Assume the number of days it takes a homebuilder to complete a house is normally distributed

profiletutor4helpyou
 (Not rated)
 (Not rated)
Chat

Assume the number of days it takes a homebuilder to complete a house is normally distributed with an average completion time of 176.7 days and a standard deviation of 24.8 days. Calculate the completion time that the builder has a 40% probability of achieving.