Note: Write the formula for every question depending upon the requirement

Question 1: 15 marks

 

A toy manufacturing company makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The company has orders for 15,000 of these tricycles. Current schedules yield the following information.

 

 

Requirements

 

 

Cost to

Cost to

Component

Plastic

Time

Space

Manufacture

Purchase

Front

2

9

2

9

15

Seat/Frame

4

7

2

5

10

Rear wheel (each)

.75

3

.1

2

5

     Available

50000

160000

30000

 

 

 

The company obviously does not have the resources available to manufacture everything needed for the completion of 15000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 16000 fully completed tricycles at the minimum cost.

What are the decision variables, objective function, constraints ?

 

Question 2: 15 marks

 

           The distribution system for a Herman Company consists of three plants, two warehouses and four customers. Plant capacities and shipping costs (€) from each plant to each warehouse are given below:

Plant

Warehouse

1

2

Capacity

1

7

4

600

2

8

5

380

3

6

7

700

 

Customer demand and shipping costs per unit in € from each warehouse to each customer are given in the table below:

 

 

Warehouse

Customer

1

2

3

4

1

3

4

8

7

2

5

7

6

4

Demand

500

400

300

480

 

a.       Draw a network model of this problem.

b.      Develop the linear program for this problem.

 

Question 3: 20 marks

 

Given the following details of activities and times estimated in days,

 

 

Activity

Precedence

Activities

 

Optimistic

Most

Probable

 

Pessimistic

A

---

2

5

6

B

---

1

3

7

C

---

6

7

10

D

A

5

12

14

E

A

3

4

5

F

A, B

8

9

12

G

C

4

6

8

H

C

2

6

9

I

E, F, G

5

7

12

J

H

12

13

14

K

D, J

2

3

4

 

 

a.      What are the critical path activities?

b.      What is the expected time to complete the project?

 

c.       What is the probability the project will take more than 32 days to complete?

    • 9 years ago
    A++ ANSWER
    NOT RATED

    Purchase the answer to view it

    blurred-text
    • attachment
      assignment_solved.docx