3. (TCO C) A project to remodel an office area has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)
Activity | Duration | Predecessors |
A | 3 months | --- |
B | 2 months | --- |
C | 3 months | --- |
D | 4 months | A, B |
E | 3 months | A |
F | 2 months | B, C |
G | 2 months | F |
H | 1 month | G |
I | 4 months | D, E, F |
J | 5 months | H |
a) What are the critical path activities? (5 points)
b) What is the project's scheduled completion time? (5 points)
c) What is the slack or float for Activity B? Show your calculations. (5 points)
d) What is the slack or float for Activity C? Show your calculations. (5 points)
e) What is the slack or float for Activity E? Show your calculations. (5 points)
f) What is the slack or float for Activity H? Show your calculations. (5 points) (Points : 30)
12 years ago
10
Answer(2)![blurred-text]()
![]()
![blurred-text]()
![]()
Purchase the answer to view it

- pert_cpm.docx
Purchase the answer to view it

NOT RATED
- tco_c_a_project_to_remodel_solve_file.doc
Bids(1)
other Questions(10)
- The Role of the Leader in Evaluating Data to Improve Quality and Safety Paper
- Discuss three ways by which the female reproductive system function can become impaired.
- Grammar
- astronomy
- Write a 350- to 700-word paper, describing Amazon’s strategy. Discuss whether the company is moving away from its core competency of being a leading online retailer. Discuss whether this is a wise strategy and address the following:
- The Progressives
- IT Virtualisation
- MGT 307 Week 4 Team Paper
- mgt -350 team assignment week-2
- Cultural Diversity 7