A+ Answers
Section I
Use the table and partial network diagram provided to answer the questions in this section.
1. What is the early start (ES) time for activity J? (5 pts.)
2. What is the early finish (EF) time for activity H? (5 pts.)
3. What is the late finish (LF) time for activity D? (5 pts.)
9 days
4. What is the late start (LS) time for activity C? (5 pts.)
5. What is the finish slack for activity F? (5 pts.)
Section II
Use the table provided to answer the questions in this section.
6. Which activities are on the critical path? (10 pts.)
7. What is the duration of the project? (Write only the number; do not write units, such as days.) (10 pts.)
8. Which activity has the most start slack? (5 pts.)
Section III
Use the table and partial network diagram provided to answer the questions in this section.
9. What is the early start (ES) time for activity G? (5 pts.)
10. What is the early finish (EF) time for activity E? (5 pts.)
11. What is the late finish (LF) time for activity A? (5 pts.)
12. What is the late start (LS) time for activity C? (5 pts.)
3
13. What is the finish slack for activity J? (5 pts.)
Section IV
Use the table provided to answer the questions in this section.
14. Which activities are on the critical path? (10 pts.)
15. What is the duration of the project? (Write only the number; do not write units, such as days.) (10 pts.)
16. Which activity has the most start slack? (5 pts.)
11 years ago