After reading “Boeing Commercial Aircraft” case study (attached file). Complete a SWOT analysis on the case.

profileesolutions
 (Not rated)
 (Not rated)
Chat

After reading “Boeing Commercial Aircraft” case study (attached file). Complete a SWOT analysis on the case. 

•Strengths•Weaknesses•Opportunities•Threats

•Personal Observations. 

Each section is to be 190-200 words, with reference citations if it is possible. 

 

 

Case 1 

 

 

Boeing Commercial 

Aircraft: Comeback? 

 

 

This case was prepared by Charles W. L. Hill, the University of Washington. 

 

I

I

t looked as if 2006 would be the year that Boeing 

could boast of a comeback in its three-decadeslong 

duel with Airbus Industries. Long the dominant 

player in the commercial aerospace industry, Boeing 

has been steadily losing market share to Airbus from 

the mid-1990s onwards (represented in Exhibit 1). 

In 1999, for the first time in its history, Airbus garnered 

more orders for new commercial jet aircraft 

than Boeing. The European upstart repeated this 

achievement regularly between 2001 and 2005. 

 

By mid-2006, however, the tide seemed to be 

shifting in Boeing's favor. Underlying this were 

strong sales of Boeing's newest jet, the super-efficient 

wide-bodied 787, along with surging sales of its well-

established 737 and 777 jets. For the first six months 

of 2006, Boeing took orders for 487 aircraft; Airbus 

took just 117. While Boeing seemed to be leaving a 

decade of production problems and ethics scandals 

behind it, Airbus was mired in problems of its own. 

Its largest jet to date, the A380 super jumbo, had 

been delayed from entering service while the company 

struggled with production problems. Orders 

for the A380 had stalled at 159 for almost a year, and 

analysts were beginning to question whether the aircraft 

would be a commercial success. Moreover, Airbus's 

contender to the Boeing 787, the A350, had to 

be scrapped before it even left the drawing board 

 

Copyright © 2007 by Charles W. L. Hill. This case is intended to be 

used as a basis for class discussion rather than as an illustration of either 

effective or ineffective handling of the situation. Reprinted by 

permission of Charles W. L. Hill. All rights reserved. For the most recent 

financial results of the company discussed in this case, go to 

http://finance.yahoo.com, input the company's stock symbol, and 

download the latest company report from its homepage. 

 

due to negative customer feedback. The challenge 

facing Boeing's management was to translate this revival 

in fortunes for the company into a sustainable 

competitive advantage. It was off to a good start, but 

what else needed to be done? 

 

The Competitive Environment 

 

By the 2000s, the market for large commercial jet 

aircraft was dominated by just two companies, 

Boeing and Airbus. A third player in the industry, 

McDonnell Douglas, had been significant historically 

but had lost share during the 1980s and 1990s. 

In 1997, Boeing acquired McDonnell Douglas, primarily 

for its strong military business. Since the mid1990s, 

Airbus had been gaining orders at Boeing's 

expense. By the mid-2000s, the two companies were 

splitting the market. 

 

Both Boeing and Airbus now have a full range of 

aircraft. Boeing offers five aircraft "families" that 

range in size from 100 to over 500 seats. They are the 

narrow-bodied 737 and the wide-bodied 747, 767, 

777, and 787 families. Each family comes in various 

forms. For example, there are currently four main 

variants of the 737 aircraft. They vary in size from 

110 to 215 seats and in range capability from 2,000 

to over 5,000 miles. List prices vary from $47 million 

for the smallest member of the 737 family, the 737600, 

to $282 million for the largest Boeing aircraft, 

the 747-8. The newest member of the Boeing family, 

the 787, lists for between $138 million and $188 million, 

depending on the model.1 

 

Similarly, Airbus offers four families: the narrow-

bodied A320 family and the wide-bodied A300/310, 

 

C1 

 

C2 PART 5 Cases in Strategic Management 

 

A330/340, and A380 families. These aircraft vary in 

size from 100 to 550 seats. The range of list prices is 

similar to Boeing's. The A380 super jumbo lists for 

between $282 million and $302 million, while the 

smaller A320 lists for between $62 million and $66.5 

million.2 Both companies also offer freighter versions 

of their wide-bodied aircraft. 

 

Airbus was a relatively recent entrant into the 

market. Airbus began its life as a consortium between 

a French and a Germany company in 1970. 

Later a British and a Spanish company joined the 

consortium. Initially, few people gave Airbus much 

chance for success, but the consortium gained 

ground by innovating. It was the first aircraft maker 

to build planes that "flew by wire," made extensive 

use of composites, flew with only two flight crew 

members (most flew with three), and used a common 

cockpit layout across models. It also gained 

sales by being the first company to offer a wide-

bodied twin engine jet, the A300, that was positioned 

between smaller single-aisle planes like the 737 and 

large aircraft such as the Boeing 747. 

 

In 2001, Airbus became a fully integrated company. 

The European Defense and Space Company 

(EADS), formed by a merger between French, German, 

and Spanish interests, acquired 80% of the 

shares in Airbus, and BAE Systems, a British company, 

took a 20% stake. 

 

Development and Production 

 

The economics of development and production in 

the industry are characterized by a number of facts. 

First, the R&D and tooling costs associated with developing 

a new airliner are very high. Boeing spent 

some $5 billion to develop the 777. Its latest aircraft, 

the 787, is expected to cost $8 billion to develop. Development 

costs for Airbus's latest aircraft, the A380 

super jumbo, could run as high as $15 billion. 

 

Second, given the high upfront costs, to break 

even a company has to capture a significant share of 

projected world demand. The breakeven point for 

the Airbus super jumbo, for example, is estimated to 

be between 250 and 270 aircraft. Estimates of the total 

potential market for this aircraft vary widely. 

Boeing suggests that the total world market will be 

no more than 320 aircraft over the next twenty years. 

Airbus believes that demand for this size aircraft will 

be more like 1,250 jets. In any event, it may take five 

to ten years of production before Airbus breaks even 

on the A380—and that's on top of years of negative 

cash flow during development.3 

 

Third, there are significant learning effects in aircraft 

production.4 On average, unit costs fall by 

about 20% each time cumulative output of a specific 

model is doubled. The phenomenon occurs because 

managers and shop floor workers learn over time 

how to assemble a particular model of plane more 

efficiently, reducing assembly time, boosting productivity, 

and lowering the marginal costs of producing 

subsequent aircraft. 

 

Fourth, the assembly of aircraft is an enormously 

complex process. Modern planes have over 1 million 

component parts that have to be designed to fit with 

each other, and then produced and brought together 

at the right time to assemble the engine. At several 

times in the history of the industry, problems with 

the supply of critical components have held up production 

schedules and resulted in losses. In 1997, 

Boeing took a charge of $1.6 billion against earnings 

when it had to halt the production of its 737 and 747 

models due to a lack of component parts. 

 

Historically, airline manufacturers tried to manage 

the supply process through vertical integration, 

making many of the component parts that went into 

an aircraft (engines were long the exception to this). 

Over the last two decades, however, there has been a 

trend to contract out production of components and 

even entire subassemblies to independent suppliers. 

On the 777, for example, Boeing outsourced about 

65 percent of the aircraft production, by value, excluding 

the engines.5 While helping to reduce costs, 

contracting out has placed an enormous onus on 

airline manufacturers to work closely with their suppliers 

to coordinate the entire production process. 

 

Finally, all new aircraft are now designed digitally 

and assembled virtually before a single component is 

produced. Boeing was the first to do this with its 777 

in the early 1990s and its new version of the 737 in 

the late 1990s. 

 

Customers 

 

Demand for commercial jet aircraft is very volatile 

and tends to reflect the financial health of the commercial 

airline industry, which is prone to boom and 

bust cycles (see Exhibits 1 and 2). After a moderate 

boom during the 1990s, the airline industry went 

through a particularly nasty downturn during 

2001-2005. The downturn started in early 2001 due 

to a slowdown in business travel after the boom of 

the 1990s. It was compounded by a dramatic slump 

in airline travel after the terrorist attacks on the 

United States on September 11, 2001. Between 2001 

 

CASE 1 Boeing Commercial Aircraft: Comeback? C3 

 

Exhibit 1 

Commercial Aircraft Orders 1990-2005 

1200 

 

1000 

 

10 

 

 

1990 '91 '92 '93 '94 '95 '96 '97 '98 '99 2000 '01 '02 '03 '04 '05 

 

Boeing Airbus 

 

Sources: http://www.boeing.com, accessed September 2006; and http://www.airbus.com/en, accessed 

September 2006. 

 

and 2005, the entire global airline industry lost some 

$40 billion, more money than it had made since its 

inception.6 

 

For 2006, the industry was forecasted to lose $1.7 

billion, which represents an incremental improvement 

over the $3.2 billion lost in 2005. The industry 

would have been profitable in both 2005 and 2006 

 

Exhibit 2 

 

World Airline Industry Revenues 

 

500 

 

450 

 

400 

 

were it not for surging jet fuel prices after January 

2004 (prices for jet fuel more than doubled between 

2004 and 2006—see Exhibit 3). The International Air 

Travel Association estimates that the fuel bill for all 

airlines in 2006 was around $115 billion. This would 

represent over 25% of the industry's total operating 

costs in 2006, compared to less than 10% in 2001.7 

 

« 

 

2000 2001 2002 2003 2004 2005 2006 2007 

 

 

Source: IATA data (figures for 2006 and 2007 are forecasts), 

http://www.iata.org/whatwedo/economics/fuel_monitor/price_development. htm, 

accessed February 12,2007. 

 

C4 PART 5 Cases in Strategic Management 

 

Exhibit 3 

Jet Fuel and Crude Oil Prices 

 

120.0 

 

100.0 

 

Jan May Sep Jan May Sep Jan May Sep Jan May Sep 

'03 '03 '03 '04 '04 '04 '05 '05 '05 '06 '06 '06 

 

—— Jet fuel — Crude oil price (Brent) 

Source: IATA data, http://www.iata.org/whatwedo/economics/fuel monitor/price_ 

 

development.htm, accessed February 12, 2007. 

 

Losses were particularly severe among the big six 

airlines in the world's largest market, the United 

States (American Airlines, United, Delta, Continental, 

US Airways, and Northwest). Three of these airlines 

(United, Delta, and Northwest) were forced to 

seek chapter 11 bankruptcy protections. Even 

though demand and profits plummeted at the big six 

airlines, some carriers continued to make profits 

during 2001-2005, most notably the budget airline 

Southwest. In addition, other newer budget airlines, 

including AirTran and Jet Blue (which was started in 

2000), gained market share during this period. Indeed, 

between 2000 and 2003, the budget airlines in 

the United States expanded capacity by 44%, even as 

the majors slashed their carrying capacities and 

parked unused planes in the desert. In 1998, the 

budget airlines held a 16% share of the U.S. market; 

by mid-2004, their share had risen to 29%.8 

 

The key to the success of the budget airlines is a 

strategy that gives them a 30 to 50% cost advantage 

over traditional airlines. The budget airlines all follow 

the same basic script: They purchase just one 

type of aircraft (some standardize on Boeing 737s, 

others on Airbus 320s). They hire nonunion labor 

and cross-train employees to perform multiple jobs 

(to help meet turnaround times, for example, pilots 

might help check tickets at the gate). As a result of 

flexible work rules, Southwest needs only 80 employ

 

 

ees to support and fly an aircraft, compared to 115 at 

the big six airlines. The budget airlines also favor flying 

"point to point" rather than through hubs, and 

often use less costly secondary airports rather than 

major ones. They focus on large markets with lots of 

traffic (up and down the East Coast, for example). 

There are no frills on the flights (passengers receive 

no in-flight food or complementary drinks, for example). 

And prices are set low to fill the seats. 

 

In contrast, major airlines base their operations 

on the network, or "hub and spoke," system. Network 

airlines route their flights through major hubs; 

one airline often dominates a single hub (United 

dominates Chicago's O'Hare airport, for example). 

This system was developed for good reason: It efficiently 

uses airline capacity when there isn't enough 

demand to fill a plane flying point to point. By using 

a hub and spoke system, major network airlines are 

able to serve some 38,000 city pairs, some of which 

generate fewer than fifty passengers per day. By focusing 

on a few hundred city pairs, where there is 

sufficient demand to fill their planes, and flying directly 

between them (point to point), the budget airlines 

seem to have found a way around this constraint. 

The network carriers also suffer from a 

higher cost structure due to their legacy of a unionized 

workforce. In addition, their costs are pushed 

higher by their superior in-flight service. In good 

 

times, the network carriers can recoup their costs by 

charging higher prices than the discount airlines, 

particularly for business travelers, who pay more to 

book late and to fly business or first class. In the 

competitive environment of the early 2000s, however, 

this was no longer the case. 

 

Due to the effect of increased competition, the 

real yield that U.S. airlines get from passengers has 

fallen from 8.70 cents per mile in 1980 to 6.37 cents 

per mile in 1990, 5.12 cents per mile in 2000, and 

 

4.00 cents per mile in 2005 (these figures are expressed 

in constant 1978 cents).9 Real yields are also 

declining elsewhere. With real yields declining, the 

only way that airlines can become profitable is to reduce 

their operating costs. 

Outside of the United States, competition has intensified 

as deregulation has allowed low-cost airlines 

to enter local markets and capture share from 

long-established national airlines that have used the 

hub and spoke model. In Europe, for example, Ryan 

Air and Easy Jet have adopted the business model of 

Southwest and used it to grow aggressively. 

 

By the mid-2000s, large airlines in the United 

States were starting to improve their operating efficiency, 

helped by growing traffic volumes, higher 

load factors, and reductions in operating costs, particularly 

labor costs. Load factor refers to the percentage 

of a plane that is full on average, which hit a 

record 86% in 2006 in the United States and 81% in 

international markets. Total losses for the U.S. industry 

were projected to be $4.5 billion in 2006, primarily 

due to one-time accounting charges. European 

airlines were projected to make profits of $1.8 billion 

in 2006, and Asian airlines profits of $1.7 billion. For 

2007, the U.S. airlines were projected to break even, 

and the global industry was projected to earn 

around $2 billion.10 

 

Demand Projections 

 

Both Boeing and Airbus issue annual projections of 

likely future demand for commercial jet aircraft. 

These projections are based on assumptions about 

future global economic growth, the resulting growth 

in demand for air travel, and the financial health of 

the world's airlines. 

 

In its 2006 report, Boeing assumed that the world 

economy would grow by 3.1% per annum over the 

next twenty years, which should generate growth in 

passenger traffic of 4.8% per annum and growth in 

cargo traffic of 6.1% per year. On this basis, Boeing 

 

CASE 1 Boeing Commercial Aircraft: Comeback? C5 

-,*..-, 

 

forecast demand for some 27,210 new aircraft valued 

 

at $2.6 trillion over the next twenty years (1,360 de

 

 

liveries per year). Of this, some 9,580 aircraft will be 

 

replacements for aircraft retired from service, with 

 

the balance being aircraft to satisfy an expanded 

 

market. In 2025, Boeing estimates that the total 

 

global fleet of aircraft will be 35,970, up from 17,330 

 

in 2005. Boeing believes that North America will ac

 

 

count for 28% of all new orders, Asia Pacific for 

 

36%, and Europe for 24%. Passenger traffic is pro

 

 

jected to grow at 6.4% per annum in Asia versus 

 

3.6% in North America and 3.4% in Europe.11 

 

Regarding the mix of orders, Boeing believes that 

 

the majority will be for aircraft between regional jets 

 

(which have fewer than 100 seats) and the Boeing 

 

747 (see Exhibit 4). Aircraft in the 747 range (in

 

 

cluding the Airbus A380) will account for some 3% 

 

of deliveries and 10% of value between 2006 and 

 

2025, according to Boeing. 

 

The latest Airbus forecast covers 2004-2023. Over 

 

that period, Airbus forecasts world passenger traffic 

 

to grow by 5.3% per annum and predicts demand 

 

for 17,328 new aircraft worth $1.9 trillion. (Note 

 

that Airbus excludes regional jets from its forecasts; 

 

Boeing's forecasts include some 3,450 regional jet 

 

deliveries.) Airbus believes that demand for very 

 

large aircraft will be robust, amounting to 1,648 

 

large passenger aircraft and freighters in the 747 

 

range and above, or 22% of the total value of aircraft 

 

delivered.12 

 

The differences in the mix of orders projected by 

 

Boeing and Airbus reflect different views of how fu

 

 

ture demand will evolve. Airbus believes that hubs 

 

will continue to play an important role in airline 

 

travel, particularly international travel, and that very 

 

large jets will be required to transport people be

 

 

tween hubs. Airbus bases this assumption partly on 

 

an analysis of data over the last twenty years, which 

 

shows that traffic between major airline hubs has 

 

grown faster than traffic between other city pairs. 

 

Airbus also assumes that urban concentrations will 

 

continue to grow, with fifteen cities having popula

 

 

tions of more than 20 million by 2023, up from five 

 

in 2004. Airbus states that demand is simply a func

 

 

tion of where people want to go, and most people 

 

want to travel between major urban centers. The 

 

company notes, for example, that 90% of travelers 

 

going from the United States to China travel to three 

 

major cities. Fifty other cities make up the remaining 

 

10%, and Airbus believes that very few of these cities 

 

C6 PART 5 Cases in Strategic Management 

 

Exhibit 4 

Projected New Airplane Deliveries, 2006-2025 

 

New Airplane Deliveries New Airplane Market Value 

2006 to 2025 2006 to 2025 

 

(in year 2005 dollars) 

 

4% 

 

10% 

 

41% 

 

61% 

 

27,210 new airplanes $2.6 trillion 

 

Regional jets Single-aisle Twin-aisle 747 and larger 

Source: Boeing, http://www.boeing.com/commercial/cmo/new.html, accessed 2007. 

 

will have demand large enough to justify a nonstop 

service from North America or Europe. Based on 

this assumption, Airbus sees robust demand for very 

large aircraft, particularly its A380 offering. 

 

Boeing has a different view of the future. The 

company theorizes that hubs will become increasingly 

congested and that many travelers will seek to 

avoid them. Boeing thinks that passengers prefer frequent 

nonstop service between the cities they wish 

to visit. It also sees growth in travel between city 

pairs as being large enough to support an increasing 

number of direct long-haul flights. The company 

notes that continued liberalization of regulations 

governing airline routes around the world will allow 

for the establishment of more direct flights between 

city pairs. As in the United States, the company believes 

that long-haul, low-cost airlines will emerge 

that serve city pairs worldwide and avoid hubs. 

 

In sum, Boeing believes that airline travelers will 

demand more frequent nonstop flights, not larger 

aircraft.13 To support this, the company has data 

showing that all of the growth in airline travel since 

1995 has been met by the introduction of new nonstop 

nights between city pairs and by an increased 

frequency of flights between city pairs, not by an increase 

in airplane size. For example, Boeing notes 

that following the introduction of the 767, airlines 

introduced more flights between city pairs in North 

America and Europe and more frequent departures. 

In 1984, 63% of all flights across the North Atlantic 

were in the 747. By 2004, the figure had declined to 

 

13%, with smaller wide-bodied aircraft such as the 

767 and 777 dominating traffic. Following the introduction 

of the 777, which can fly nonstop across the 

Pacific and is smaller than the 747, the same process 

occurred in the North Pacific. In 2006, there were 

seventy-two daily flights serving twenty-six city pairs 

in North America and Asia. 

 

Boeing's History14 

 

William Boeing established the Boeing Company in 

1916 in Seattle. In the early 1950s, Boeing took an 

enormous gamble when it decided to build a large 

jet aircraft that could be sold both to the military as 

a tanker and to commercial airlines as a passenger 

plane. Known as the Dash 80, the plane had swept-

back wings and four jet engines. Boeing invested $16 

million to develop the Dash 80, two-thirds of the 

company's entire profits during the postwar years. 

The Dash 80 was the basis for two aircraft, the KC135 

Air Force tanker and the Boeing 707. Introduced 

into service in 1957, the 707 was the world's first 

commercially successful passenger jet aircraft. Boeing 

went on to sell some 856 Boeing 707s, along with 

820 KC-135s. The final 707, a freighter, rolled off the 

production line in 1994 (production of passenger 

planes ended in 1978). The closest rival to the 707 

was the Douglas DC 8, of which some 556 were ultimately 

sold. 

 

The 707 was followed by a number of other successful 

jet liners, including the 727, which entered 

 

service in 1962; the 737, which entered service in 

1967; and the 747, which entered service in 1970. 

The single-aisle 737 went on to become the workhorse 

of many airlines. In the 2000s, a completely redesigned 

version of the 737 that could seat between 

110 and 180 passengers was still selling strong. Cumulative 

sales of the 737 totaled 6,500 by mid-2006, 

making it by far the most popular commercial jet 

aircraft ever sold. 

 

It was the 747 "jumbo jet," however, that probably 

best denned Boeing. In 1966, when Boeing's 

board decided to develop the 747, they were widely 

viewed as betting the company on the jet. The 747 

was born out of the desire of Pan Am, then America's 

largest airline, for a 400-seat passenger aircraft 

that could fly 5,000 miles. Pan Am believed that the 

aircraft would be ideal for the growing volume of 

transcontinental traffic. However, beyond Pan Am, 

which committed to purchasing 25 aircraft, demand 

was very uncertain. Moreover, the estimated $400 

million in development and tooling costs placed a 

heavy burden on Boeing's financial resources. To 

make a return on its investment, the company estimated 

it would have to sell close to 400 aircraft. To 

complicate matters further, Boeing's principal competitors, 

Lockheed and McDonnell Douglas, were 

each developing 250-seat jumbo jets. 

 

Boeing's big bet turned out to be auspicious. Pan 

Am's competitors feared being left behind, and by 

the end of 1970, almost 200 orders for the aircraft 

had been placed. Successive models of the 747 extended 

the range of the aircraft. The 747-400, introduced 

in 1989, had a range of 8,000 miles and a 

maximum seating capacity of 550 (although most 

configurations seated around 400 passengers). By 

this time, both Douglas and Lockheed had exited the 

market, giving Boeing a lucrative monopoly in the 

very large commercial jet category. By 2005, the 

company had sold some 1,430 747s and was actively 

selling its latest version of the 747 family, the 747-8, 

which was scheduled to enter service in 2008. 

 

By the mid-1970s, Boeing was past the breakeven 

point on all of its models (707, 727, 737, and 747). 

The positive cash flow helped to fund investment in 

two new aircraft, the narrow-bodied 757 and the 

wide-bodied 767. The 757 was designed as a replacement 

to the aging 727, while the 767 was a response 

to a similar aircraft from Airbus. These were the first 

Boeing aircraft to be designed with two-person 

cockpits, rather than three. Indeed, the cockpit lay-

 

CASE 1 Boeing Commercial Aircraft: Comeback? 

 

out was identical, allowing the crew to shift from one 

 

aircraft to the other. The 767 was also the first air

 

 

craft for which Boeing subcontracted a significant 

 

amount of work to a trio of Japanese manufactur

 

 

ers—Mitsubishi, Kawasaki, and Fuji—which sup

 

 

plied about 15% of the airframe. Introduced in 1981, 

 

both aircraft were successful. Some 1,049 757s were 

 

sold during the life of the program, which ended in 

 

2003. Over 950 767s had been sold by 2006, and the 

 

program is still going. 

 

The next Boeing plane was the 777. A two-

 

engine, wide-bodied aircraft with seating capacity 

 

of up to 400 and a range of almost 8,000 miles, the 

 

777 program was initiated in 1990. The 777 was seen 

 

as a response to Airbus's successful A330 and A340 

 

wide-bodied aircraft. Development costs were esti

 

 

mated at some $5 billion. The 777 was the first wide-

 

bodied, long-haul jet to have only two engines. It 

 

was also the first to be designed entirely on com

 

 

puter. To develop the 777, for the first time Boeing 

 

used cross-functional teams composed of engineer

 

 

ing and production employees. It also brought major 

 

suppliers and customers into the development 

 

process. As with the 767, a significant amount of 

 

work was outsourced to foreign manufacturers, in

 

 

cluding the Japanese trio of Mitsubishi, Kawasaki, 

 

and Fuji, which supplied 20% of the 777 airframe. In 

 

total, some 60% of parts for the 777 were out

 

 

sourced. The 777 proved to be another successful 

 

venture. By mid-2006, 850 777s had been ordered, 

 

far more than the 200 or so required to break even. 

 

In December 1996, Boeing stunned the aerospace 

 

industry by announcing it would merge with long

 

 

time rival McDonnell Douglas in a deal estimated to 

 

be worth $13.3 billion. The merger was driven by 

 

Boeing's desire to strengthen its presence in the de

 

 

fense and space side of the aerospace business, where 

 

McDonnell Douglas was traditionally strong. On the 

 

commercial side of the aerospace business, Douglas 

 

had been losing market share since the 1970s. By 

 

1996, Douglas accounted for less than 10% of pro

 

 

duction in the large commercial jet aircraft market 

 

and only 3% of new orders placed that year. The 

 

dearth of new orders meant the long-term outlook 

 

for Douglas's commercial business was increasingly 

 

murky. With or without the merger, many analysts 

 

felt that it was only a matter of time before McDon

 

 

nell Douglas would be forced to exit from the com

 

 

mercial jet aircraft business. In their view, the merger 

 

with Boeing merely accelerated that process. 

 

C8 PART 5 Cases in Strategic Management 

 

The merger transformed Boeing into a broad-

based aerospace business within which commercial 

aerospace accounted for 40 to 60% of total revenue, 

depending on the stage of the commercial production 

cycle. In 2001, for example, the commercial aircraft 

group accounted for $35 billion in revenues out 

of a corporate total of $58 billion, or 60%. In 2005, 

with the delivery cycle at a low point (but the order 

cycle rebounding), the commercial airplane group 

accounted for $22.7 billion out of a total of $54.8 

billion, or 41%. The balance of revenue was made up 

by a wide range of military aircraft, weapons and defense 

systems, and space systems. 

 

In the early 2000s, in a highly symbolic act, 

Boeing moved its corporate headquarters from 

Seattle to Chicago. The move was an attempt to put 

some distance between top corporate officers and 

the commercial aerospace business, the headquarters 

of which remained in Seattle. The move was 

also intended to signal to the investment community 

that Boeing was far more than its commercial 

businesses. 

 

To some extent, the move to Chicago may have 

been driven by a number of production missteps in 

the late 1990s that hit the company at a time when it 

should have been enjoying financial success. During 

the mid-1990s, orders boomed as Boeing cut prices 

in an aggressive move to gain share from Airbus. 

However, delivering these aircraft meant that Boeing 

had to more than double its production schedule between 

1996 and 1997. As it attempted to do this, the 

company ran into some severe production bottlenecks.

15 The company scrambled to hire and train 

some 41,000 workers, recruiting many from suppliers, 

a move it came to regret when many of the suppliers 

could not meet Boeing's demands and shipments 

of parts were delayed. In the fall of 1997, 

things got so bad that Boeing shut down its 747 and 

737 production lines so that workers could catch up 

with out-of-sequence work and wait for back-

ordered parts to arrive. Ultimately, the company had 

to take a $1.6 billion charge against earnings to account 

for higher costs and penalties paid to airlines 

for the late delivery of jets. As a result, Boeing made 

very little money out of its mid-1990s' order boom. 

The head of Boeing's commercial aerospace business 

was fired, and the company committed itself to a 

major acceleration of its attempt to overhaul its production 

system, elements of which dated back half 

a century. 

 

Boeing in the 2000s 

 

In the 2000s, three things dominated the development 

of Boeing Commercial Aerospace. First, the 

company accelerated a decade-long project aimed at 

improving the company's production methods by 

adopting the lean production systems initially developed 

by Toyota and applying them to the manufacture 

of large jet aircraft. Second, the company considered 

and then rejected the idea of building a 

successor to the 747. Third, Boeing decided to develop 

a new wide-bodied, long-haul jetliner, the 787. 

 

Lean Production at Boeing 

 

Boeing's attempt to revolutionize the way planes are 

built dates back to the early 1990s. Beginning in 

1990, the company started to send teams of executives 

to Japan to study the production systems of 

Japan's leading manufacturers, particularly Toyota. 

Toyota had pioneered a new way of assembling automobiles 

known as lean production (in contrast to 

conventional mass production). 

 

Toyota's lean production system was developed 

by one of the company's engineers, Ohno Taiichi.16 

After working at Toyota for five years and visiting 

Ford's U.S. plants, Ohno became convinced that the 

mass-production philosophy for making cars was 

flawed. He saw numerous problems, including three 

major drawbacks. First, long production runs created 

massive inventories, which had to be stored in 

large warehouses. This was expensive because of the 

cost of warehousing and because inventories tied up 

capital in unproductive uses. Second, if the initial 

machine settings were wrong, long production runs 

resulted in the production of a large number of defects 

(that is, waste). And third, the mass-production 

system was unable to accommodate consumer preferences 

for product diversity. 

 

In looking for ways to make shorter production 

runs economical, Ohno developed a number of techniques 

designed to reduce setup times for production 

equipment, a major source of fixed costs. By using 

a system of levers and pulleys, he was able to 

reduce the time required to change dies on stamping 

equipment from a full day in 1950 to three minutes 

by 1971. This advance made small production runs 

economical, which allowed Toyota to respond more 

efficiently to consumer demands for product diversity. 

Small production runs also eliminated the need 

to hold large inventories, thereby reducing ware

 

 

 _ -

 

Ei.

 

housing costs. Furthermore, small product runs and 

the lack of inventory meant that defective parts were 

produced only in small numbers and entered the assembly 

process immediately. This reduced waste 

made it easier to trace defects to their source and fix 

the problem. In sum, Ohno's innovations enabled 

Toyota to produce a more diverse range of products 

at a lower unit cost than was possible with conventional 

mass production. 

 

Impressed with what Toyota had done, in the 

mid-1990s Boeing started to experiment with applying 

Toyota-like lean production methods to the production 

of aircraft. Production at Boeing used to be 

all about producing parts in high volumes and then 

storing them in warehouses until they were ready to 

be used in the assembly process. After visiting Toyota, 

engineers realized that Boeing was drowning in inventory. 

A huge amount of space and capital was tied 

up in things that didn't add value. Moreover, expensive 

specialized machines often took up a lot of space 

and were frequently idle for long stretches of time. 

 

Like Ohno at Toyota, company engineers started 

to think about how they could modify equipment 

and processes at Boeing to reduce waste. Boeing set 

aside space and time for teams of creative plant 

employees—design engineers, maintenance technicians, 

electricians, machinists, and operators—to start 

experimenting with machinery. They called these 

teams moonshiners. The term moonshine was coined 

by Japanese executives who visited the United States 

after World War II. They were impressed by two 

things in the United States—supermarkets and the 

stills built by people in the Appalachian hills. They 

noticed that people built these stills with no money. 

They would use salvaged parts to make small stills 

that produced alcohol that they sold for money. The 

Japanese took this philosophy back home with them 

and applied it to industrial machinery, which is where 

Boeing executives saw the concept in operation in the 

1990s. With the help of Japanese consultants, they decided 

to apply the moonshine creative philosophy at 

Boeing to produce new low-cost, "right-sized" machines 

that could be used to increase profits. 

 

The moonshine teams were trained in lean production 

techniques, given a small budget, and then 

set loose. Initially, many of the moonshine teams focused 

on redesigning equipment to produce parts. 

Underlying this choice was a Boeing study that 

showed that more than 80% of the parts manufactured 

for aircraft were less than 12 inches long, and 

 

CASE 1 Boeing Commercial Aircraft: Comeback? C9 

 

yet the metal-working machinery was huge and in

 

 

flexible and could economically produce parts only 

 

in large lots.17 

 

Soon, empowered moonshine teams were de

 

 

signing their own equipment—small-scale machines 

 

that took up little space and used wheels to allow the 

 

machines to move around the plant. One team, for 

 

example, replaced a large stamping machine that 

 

cost six figures and was used to produce L-shaped 

 

metal parts in batches of 1,000 with a miniature 

 

stamping machine powered by a small hydraulic 

 

motor that could be wheeled around the plant. With 

 

the small machine, which cost a couple of thousand 

 

dollars, parts could be produced very quickly in 

 

small lots, eliminating the need for inventory. They 

 

also made a sanding machine and a parts cleaner of 

 

equal size. Now the entire process—from stamping 

 

the raw material to the finished part—was com

 

 

pleted in minutes (instead of hours or days) just by 

 

configuring these machines into a small cell and hav

 

 

ing them serviced by a single person. The small scale 

 

and quick turnaround now made it possible to pro

 

 

duce these parts just in time, eliminating the need to 

 

produce and store inventory.18 

 

Another example of a moonshine innovation 

 

concerned the process for loading seats onto a plane 

 

during assembly. Historically, this was a cumber

 

 

some process. After the seats arrived at Boeing from 

 

a supplier, wheels were attached to each seat, and 

 

then the seats were delivered to the factory floor in a 

 

large container. An overhead crane lifted the con

 

 

tainer up to the level of the aircraft door. Then the 

 

seats were unloaded and rolled into the aircraft, be

 

 

fore being installed. The process was repeated until 

 

all of the seats had been loaded. For a single-aisle 

 

plane, this could take twelve hours. For a wide-

 

bodied jet, it would take much longer. A moonshine 

 

team adapted a hay elevator to perform the same job 

 

(see Exhibit 5). It cost a lot less, delivered seats 

 

quickly through the passenger door, and took just 

 

two hours, while eliminating the need for cranes.19 

 

Multiply the examples given here, and soon you 

 

have a very significant impact on production costs: A 

 

drill machine was built for 5% of the cost of a full-

 

scale machine from Ingersoll-Rand. Portable routers 

 

were built for 0.2% of the cost of a large fixed router. 

 

One process that took 2,000 minutes for a 100-part 

 

order (20 minutes per part because of setup, ma

 

 

chining, and transit) now takes 100 minutes (1 

 

minute per part). Employees building 737 floor 

 

CIO PART 5 Cases in Strategic Management 

 

Exhibit 5 

 

The Converted Hay Loader at Work 

 

Source: Copyright © Boeing. All rights reserved. 

 

beams reduced labor hours by 74%, increased inventory 

turns from two to eighteen per year, and reduced 

manufacturing space by 50%. Employees 

building the 777 tail cut lead time by 70% and reduced 

space and work in progress by 50%. Production 

of parts for landing gear support used to take 

thirty-two moves from machine to machine and required 

ten months; production now takes three 

moves and twenty-five days.20 

 

In general, Boeing found that it was able to produce 

smaller lots of parts economically, often from 

machines that it built itself, which were smaller and 

cost less than the machines available from outside 

vendors. In turn, these innovations enabled Boeing 

to switch to just-in-time inventory systems and 

reduce waste. Boeing was also able to save on space. 

By eliminating large production machinery at its 

Auburn facility, replacing much of it with smaller, 

more flexible machines, Boeing was able to free up 

 

1.3 million square feet of space and sold seven 

buildings.21 

In addition to moonshine teams, Boeing adopted 

other process improvement methodologies, using 

 

them when deemed appropriate. Six Sigma quality 

improvement processes are widely used within Boeing. 

The most wide-reaching process change, however, 

was the decision to switch from a static assembly 

line to a moving line. In traditional aircraft 

manufacture, planes are docked in angled stalls. 

Ramps surround each plane, and workers go in and 

out to find parts and install them. Moving a plane to 

the next workstation is a complex process. The aircraft 

has to be down-jacked from its workstation, a 

powered cart brought in, and the aircraft towed to 

the next station, where it is then jacked up. This can 

take two shifts. A lot of time is wasted bringing parts 

to a stall and moving a plane from one stall to the 

next. 

 

In 2001, Boeing introduced a moving assembly 

line into its Renton plant near Seattle, which manufactures 

the 737 (see Exhibit 6). With a moving line, 

each aircraft is attached to a "sled" that rides a magnetic 

strip embedded in the factory floor, pulling the 

aircraft at a rate of 2 inches per minute, moving past 

a series of stations where tools and parts arrive at the 

moment needed, allowing workers to install the 

 

proper assemblies. The setup eliminates wandering 

for tools and parts, as well as expensive tug pulls or 

crane lifts (just having tools delivered to workstations, 

rather than having workers fetch them, was 

found to save twenty to forty-five minutes on every 

shift). Preassembly tasks are performed on feeder 

lines. For example, inboard and outboard flaps are 

assembled on the wing before it arrives for joining to 

the fuselage.22 

 

Like a Toyota assembly line, the moving line can 

be stopped if a problem arises. Lights are used to indicate 

the state of the line. A green light indicates a 

normal work flow; the first sign of a stoppage brings 

a yellow warning light; and, if the problem isn't 

solved within fifteen minutes, a purple light indicates 

that the line has stopped. Each work area and 

feeder line has its own lights, so there is no doubt 

where the problem is.23 

 

The cumulative effects of these process innovations 

have been significant. By 2005, assembly time 

for the 737 had been cut from twenty-two days to 

just eleven days. In addition, work-in-progress in-

 

Exhibit 6 

The Moving Line 

 

Source:Copyright© Boeing. All rights reserved. 

 

CASE 1 Boeing Commercial Aircraft: Comeback? C11 

 

ventory had been reduced by 55 percent and stored 

inventory by 59 percent.24 By 2006, all of Boeing's 

production lines except that for the 747 had shifted 

from static bays to moving lines. The 747 was expected 

to shift to moving line when Boeing started 

production of the 747-8. 

 

The Super-Jumbo Decisions 

 

In the early 1990s, Boeing and Airbus started to con

 

 

template new aircraft to replace Boeing's aging 747. 

 

The success of the 747 had given Boeing a monopoly 

 

in the market for very large jet aircraft, making the 

 

plane one of the most profitable in the jet age. But 

 

the basic design dated back to the 1960s, and some 

 

believed there might be sufficient demand for a 

 

super-jumbo aircraft with as many as 900 seats. 

 

Initially, the two companies considered establish

 

 

ing a joint venture to share the costs and risks associ

 

 

ated with developing a super-jumbo aircraft, but 

 

Boeing withdrew in 1995, citing costs and uncertain 

 

demand prospects. Airbus subsequently concluded 

 

that Boeing was never serious about the joint venture, 

 

C12 PARTS Cases in Strategic Management 

 

and the discussions were nothing more than a ploy to 

keep Airbus from developing its own plane.25 

 

After Boeing withdrew, Airbus started to talk 

about offering a competitor to the 747 in 1995. The 

plane, then dubbed the A3XX, was to be a super 

jumbo with capacity for over 500 passengers. Indeed, 

Airbus stated that some versions of the plane might 

carry as many as 900 passengers. Airbus initially estimated 

that there would be demand for some 1,400 

planes of this size over twenty years, and that development 

costs would total around $9 billion (estimates 

ultimately increased to some $15 billion). 

Boeing's latest 747 offering—the 747-400—could 

carry around 416 passengers in three classes. 

 

Boeing responded by drafting plans to develop 

new versions of the 747 family—the 747-500X and 

the 747-600X. The 747-600X was to have a new 

(larger) wing and a fuselage almost 50 feet longer 

than that of the 747-400, carry 550 passengers in 

three classes, and have a range of 7,700 miles. The 

smaller 747-500X would carry 460 passengers in 

three classes and have a range of 8,700 miles. 

 

After taking a close look at the market for a 

super-jumbo replacement to the 747, in early 1997 

Boeing announced that it would not proceed with 

the program. The reasons given for this decision included 

the limited market and high development 

costs, which at the time were estimated to be $7 billion. 

There were also fears that the wider wing span 

of the new planes would mean that airports would 

have to redesign some of their gates to take the aircraft. 

Boeing, McDonnell Douglas (prior to the 

merger with Boeing), and the major manufacturers 

of jet engines all forecast demand for about 500 to 

750 such aircraft over the next twenty years. Airbus 

alone forecast demand as high as 1,400 aircraft. Boeing 

stated that the fragmentation of the market due 

to the rise of "point-to-point" flights across oceans 

would limit demand for a super jumbo. Instead of 

focusing on the super-jumbo category, Boeing stated 

that it would develop new versions of the 767 and 

777 aircraft that could fly up to 9,000 miles and 

carry as many as 400 passengers. 

 

Airbus, however, continued to push forward with 

plans to develop the A3XX. In December 2000, with 

more than fifty orders in hand, the board of EADS, 

Airbus's parent company, approved development of 

the plane, which was now dubbed the A380. Development 

costs at this point were pegged at $12 billion, 

and the plane was forecast to enter service in 

 

2006 with Singapore Airlines. The A380 was to have 

two passenger decks, more space per seat, and wider 

aisles. It would carry 555 passengers in great comfort, 

something that passengers would appreciate on 

long transoceanic flights. According to Airbus, the 

plane would carry up to 35% more passengers than 

the most popular 747-400 configuration, yet cost per 

seat would be 15 to 20% lower due to operating efficiencies. 

Concerns were raised about turnaround 

time at airport gates for such a large plane, but Airbus 

stated that dual-boarding bridges and wider 

aisles meant that turnaround times would be no 

more than those for the 747-400. 

 

Airbus also stated that the A3 80 was designed to 

operate on existing runways and within existing 

gates. However, London's Heathrow airport found 

that it had to spend some $450 million to accommodate 

the A380, widening taxiways and building a 

baggage reclaim area for the plane. Similarly, eighteen 

U.S. airports had reportedly spent some $1 billion 

just to accommodate the A380.26 

 

The 787 

 

While Airbus pushed forward with the A380, in 

March 2001 Boeing announced the development of 

a radically new aircraft. Dubbed the Sonic Cruiser, 

the plane would carry 250 passengers 9,000 miles 

and fly just below the speed of sound, cutting one 

hour off transatlantic flights and three hours off 

transpacific flights. To keep down operating costs, 

the sonic cruiser would be built out of low-weight 

carbon fiber "composites." Although the announcement 

created considerable interest in the aviation 

community, in the wake of the recession that hit the 

airline industry after September 11, 2001, both Boeing 

and the airlines became considerably less enthusiastic. 

In March 2002, the program was canceled. 

Instead, Boeing said that it would develop a more 

conventional aircraft using composite technology. 

The plane was initially known as the 7E7, with the E 

standing for efficient (the plane was renamed the 787 

in early 2005). 

 

In April 2004, the 7E7 program was formally 

launched with an order for fifty aircraft worth $6 billion 

from All Nippon Airlines of Japan. It was the 

largest launch order in Boeing's history. The 7E7 was 

a twin-aisle, wide-bodied, two-engine plane designed 

to carry 200 to 300 passengers up to 8,500 

miles, making the 7E7 well suited for long-haul, 

point-to-point flights. The range exceeded that of all 

 

but the longest range plane in the 777 family, and the 

7E7 could fly 750 miles more than Airbus's closest 

competitor, the mid-sized A330-200. With a fuselage 

built entirely out of composites, the aircraft was 

lighter and would use 20% less fuel than existing aircraft 

of comparable size. 

 

The plane was also designed with passenger comfort 

in mind. The seats would be wider, as would the 

aisles, and the windows were larger than in existing 

aircraft. The plane would be pressurized at an altitude 

of 6,000 feet, as opposed to 8,000 feet, which is 

standard industry practice. Airline cabin humidity 

was typically kept at 10% to avoid moisture buildup 

and corrosion, but composites don't corrode, so humidity 

would be closer to 20 to 30%.27 

 

Initial estimates suggested that the jet would cost 

some $7 to $8 billion to develop and enter service in 

2008. Boeing decided to outsource more work for 

the 787 than on any other aircraft to date. Some 35% 

of the plane's fuselage and wing structure would be 

built by Boeing. The trio of Japanese companies that 

worked on the 767 and 777—Mitsubishi Heavy Industries, 

Kawasaki Heavy Industries, and Fuji Heavy 

Industries—would build another 35%, and some 

26% would be built by Italian companies, particularly 

Alenia.28 For the first time, Boeing asked its major 

suppliers to bear some of the development costs 

for the aircraft. 

 

The plane was to be assembled at Boeing's wide-

bodied plant in Everett, Washington. Large subassemblies 

were to be built by major suppliers and then 

shipped to Everett for final assembly. The idea was to 

"snap together" the parts in Everett in three days, cutting 

down on total assembly time. To speed up transportation, 

Boeing would adopt air freight as its major 

transportation method for many components. 

 

Airbus's initial response was to dismiss Boeing's 

claims of cost savings as inconsequential. They 

pointed out that even if the 787 used less fuel than 

the A330, that was equivalent to just 4% of total operating 

costs.29 However, even by Airbus's calculations, 

as fuel prices started to accelerate, the magnitude 

of the savings rose. Moreover, Boeing quickly 

started to snag some significant orders for the 787. 

In 2004, Boeing booked 56 orders for the 787, and in 

2005, some 232 orders. Another 85 orders were 

booked in the first nine months of 2006 for a running 

total of 373—well beyond the breakeven point. 

 

In December 2004, Airbus announced that it 

would develop a new model, the A350, to compete 

 

CASE 1 Boeing Commercial Aircraft: Comeback? C13 

 

directly with the 787. The planes were to be long-

haul, twin-aisle jets, seating 200 to 300 passengers, 

and constructed of composites. The order flow, however, 

was slow, with airlines complaining that the 

A350 did not match the Boeing 787 on operating efficiency, 

range, or passenger comfort. Airbus went back 

to the drawing board and, in mid-2006, announced a 

new version of the A350, the A350 XWB (for "extrawide 

body"). Airbus estimates that the A350 XWB 

will cost $10 billion to develop and enter service in 

2012, several years behind the 787. The two-engine 

A350 XWB will carry between 250 and 375 passengers 

and fly up to 8,500 miles. The largest versions of 

the A350 XWB will be competing directly with the 

Boeing 777, not the 787. Like the 787, the A350 XWB 

will be built primarily of composite materials. The 

extra-wide body is designed to enhance passenger 

comfort. To finance the A350 XWB, Airbus stated 

that it would probably seek launch aid from Germany, 

France, Spain, and the United Kingdom, all 

countries where major parts of Airbus are based.30 

 

Trade Tensions 

 

It is impossible to discuss the global aerospace industry 

without touching on trade issues. Over the 

last three decades, both Boeing and Airbus have 

charged that their competitor benefited unfairly 

from government subsidies. Until 2001, Airbus functioned 

as a consortium of four European aircraft 

manufacturers: one British (20.0% ownership stake), 

one French (37.9% ownership), one German (37.9% 

ownership), and one Spanish (4.2% ownership). In 

the 1980s and early 1990s, Boeing maintained that 

subsidies from these nations allowed Airbus to set 

unrealistically low prices, to offer concessions and 

attractive financing terms to airlines, to write off development 

costs, and to use state-owned airlines to 

obtain orders. According to a study by the U.S. Department 

of Commerce, Airbus received more than 

$13.5 billion in government subsidies between 1970 

and 1990 ($25.9 billion if commercial interest rates 

are applied). Most of these subsidies were in the 

form of loans at below-market interest rates and tax 

breaks. The subsidies financed research and development 

and provided attractive financing terms for 

Airbus's customers. Airbus responded by pointing 

out that Boeing had benefited for years from hidden 

 

U.S. government subsidies, particularly Pentagon 

R&D grants. 

C14 PART 5 Cases in Strategic Management 

 

In 1992, the two sides appeared to reach an 

agreement that put to rest their long-standing trade 

dispute. The 1992 pact, which was negotiated by the 

European Union (EU) on behalf of the four member 

states, limited direct government subsidies to 33% of 

the total costs of developing a new aircraft and specified 

that such subsidies had to be repaid with interest 

within seventeen years. The agreement also limited 

indirect subsidies, such as government-supported 

military research that has applications to commercial 

aircraft, to 3% of a country's annual total commercial 

aerospace revenues or 4% of commercial aircraft 

revenues of any single company in that country. Although 

Airbus officials stated that the controversy 

had now been resolved, Boeing officials argued that 

they would still be competing for years against subsidized 

products. 

 

The trade dispute heated up again in 2004 when 

Airbus announced the first version of the A350 to 

compete against Boeing's 787. What raised a red flag 

for the U.S. government was a sign from Airbus that 

it would apply for $1.7 billion in launch aid to help 

fund the development of the A350. As far as the 

United States was concerned, this was too much. In 

late 2004, U.S. Trade Representative Robert Zoellick 

issued a statement formally renouncing the 1992 

agreement and calling for an end to launch subsidies. 

According to Zoellick, 

 

Since its creation 35 years ago, some Europeans 

have justified subsidies to Airbus as necessary 

to support an infant industry. If that rationalization 

were ever valid, its time has long 

passed. Airbus now sells more large civil aircraft 

than Boeing. 

 

Zoellick went on to claim that Airbus has received 

some $3.7 billion in launch aid for the A380 plus another 

$2.8 billion in indirect subsidies, including 

$1.7 billion in taxpayer-funded infrastructure improvements, 

for a total of $6.5 billion. 

 

Airbus shot back that Boeing too continued to 

enjoy lavish subsidies and that the company had received 

some $12 billion from NASA to develop technology, 

much of which had found its way into commercial 

jet aircraft. The Europeans also contended 

that Boeing would receive as much as $3.2 billion in 

tax breaks from Washington State, where the 787 is 

to be assembled, and more than $1 billion in loans 

from the Japanese government to three Japanese 

suppliers, who will build over one-third of the 787. 

 

Moreover, Airbus was quick to point out that a trade 

war would not benefit either side and that Airbus 

purchased some $6 billion a year in supplies from 

companies in the United States. 

 

In January 2005, both the United States and the 

EU agreed to freeze direct subsidies to the two aircraft 

makers while talks continued. However, in May 

2005 news reports suggested, and Airbus confirmed, 

that the jet maker had applied to four EU governments 

for launch aid for the A3 50 and that the 

British government would announce some $700 million 

in aid at the Paris Air Show in mid-2005. Simultaneously, 

the EU offered to cut launch aid for the 

A350 by 30%. Dissatisfied, the U.S. side decided that 

the talks were going nowhere, and on May 31 the 

United States formally filed a request with the World 

Trade Organization (WTO) for the establishment of 

a dispute resolution panel to resolve the issues. The 

EU quickly responded, filing a countersuit with the 

WTO claiming that U.S. aid to Boeing exceeded 

the terms set out in the 1992 agreement. The dispute 

is currently before the WTO.31 

 

Although the decision to scrap the original design 

of the A350 took some of the heat out of the 

dispute, Airbus is expected to ask for launch aid for 

the redesigned A350 XWB. 

 

The Next Chapter 

 

Huge financial bets have been placed on very different 

visions of the future of airline travel: Airbus with 

the A380 and Boeing with the 787. Airbus has 

hedged its bets by announcing the A350 XWB, but 

will this be too little too late? Moreover, there are 

signs of production turmoil at Airbus. Orders for the 

A380 have stalled. In mid-2006, the company announced 

that deliveries for the aircraft would be delayed 

by six months while the company dealt with 

"production issues" arising from problems installing 

the wiring bundles in the A380. Estimates suggest 

that the delay would cost Airbus some $2.6 billion 

over the next four years.32 Within months, Airbus 

had revised the expected delay to eighteen months 

and stated that the number of A380s it now needed 

to sell to break even had increased from 250 to 420 

aircraft. The company also stated that due to production 

problems, it would be able to deliver only 84 

A380 planes by 2010, compared to an original estimate 

of 420.33 In response, several significant launch 

customers for the A380 were said to be reconsidering 

 

their purchase decisions. United Parcel Service, 

which has 10 A380 cargo planes on order, was reportedly 

considering switching to the Boeing 747-8, 

Boeing's latest offering in the venerable 747 family. 

 

Boeing quietly launched the 747-8 program in 

November 2005. This plane will be a completely redesigned 

version of the 747 and will incorporate 

many of the technological advances developed for 

the 787, including significant use of composites. It 

will be offered in both a freighter and an intercontinental 

passenger configuration that will carry 467 

passengers in a three-seat configuration and have a 

range of 8,000 miles (the 747-400 can carry 416 passengers). 

The 747-8 will also use the fuel-efficient 

engines developed for the 787 and will have the same 

cockpit configuration as the 737, 777, and 787. Development 

costs are estimated to be around $4 billion. 

By October 2006, Boeing had orders for forty-

four 787-8 freighters, but none for passenger planes. 

However, some analysts speculated that with the 

A380 mired in delays, the 747-8 passenger configuration 

might begin to garner more orders. 

 

Not all is smooth sailing at Boeing. The company 

experienced some problems with suppliers for the 

787, who have fallen behind schedule designing 

some components for the project. As of late 2006, 

Boeing was insisting that the 787 was still on schedule. 

Some analysts, however, are concerned that this 

might be a sign of things to come and that the complexity 

associated with coordinating a diverse base of 

suppliers might lead to delays in the 787. 

 

Complicating issues, both Airbus and Boeing 

have been through some changes in key management 

over the last few years. At Boeing, CEO Phil Condit 

resigned in late 2003, after it was revealed that the 

company's CFO, Mike Sears, had hired a key Department 

of Defense procurement officer in return for 

her backing of a huge order for air force tankers 

based on the 767. Sears was subsequently prosecuted 

and sent to jail. The Sears scandal was only the latest 

in a number that Boeing executives had become embroiled 

in during the early 2000s. Condit's resignation 

was widely taken to indicate that the board felt 

that a new CEO was needed to clean house. Condit 

was replaced by Harry Stonecipher, who was CEO of 

McDonnell Douglas when it was acquired by Boeing 

and later president of Boeing. Stonecipher resigned 

fifteen months later, when it was revealed that he had 

had an affair with a subordinate and communicated 

with her using the company's email service. Stoneci-

 

CASE 1 Boeing Commercial Aircraft: Comeback? C15 

 

pher was replaced by Jim McNerney, who moved to 

 

Boeing from the CEO position at 3M. Prior to join

 

 

ing 3M, McNerney had run the aircraft engine busi

 

 

ness at General Electric. McNerney was widely 

 

viewed as a skilled manager who had brought the op

 

 

erating discipline that GE is famous for to 3M. He 

 

was expected to do the same at Boeing, pushing the 

 

company to continue to pursue various productivity 

 

initiatives, such as lean production, Six Sigma 

 

processes, and global sourcing. 

 

At Airbus, following the announcement of the 

 

delay in A380 production, there was pressure on 

 

Noel Forgeard, the CEO of EADS, Airbus's parent 

 

company, to resign. Forgeard refused, although Gus

 

 

tav Humbert, the CEO of Airbus, did offer to step 

 

down. After a three-week crisis, the board of EADS 

 

took matters into its own hands and fired both 

 

Forgeard and Humbert. They were replaced by Louis 

 

Gallois, a Frenchman who once ran an aerospace 

 

company that was acquired by EADS, and Christian 

 

Streiff, the former number 2 at Saint Gobain, the 

 

French glassmaker. 

 

With new management in place at both compa

 

 

nies, the focus is on the unfolding competitive battle. 

 

Can Airbus make money on the A380, and, if it does, 

 

will it gain a monopoly that rivals Boeing's 747 dy

 

 

nasty? Will the 787 live up to its promise and be

 

 

come the right plane for a new era of global travel? 

 

Can Airbus come back at Boeing with its new ver

 

 

sion of the A350, the A350 XWB? And what of the 

 

ongoing trade dispute? How will this impact on the 

 

long-running dog fight between the two companies? 

 

ENDNOTES 

 

1. http://www.boeing.com, accessed September 2006. 

2. http://www.airbus.com/en, accessed September 2006. 

3. 

J. Palmer, "Big Bird," Barren's (December 19, 2005): 25-29; 

http://www.yeald.com/Yeald/a/33941/both_a380_and_787_ 

have_bright_futures.html. 

4. 

G. J. Steven, "The Learning Curve: from Aircraft to Spacecraft" 

Management Accounting (May 1999): 64-66. 

5. 

D. Gates, "Boeing 7E7 Watch: Familiar Suppliers Make Short 

List," Seattle Times. 

6. 

The figures are from the International Airline Travelers Association 

(IATA). 

7. 

IATA, "2006 Loss Forecast Drops to US$1.7 Billion," Press Release, 

August 31,2006. 

8. 

"Turbulent Skies: Low Cost Airlines," Economist (July 10, 2004): 

68-72; "Silver Linings, Darkening Clouds," Economist (March 27, 

2004): 90-92. 

9. Data from the Air Transport Association at www.airlines.org. 

10. IATA, "2006 Loss Forecast Drops to US$1.7 Billion." 

11. Boeing, Current Market Outlook, 2006, http://www.boeing.com. 

 

12. http://www.airbus.com/en/myairbus/global_market_forecast.html. 

    • 10 years ago
    After reading “Boeing Commercial Aircraft” case study (attached file). Complete a SWOT analysis on the case.
    NOT RATED

    Purchase the answer to view it

    blurred-text
    • attachment
      boeing_commercial_aircraft_a.txt.doc