3. (TCO C) A project to remodel an office area has the following activities. (Hint: You will need to build an AIB/AON diagram, perform a forward pass, and perform a backward pass to answer this question.)

Activity
Duration
Predecessors
A
3 months
---
B
2 months
---
C
3 months
---
D
4 months
A, B
E
3 months
A
F
2 months
B, C
G
2 months
F
H
1 month
G
I
4 months
D, E, F
J
5 months
H


 
a) What are the critical path activities? (5 points)
b) What is the project's scheduled completion time? (5 points)
c) What is the slack or float for Activity B? Show your calculations. (5 points)
d) What is the slack or float for Activity C? Show your calculations. (5 points)
e) What is the slack or float for Activity E? Show your calculations. (5 points)
f) What is the slack or float for Activity H? Show your calculations. (5 points)
 
(Points : 30)

    • 12 years ago
    • 10
    Answer(2)

    Purchase the answer to view it

    blurred-text
    • attachment
      pert_cpm.docx

    Purchase the answer to view it

    blurred-text
    NOT RATED
    • attachment
      tco_c_a_project_to_remodel_solve_file.doc
    Bids(1)