tasks are assigned to workstations using the longest task time rule?


 

 

Line Balancing Worksheet

 

Work

Station

Rem.

Time

 

Candidates

 

Feasible

 

Assign

 

Idle Time

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 