Services Pre PNM Assignment
PROC 5870 Services Pre PNM Exercise Due Week 8 TEMPLATE GUIDE
General comments:
This template was developed to assist you in working through the exercise addressing the concepts and cost elements associated with the Services Pre-PNM assignment. You will find the proposed and objective portions of the total cost element table completed for you as well as entries in the tables addressing the individual cost elements. Make sure you look at each one carefully to see what is missing and need to complete the optimistic and pessimistic positions . To save some effort, in the total cost area under III you only need to plug in the dollars you would propose for the pessimistic – you can explain the rationale in the supporting narrative for each of the cost elements, you do not have to present the buildup in the table. (This also allows the table to fit on the page!). Remember there are four positions presented in this pre-PNM: the contractor’s proposed, the objective/target where we think we will end up, the optimistic if everything goes our way and the pessimistic worst case scenario.
You may answer the “questions for thought and comment” outside of the PNM document if you wish, or because of the manner in which Mr. Bitner (course developer) presents the in the case, you are welcome to address the questions where they appear in the pre-PNM discussion. All the questions I require you to address are listed in this template in the pertinent areas so if you just work from this template you will cover everything you need to complete. All three assignments are included in this template –Assignment 1 is the pre PNM and questions, Assignments 2 and 3 following the PNM. Throughout the template I have added some extra reminders and/or notes to help you. In exercise 3 for example you are provided the formulas and a table to use for calculating the final CPIF based on an underrun (undertarget cost).
Remember from your first PNM there are cases when the target (most likely objective) and pessimistic positions could be the same; likewise, sometimes the proposed and objective are the same, or your optimistic is the same as the objective. To save time on this case, assume any allowed questioned or unsupported areas of the contractor proposal could be supported and/or defended by the contractor at the prices proposed for a pessimistic position. Remember however, if there had been unallowed costs these should not be part of any of your negotiating positions and would never be permitted.
In the fee area you are not asked to present a weighted guideline analysis but know that in practice you would actually include that calculation to support your fee position. Likewise you are not asked to work through a capital cost of money. For both you may just accept what is provided as sufficient.
Be sure to remove my comments as you write your narrative.
This project is worth 150 or the total 1,000 course points – you see noted in this template the point value for each area.
===============================================================================
SUBJECT: PRELIMINARY PRICE NEGOTIATION MEMORANDUM (PRE-PNM)
I. OVERVIEW (6 POINTS)
Enter narrative following the format of the PNM – remember key things about the acquisition and write it so that someone who doesn’t know anything about the action has a good understanding of what you plan to do and why. Look at the score sheet from your first PNM to help you hit the highlights.
II. COST ANALYSIS SUMMARY (2 POINTS)
A. The contractor’s proposal price is $____________ The government objective is __________ with an optimistic of $___________ and pessimistic of $___________ (as stated below). __________ The objective determinations were based on ____________________________. See Section IV to see how these objectives were determined.
III. TOTAL COSTS: (5 POINTS)
A.
IV. PARTICULARS AND FACT FINDING
Comment: look at the summary table in developing the particulars and use them as presented. Frequently in negotiations we find there is nothing wrong with the positions but the numbers are different due to rounding – I have created a bit of that in this exercise. Just use the numbers provided.
For the database analyst II I want you to use some creative writing to come up with the objective I have provided of 4,160 hours reflected in the summary table above. The point here is to understand that even when DCAA and the technical personnel provide input ultimately the Contracting Officer has to document and then negotiation to what they believe is best. Reflect on concepts you have learned in this course and come up with a plausible reason for this position.
A. LABOR: (8 POINTS)
i. ON-SITE:
1. Hours: The contractor proposed 8,320 hours per year for their analyst (application systems, programmer and database), 34,944 hours for computer support/operations and 17,472 for systems administration.
a. Questioned and or Unsupported Hours -.
i. Optimistic –
ii. Objective/Target (Most Likely to Negotiate) –
iii. Pessimistic -
2. Labor Rates:
PROPOSED
Questioned and or Unsupported Rates: .
OPTIMISTIC
a. Optimistic:
OJECTIVE/TARGET (MOST LIKELY)
b. Objective/Target (Most Likely to Negotiate
PESSIMISTIC
c. Pessimistic:
3. Costs: Per the hours and labor rates given above, below please find the total costs for all years.
Thoughts and Comments (3 POINTS FOR EACH QUESTION 9 POINTS)
1. In doing market research to assess the labor market and wage/salary trends for computer/information technology support, you noticed that support is increasingly being provided on a remote basis (vice on-site), thanks to improving technology. Being on-site to provide support is not as important as it used to be. How could you use that information?
2. What sources could you go to conduct this market research on the labor market?
3. (There are several sources of wage rate escalation factors. A widely-accepted source is Data Resources, Inc. (DRI). DRI rates are privately produced escalation factors based in part on BLS indices for material and labor, such as the Consumer Price Index and the PPI. DRI incorporates economic and social variables into their economic forecast models. DCAA recommended use of DRI escalation. The contractor proposes using DRI plus .5% due to the tight labor market. What would you do to resolve the DCAA recommendation and the proposed addition of .5% escalation?
ii. ON-CALL SUPPORT: (5 POINTS)
1. Hours: The contractor proposed the following hours per year based upon 1 person at each site.
a. Questioned and or Unsupported:
i. Optimistic –
.
ii. Objective/Target (Most Likely to Negotiate)
iii. Pessimistic –.
2. Labor Rates:
|
Position |
PROPOSED |
||
|
|
1999 Rate |
2000 Rate |
2001 Rate |
|
Applics Sys Anal II |
$ 38.10 |
$ 40.27 |
$ 42.53 |
|
Progr Analyst II |
$ 39.77 |
$ 42.04 |
$ 44.39 |
|
Database Anal/Prog II |
$ 25.13 |
$ 26.56 |
$ 28.05 |
a. Questioned and or Unsupported Rates:
.
b. Optimistic :
c. Objective/Target (Most Likely to Negotiate )
d. Pessimistic :
3. Costs: Per the hours and labor rates given above, below please find the total costs.
|
Position |
PROPOSED |
||
|
|
1999 Total |
2000 Total |
2001 Total |
|
Applics Sys Anal II |
$ 27,432.00 |
$ 33,826.80 |
$ 40,828.80 |
|
Progr Analyst II |
$ 33,406.80 |
$ 40,358.40 |
$ 47,941.20 |
|
Database Anal/Prog II |
$ 18,093.60 |
$ 22,310.40 |
$ 26,928.00 |
|
Yearly Totals |
$ 78,932.40 |
$ 96,495.60 |
$ 115,698.00 |
|
3 Year Totals |
|
|
$ 291,126.00 |
Thoughts and Comments: (3 POINTS EACH 21 POINTS TOTAL)
1. What quantitative analysis methods could you suggest to better assess whether there will be an increasing occurrence of failures?
2. What is the turnover rate for support personnel? If it is high, is learning starting all over again with new personnel? Why the high turnover? Is the contractor paying competitive wages/salaries? If there is high turnover and you negotiate "hard" to minimize the number of personnel, how could this impact performance risk?
3. In what ways could we DCAA support for our analysis of turnover? What specific request would you make to them? What is an example of a request that would be too general?
4. Why does introducing incentives on cost performance make sense in this situation?
5. What are the possibilities if we stated the requirement only in terms of the 2% downtime goal? Would the contractor have more freedom in how support was accomplished?
6. Would performance incentives be more or less motivating if requirements were restated this way? How could award fee be used? FPIF?
7. Discuss the possibility of endangering performance by overemphasizing cost control through incentives.
B. FRINGE: Make sure you comment on what DCAA said! (3 POINTS)
Thoughts and Comments: (3 POINTS EACH 21 POINTS TOTAL)
1. What costs are typically included in fringe?
2. What is one reason that fringe would specifically be identified in the proposal, as opposed to just being included as part of the overhead?
3. Where could you find out what the Dept of Labor minimum wages and fringe are for in your area?
4. Discuss why contracting officer involvement in fringe issues differs significantly based on whether contract administration has been delegated to DCMC or not.
5. Where could you go to get information on fringe costs? Allowability policy? Calculating an indirect cost? DCAA guidance?
6. What are the implications of whether this contract is CAS covered or not?
7. If the company experienced a significant decline in its business base and workforce, how might this impact its cost of fringe benefits per labor hour?
C. OVERHEAD: .For the overhead calculation both on site and on call labor dollars are added together from the total cost summary sheet and reflects both on-site and on call labor. (3 POINTS)
|
|
1999 Proposed Total |
2000 Proposed Total |
2001 Proposed Total |
Proposed Total Costs |
|
TOTAL LABOR COST |
$ 2,337,503 |
$ 2,387,308 |
$ 2,520,996 |
$ 7,166,873 |
|
OVERHEAD |
35% |
50% |
50% |
|
|
OVERHEAD TOTALS |
$ 790,499 |
$ 1,193,654 |
$ 1,260,498 |
$ 3,244,651 |
Thoughts and Comments: (3 POINTS EACH 9 POINTS TOTAL)
1. What costs are typically included in overhead?
2. Discuss common indirect cost rate misunderstanding; i.e., assessing a rate as too high or too low without understanding the composition and costs included in its pool and base.
3. If a company is doing business predominantly with Government and its Government business is declining, what would likely happen to its overhead rate?
D. MATERIAL AND PARTS: (5 POINTS)
Presented in Proposal
|
Material Proposed |
1999 Rate |
1999 |
2000 Rate |
2000 |
2001 Rate |
2001 |
Totall |
|
Scheduled |
|
$200,000. |
0.941 |
$225,816.00 |
0.930 |
$204,514.00 |
$630,330.00 |
|
Unscheduled |
1.261 |
$151,320 |
1.261 |
$190,815 |
1.284 |
$245,082 |
$587,217 |
|
Minor enhancements |
1.358 |
$40,740 |
1.358 |
$55,325 |
1.383 |
$76,525 |
$172,590 |
|
Miscellaneous |
1.067 |
$8,536 |
1.067 |
$9,108 |
1.087 |
$9,898 |
$27,542 |
|
TOTAL MATERIAL |
|
$400,596 |
|
$481,063 |
|
$536,020 |
$1417,679 |
Material Growth Factors:
Be sure to explain what the escalations are based upon also note what was presented in the proposal and what was cited in the DCAA report as proposed growth factors… what do you think happened here as they are not the same – comment in your PNM.
The following summarizes the proposed and recommended growth factors for materials supporting unscheduled maintenance, minor system enhancements, and miscellaneous use:
|
Material Growth Factors - Proposed |
|||
|
|
1999 |
2000 |
2001 |
|
Unscheduled |
1.30 |
1.30 |
1.30 |
|
Minor Enhancements |
1.40 |
1.40 |
1.40 |
|
Miscellaneous |
1.10 |
1.10 |
1.10 |
|
Material Growth Factors - Govt Objective |
|||
|
|
1999 |
2000 |
2001 |
|
Unscheduled |
1.00 |
1.05 |
1.10 |
|
Minor Enhancements |
1.00 |
1.00 |
0.25 |
|
Miscellaneous |
1.05 |
1.05 |
1.05 |
|
Material |
1999 Optimistic Rate |
1999 Optimistic $ |
2000 Optimistic . Rate |
2000 Optimistic $ |
2001 Optimistic Rate |
2001 Optimistic $ |
Optimistic Total $ |
|
Scheduled |
|
|
|
|
|
|
|
|
Unscheduled |
1.00 |
|
1.05 |
|
1.10 |
|
|
|
Minor enhancements |
1.00 |
|
1.00 |
|
0.25 |
|
|
|
Miscellaneous |
1.05 |
|
1.05 |
|
1.05 |
|
|
|
TOTAL MATERIAL |
|
|
|
|
|
|
|
i. Optimistic:
|
Material |
1999 Target/Objective Most Likely to Negotiate Rate |
1999 Target/Objective Most Likely to Negotiate $ |
2000 Target/Objective Most Likely to Negotiate Rate |
2000 Target/Objective Most Likely to Negotiate $ |
2001 Target/Objective Most Likely to Negotiate Rate |
2001 Target/Objective Most Likely to Negotiate $ |
Target/Objective Most Likely to Negotiate Total $ |
|
Scheduled |
|
$ 200,000 |
|
$225,816 |
|
$ 204,514 |
|
|
Unscheduled |
|
$ 116,400 |
|
$118,553 |
|
$ 128,844 |
|
|
Minor enhancements |
|
$ 29,100 |
|
$28,227 |
|
$ 6,972 |
|
|
Miscellaneous |
|
$ 8,148 |
|
$8,299 |
|
$ 8,609 |
|
|
TOTAL MATERIAL |
|
$ 353,648 |
|
$380,895 |
|
$ 348,939 |
|
ii. Objective/Target (Most Likely to Negotiate):
Locate the rates to complete the table above from the cost summary at the beginning of the PNM!
|
Material |
1999 Pessimistic Rate |
1999 Pessimistic $ |
2000 Pessimistic Rate |
2000 Pessimistic $ |
2001 Pessimistic Rate |
2001 Pessimistic $ |
Pessimistic Total $ |
|
Scheduled |
|
|
|
|
|
|
|
|
Unscheduled |
|
|
|
|
|
|
|
|
Minor enhancements |
|
|
|
|
|
|
|
|
Miscellaneous |
|
|
|
|
|
|
|
|
TOTAL MATERIAL |
|
|
|
|
|
|
|
iii. Pessimistic:
E. GENERAL AND ADMINISTRATIVE (G & A) COSTS: (2 POINTS)
You may enter a table here or just discuss the proposed, objective, optimistic and pessimistic rates.
Thoughts and Comments: (3 POINTS)
1. What costs are typically included in G&A?
F. TARGET FEE: The proposed fee given by McGhee is 11% (pessimistic outcome). We will offer 9% (optimistic and most likely to negotiate target) based on the calculated weighted guidelines. (5 POINTS)
Thoughts and Comments: (3 POINTS EACH 12 POINTS TOTAL)
1. Why is it very likely that a service oriented company would not propose Facilities Capital Cost of Money?
2. Discuss how the Weighted Guidelines could be used to develop a minimum and maximum fee; and how with share ratios pessimistic and optimistic costs could be calculated.
3. Discuss how the minimum and maximum fee could be calculated given share ratios and optimistic/pessimistic costs.
4. Discuss how the dollar amount of potential share (over or under) must be enough to provide effective incentive.
G. CPIF SHARE RATIOS: (2 POINTS)
.
i. Optimistic
ii. Objective/Target (Most Likely to Negotiate):
iii. Pessimistic:
Thoughts and Comments: (3 POINTS EACH 12 POINTS TOTAL)
1. It may be worthwhile to review the difference between the proposed 90/10 and 70/30 ratios. Why does it make sense that the
contractor would propose 90/10 given its anticipation of future breakdowns?
2. Prompt clarifying discussion on why the most likely causes of over target costs are a significant factor in determining the over target share.
3. Ask what yourself questions you would raise as the contracting rep on an IPT doing an acquisition strategy planning session.
4. Discuss where you would go for guidance/policy on incentive contracts.
H. OPTIMISTIC/PESSIMISTIC COST: Please see the optimistic/pessimistic costs given above. (2 POINTS)
i. Optimistic
ii. Objective/Target (Most Likely to Negotiate):
.
iii. Pessimistic:
Thoughts and Comments: (3 POINTS)
1. Ask what type of contract the CPIF effectively becomes once incurred costs hit pessimistic cost.
ATTACHMENTS: (2 POINTS)
What kind of attachments would you think would be provided?
Anything else you would need to “put on” the PNM (assume it doesn’t have all the instructor Q&A and is a real pre PNM—there is something special that you need to make sure you place on the document. Check your score sheet for the first PNM if you are in doubt!
ASSIGNMENT 2: (5 POINTS)
Y2K Testing and BRAC! Three months after contract award, DoD mandates Y2K testing of all computer systems be accomplished within the next four months. In addition, both computer center operations are to be combined at Fogleman AFB and the combination completed by Jan 2001! The contracting officer notifies McGhee Systems in writing to start support of the Y2K testing immediately. The contracting officer sends a separate letter notifying McGhee Systems to submit a combined proposal for both the added Y2K effort and for combining and continuing computer center support. McGhee Systems submits the equitable adjustment proposal. Your technical folks have alerted you that since contract award the contractor has reduced its staff….and that it has not impacted performance a bit! You look at the contractor's proposal. Regarding the combination of computer centers, they are proposing simply adding the staffs because the work will double when combined. They are also proposing that since we just negotiated a fair and reasonable price, we can just use the recent proposal (skill mix and quantities and rates) as a basis for negotiation. Identify and discuss two primary issues that you will pursue in your analysis.
Two primary issues I will pursue in my analysis of the request for equitable adjustment will include:
1.
.
2.
ASSIGNMENT 3: The contract is complete. Final CPIF Price. Using your CPIF Target Cost/Fee and incentive elements from Assignment 1 (assume the equitable adjustment never occurred), what is the final CPIF price if McGhee Systems experienced final incurred cost of $700,000 under target cost. Remember there are minimum and maximum fees (5 POINTS)
27 of 27
1999 Costs
| On-Site Support | Proposed Hrs./Yr. | Esc. | 1999 Rate | 1999 Proposed Total | Proposed Totals | Optimistic Hrs/Yr. | Esc. | 1999 Rate | 1999 Optimistic Total | OPTIMISTIC TOTALS | OBJ | Esc. | 1999 Rate | 1999 Obj Total | OBJECTIVE Target TOTALS | Pessimistic |
| Application Systems Analyst II | 8,320 | 1.056 | $ 25.40 | $ 211,339 | 8,320 | 1.056 | $ 25.40 | $ 211,339 | $ | |||||||
| Programmer Analyst II | 8,320 | 1.056 | $ 26.51 | $ 220,586 | 8,320 | 1.056 | $ 26.51 | $ 220,586 | $ | |||||||
| Database Analyst II | 8,320 | 1.056 | $ 16.75 | $ 139,396 | 4,160 | 1.056 | $ 16.75 | $ 69,698 | $ | |||||||
| Computer Support/Operations II | 34,944 | 1.056 | $ 29.51 | $ 1,031,273 | 34,944 | 1.056 | $ 29.51 | $ 1,031,273 | $ | |||||||
| Systems Administration | 17,472 | 1.056 | $ 37.54 | $ 655,975 | 17,472 | 1.056 | $ 37.54 | $ 655,975 | $ | |||||||
| On-Call Support | $ | |||||||||||||||
| Application Systems Analyst II | 720 | $ 38.10 | $ 27,433 | 360 | $ 38.10 | $ 13,717 | $ | |||||||||
| Programmer Analyst II | 840 | $ 39.77 | $ 33,406 | 240 | $ 39.77 | $ 9,545 | $ | |||||||||
| Database Analyst II | 720 | $ 25.13 | $ 18,095 | 240 | $ 25.13 | $ 6,032 | $ | |||||||||
| Total Labor | 79,656 | $ 2,337,503 | 74,056 | $ 2,218,164 | $ | |||||||||||
| Fringe | $ 1.47 | $ 113,743 | $ 1.47 | $ 107,628 | $ | |||||||||||
| Overhead | 35% | $ 790,499 | 35% | $ 766,105 | $ | |||||||||||
| $ | ||||||||||||||||
| Material Growth Factors | $ | |||||||||||||||
| Scheduled | $200,000 | $ 200,000 | $ | |||||||||||||
| Unscheduled | 1.261 | $151,320 | 0.970 | $ 116,400 | $ | |||||||||||
| Minor Enhancements | 1.358 | $40,740 | 0.970 | $ 29,100 | $ | |||||||||||
| Misc | 1.067 | $8,536 | 1.019 | $ 8,148 | $ | |||||||||||
| Total Material | $400,596 | $ 353,648 | $ | |||||||||||||
| Total Support Cost | $ 3,642,341 | $ 3,445,545 | $ | |||||||||||||
| $ | ||||||||||||||||
| G&A | 15% | $ 546,351 | 15% | $ 516,832 | $ | |||||||||||
| $ | ||||||||||||||||
| Target Cost | $ 4,188,692 | $ 3,962,376 | $ | |||||||||||||
| Target Fee | 11% | $ 460,756 | 9% | $ 356,614 | $ | |||||||||||
| Target Price | $ 4,649,448 | $ 4,318,990 | $ | |||||||||||||
| Minimum Fee | 90/10 | $ 418,869 | 80/20 | $ 237,743 | $ | |||||||||||
| Maximum Fee | 70/30 | $ 661,813 | 80/20 | $ 183,410 | $ | |||||||||||
| Optimistic Cost | 84% | $ 3,518,501 | 84% | $ 483,410 | $ | |||||||||||
| Pessimistic Cost | 110% | $ 4,607,561 | 115% | $ 3,328,396 | $ | |||||||||||
| Contractor Share Ratio Over | 10% | 20% | % | |||||||||||||
| Contractor Share Ratio Under | 30% | 20% | % |
On-Site Support
Proposed
Hrs./Yr.
2000
Rate
2000
Proposed
Total
Proposed
Totals
Optimistic
Hrs/Yr.
2000
Rate
2000
Optimistic
Total
Optimisti
c Totals
OJB
2000
Rate
2000
Objectiv
e/Target
Target
Objective
Totals
2000
Pessimisti
c
Application Systems Analyst
II
8,3201.057 $26.85 223,386$ 8,3201.057 $ 26.85 $ 223,386 $
Programmer Analyst II
8,3201.057 $28.02 233,159$ 8,3201.057 $ 28.02 $ 223,159 $
Database Analyst II
8,3201.057 $ 17.71 147,342$ 4,1601.057 $ 17.71 $ 73,671 $
Computer
Support/Operations II
34,9441.057 $ 31.19 1,090,055$ 34,9441.057 $ 31.19 $ 1,090,055 $
Systems Administration
17,4721.057 $39.68 693,366$ 17,4721.057 $ 39.68 $ 693,289 $
On-Call Support
$
Application Systems Analyst
II
840 $40.27 33,830$ 360 $ 40.27 $ 14,497 $
Programmer Analyst II
960 $42.04 40,354$ 240 $ 42.04 $ 10,089 $
Database Analyst II
840 $26.56 22,314$ 240 $ 26.56 $ 6,375 $
Total Labor
80,0162,483,806$ 74,0562,344,599$
$
Fringe
$ 1.47
113,743$
$ 1.47
107,628$
$
Overhead
50%
1,193,654$
47%
1,087,409$
$
$
Material Growth Factors
$
Scheduled0.94$225,8160.941225,816$
$
Unscheduled1.261$190,8151.019118,553$
$
Minor Enhancements1.358$55,3250.97028,227$
$
Misc1.067$9,1081.0198,299$
$
Total Material481,064$ 380,895$
$
Total Support Cost4,272,267$ 3,920,531$
$
$
G&A25%1,068,067$ 23%901,722$
$
$
Target Cost5,340,333$ 4,822,253$
$
Target Fee11%587,437$ 9%434,003$
$
Target Price5,927,770$ 5,256,256$
$
Minimum Fee 90/10534,033$ 80/20289,335$
$
Maximum Fee 70/30843,773$ 80/20588,315$
$
Optimistic Cost84%4,485,880$ 84%4,050,693$
$
Pessimistic Cost 110%5,874,367$ 115%5,545,591$
$
Contractor Share Ratio Over10%20%%
Contractor Share Ratio Under30%20%%
2000 Costs
| On-Site Support | Proposed Hrs./Yr. | Esc. | 2000 Rate | 2000 Proposed Total | Proposed Totals | Optimistic Hrs/Yr. | Esc. | 2000 Rate | 2000 Optimistic Total | Optimistic Totals | OJB | Esc. | 2000 Rate | 2000 Objective/Target | Target Objective Totals | 2000 Pessimistic |
| Application Systems Analyst II | 8,320 | 1.057 | $ 26.85 | $ 223,386 | 8,320 | 1.057 | $ 26.85 | $ 223,386 | $ | |||||||
| Programmer Analyst II | 8,320 | 1.057 | $ 28.02 | $ 233,159 | 8,320 | 1.057 | $ 28.02 | $ 223,159 | $ | |||||||
| Database Analyst II | 8,320 | 1.057 | $ 17.71 | $ 147,342 | 4,160 | 1.057 | $ 17.71 | $ 73,671 | $ | |||||||
| Computer Support/Operations II | 34,944 | 1.057 | $ 31.19 | $ 1,090,055 | 34,944 | 1.057 | $ 31.19 | $ 1,090,055 | $ | |||||||
| Systems Administration | 17,472 | 1.057 | $ 39.68 | $ 693,366 | 17,472 | 1.057 | $ 39.68 | $ 693,289 | $ | |||||||
| On-Call Support | $ | |||||||||||||||
| Application Systems Analyst II | 840 | $ 40.27 | $ 33,830 | 360 | $ 40.27 | $ 14,497 | $ | |||||||||
| Programmer Analyst II | 960 | $ 42.04 | $ 40,354 | 240 | $ 42.04 | $ 10,089 | $ | |||||||||
| Database Analyst II | 840 | $ 26.56 | $ 22,314 | 240 | $ 26.56 | $ 6,375 | $ | |||||||||
| Total Labor | 80,016 | $ 2,483,806 | 74,056 | $ 2,344,599 | $ | |||||||||||
| Fringe | $ 1.47 | $ 113,743 | $ 1.47 | $ 107,628 | $ | |||||||||||
| Overhead | 50% | $ 1,193,654 | 47% | $ 1,087,409 | $ | |||||||||||
| $ | ||||||||||||||||
| Material Growth Factors | $ | |||||||||||||||
| Scheduled | 0.941 | $225,816 | 0.941 | $ 225,816 | $ | |||||||||||
| Unscheduled | 1.261 | $190,815 | 1.019 | $ 118,553 | $ | |||||||||||
| Minor Enhancements | 1.358 | $55,325 | 0.970 | $ 28,227 | $ | |||||||||||
| Misc | 1.067 | $9,108 | 1.019 | $ 8,299 | $ | |||||||||||
| Total Material | $ 481,064 | $ 380,895 | $ | |||||||||||||
| Total Support Cost | $ 4,272,267 | $ 3,920,531 | $ | |||||||||||||
| $ | ||||||||||||||||
| G&A | 25% | $ 1,068,067 | 23% | $ 901,722 | $ | |||||||||||
| $ | ||||||||||||||||
| Target Cost | $ 5,340,333 | $ 4,822,253 | $ | |||||||||||||
| Target Fee | 11% | $ 587,437 | 9% | $ 434,003 | $ | |||||||||||
| Target Price | $ 5,927,770 | $ 5,256,256 | $ | |||||||||||||
| Minimum Fee | 90/10 | $ 534,033 | 80/20 | $ 289,335 | $ | |||||||||||
| Maximum Fee | 70/30 | $ 843,773 | 80/20 | $ 588,315 | $ | |||||||||||
| Optimistic Cost | 84% | $ 4,485,880 | 84% | $ 4,050,693 | $ | |||||||||||
| Pessimistic Cost | 110% | $ 5,874,367 | 115% | $ 5,545,591 | $ | |||||||||||
| Contractor Share Ratio Over | 10% | 20% | % | |||||||||||||
| Contractor Share Ratio Under | 30% | 20% | % |
On-Site Support
Proposed
Hrs./Yr.
2001
Rate
2001
Proposed
Total
Proposed
Totals
Optimistic
Hrs/Yr.
2001
Rate
2001
Optimistic
Total
Optimistic
Totals
Obj
2001
Rate
2001 Obj
Total
Objective
Target Totals
Pessimistic
Application Systems Analyst II
8,3201.056 $ 28.35 235,895$ 8,320$ 1.056 $ 28.35 $ 235,895 $
Programmer Analyst II
8,3201.056 $ 29.59 246,216$ 8,320$ 1.056 $ 29.59 $ 246,216 $
Database Analyst II
8,3201.056 $ 18.70 155,593$ 4,160$ 1.056 $ 18.70 $ 77,796 $
Computer Support/Operations
II
34,9441.056 $ 32.94 1,151,098$ 34,944$ 1.056 $ 32.94 $ 1,551,098 $
Systems Administration
17,4721.056 $ 41.91 732,194$ 17,472$ 1.056 $ 41.91 $ 732,194 $
On-Call Support
$
Application Systems Analyst II
960 $ 42.53 40,828$ 480 $ 42.53 $ 20,414 $
Programmer Analyst II
1,080 $ 44.39 47,941$ 360 $ 44.39 $ 18,980 $
Database Analyst II
960 $ 28.05 26,930$ 360 $ 28.05 $ 10,099 $
Total Labor
80,3762,636,695$ 74,4162,489,693$
$
Fringe
$ 1.47
113,743$
$ 1.47
107,628$
$
Overhead
50%
1,260,498$
47%
1,148,304$
$
$
Material Growth Factors
$
Scheduled0.93$204,5140.93204,514$
$
Unscheduled1.284$245,0821.087128,844$
$
Minor Enhancements1.383$76,5250.2476,972$
$
Misc1.087$9,8981.0378,609$
$
Total Material536,020$ 348,939$
$
Total Support Cost4,546,956$ 4,094,564$
$
$
G&A25%1,136,739$ 23%941,750$
$
$
Target Cost5,683,695$ 5,036,313$
$
Target Fee11%625,207$ 9%453,268$
$
Target Price6,308,902$ 5,489,582$
$
Minimum Fee 90/10568,370$ 80/20302,179$
$
Maximum Fee 70/30898,024$ 8020614,430$
$
Optimistic Cost84%4,774,304$ 84%4,230,503$
$
Pessimistic Cost 110%6,252,065$ 115%5,791,760$
$
Contractor Share Ratio Over10%20%
%
Contractor Share Ratio Under30%20%
%
On-Site Labor Hours
| Position | Proposed Hrs./Yr. | Proprosed Elements | Optimistic Hrs/Yr. | Variance | Comments | Most Likely to Negotiate Hrs/Yr. | Variance | Comments | Pessimestic Hrs/Yr. | Variance |
| Applications Systems Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Programmer Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Database Analysis II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% |
| Computer Support/Operations II | 34,944 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% |
| Systems Administration | 17,472 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% |
| Total Hours per year | 77,376 | 71,136 | 8% | 75,296 | 3% | 77,376 | 0% |
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Proposed Esc. | 2001 Rate | Optimistic Esc. | 1999 Rate | Optimistic Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate | Proposed Hrs./Yr. | Optimistic Hrs/Yr. | 1999 Proposed Total | 2000 Proposed Total | 2001 Proposed Total | Proposed Total Costs | 1999 Optimistic Total | 2000 Optimistic Total | 2001 Optimistic Total | Check | Optimistic Total Target | Objective Hrs/Yr. | 1999 Most Likely Total | 2000 Most Likely Total | 2001 Most Likely Total | Check | Most Likely to Negotiate Total | Pessimestic Hrs/Yr. | 1999 Pessimesitc Total | 2000 Pessimesitc Total | 2001 Pessimesitc Total | Check Total | Pessimestic Total Costs | Pessimistic Total |
| Applications Systems Analyst II | $ 24.05 | 1.056 | $ 25.40 | 1.057 | $ 26.85 | 1.056 | $ 28.35 | 1.051 | $ 25.28 | 1.052 | $ 26.59 | 1.051 | $ 27.95 | 8,320 | 6,240 | $ 211,339.00 | $ 223,386.00 | $ 235,895.00 | $ 670,620.00 | $ 157,725.67 | $ 165,927.41 | $ 174,389.70 | $ 498,042.78 | $ 498,042.78 | 8,320 | $ 211,328.00 | $ 223,392.00 | $ 235,872.00 | $ 670,592.00 | $ 670,592.00 | 8,320 | $ 211,328.00 | $ 223,392.00 | $ 235,872.00 | $ 670,592.00 | $ 670,592.00 | $ 670,592.00 |
| Programmer Analyst II | $ 25.11 | 1.056 | $ 26.51 | 1.057 | $ 28.02 | 1.056 | $ 29.59 | 1.051 | $ 26.39 | 1.052 | $ 27.76 | 1.051 | $ 29.18 | 8,320 | 6,240 | $ 220,586.00 | $ 233,159.00 | $ 246,216.00 | $ 699,961.00 | $ 164,677.41 | $ 173,240.63 | $ 182,075.90 | $ 519,993.94 | $ 519,993.94 | 8,320 | $ 220,563.20 | $ 233,126.40 | $ 246,188.80 | $ 699,878.40 | $ 699,878.40 | 8,320 | $ 220,563.20 | $ 233,126.40 | $ 246,188.80 | $ 699,878.40 | $ 699,878.40 | $ 699,878.40 |
| Database Analysis II | $ 15.87 | 1.056 | $ 16.75 | 1.057 | $ 17.71 | 1.056 | $ 18.70 | 1.051 | $ 16.68 | 1.052 | $ 17.55 | 1.051 | $ 18.44 | 8,320 | 6,240 | $ 139,396.00 | $ 147,342.00 | $ 155,593.00 | $ 442,331.00 | $ 104,079.27 | $ 109,491.39 | $ 115,075.45 | $ 328,646.11 | $ 328,646.11 | 6,240 | $ 104,520.00 | $ 110,510.40 | $ 116,688.00 | $ 331,718.40 | $ 331,718.40 | 8,320 | $ 139,360.00 | $ 147,347.20 | $ 155,584.00 | $ 442,291.20 | $ 442,291.20 | $ 442,291.20 |
| Computer Support/Operations II | $ 27.95 | 1.056 | $ 29.51 | 1.057 | $ 31.19 | 1.056 | $ 32.94 | 1.051 | $ 29.38 | 1.052 | $ 30.90 | 1.051 | $ 32.48 | 34,944 | 34,944 | $ 1,031,273.00 | $ 1,090,055.00 | $ 1,151,098.00 | $ 3,272,426.00 | $ 1,026,495.72 | $ 1,079,873.50 | $ 1,134,947.05 | $ 3,241,316.28 | $ 3,241,316.28 | 34,944 | $ 1,031,197.44 | $ 1,089,903.36 | $ 1,151,055.36 | $ 3,272,156.16 | $ 3,272,156.16 | 34,944 | $ 1,031,197.44 | $ 1,089,903.36 | $ 1,151,055.36 | $ 3,272,156.16 | $ 3,272,156.16 | $ 3,272,156.16 |
| Systems Administration | $ 35.55 | 1.056 | $ 37.54 | 1.057 | $ 39.68 | 1.056 | $ 41.91 | 1.051 | $ 37.36 | 1.052 | $ 39.31 | 1.051 | $ 41.31 | 17,472 | 17,472 | $ 655,975.00 | $ 693,366.00 | $ 732,194.00 | $ 2,081,535.00 | $ 652,807.21 | $ 686,753.18 | $ 721,777.60 | $ 2,061,337.99 | $ 2,061,337.99 | 17,472 | $ 655,898.88 | $ 693,288.96 | $ 732,251.52 | $ 2,081,439.36 | $ 2,081,439.36 | 17,472 | $ 655,898.88 | $ 693,288.96 | $ 732,251.52 | $ 2,081,439.36 | $ 2,081,439.36 | $ 2,081,439.36 |
| TOTAL | $ 2,258,569.00 | $ 2,387,308.00 | $ 2,520,996.00 | $ 7,166,873.00 | $ 2,105,785.28 | $ 2,215,286.12 | $ 2,328,265.71 | $ 6,649,337.11 | $ 6,649,337.11 | 7% | $ 2,223,507.52 | $ 2,350,221.12 | $ 2,482,055.68 | $ 7,055,784.32 | $ 7,055,784.32 | 2% | $ 2,258,347.52 | $ 2,387,057.92 | $ 2,520,951.68 | $ 7,166,357.12 | $ 7,166,357.12 | $ 7,166,357.12 | |||||||||||||||
| OVERHEAD | 35% | 50% | 50% | 35% | 47% | 47% | 35% | 47% | 47% | 35% | 50% | 50% | |||||||||||||||||||||||||
| OVERHEAD TOTALS | $ 790,499.15 | $ 1,193,654.00 | $ 1,260,498.00 | $ 3,244,651.15 | $ 737,024.85 | $ 1,041,184.47 | $ 1,094,284.88 | $ 2,872,494.21 | $ 778,227.63 | $ 1,104,603.93 | $ 1,166,566.17 | $ 3,049,397.73 | $ 790,421.63 | $ 1,193,528.96 | $ 1,260,475.84 | $ 3,244,426.43 |
2001 Costs
| On-Site Support | Proposed Hrs./Yr. | Esc. | 2001 Rate | 2001 Proposed Total | Proposed Totals | Optimistic Hrs/Yr. | Esc. | 2001 Rate | 2001 Optimistic Total | Optimistic Totals | Obj | Esc. | 2001 Rate | 2001 Obj Total | Objective Target Totals | Pessimistic |
| Application Systems Analyst II | 8,320 | 1.056 | $ 28.35 | $ 235,895 | $ 8,320 | 1.056 | $ 28.35 | $ 235,895 | $ | |||||||
| Programmer Analyst II | 8,320 | 1.056 | $ 29.59 | $ 246,216 | $ 8,320 | 1.056 | $ 29.59 | $ 246,216 | $ | |||||||
| Database Analyst II | 8,320 | 1.056 | $ 18.70 | $ 155,593 | $ 4,160 | 1.056 | $ 18.70 | $ 77,796 | $ | |||||||
| Computer Support/Operations II | 34,944 | 1.056 | $ 32.94 | $ 1,151,098 | $ 34,944 | 1.056 | $ 32.94 | $ 1,551,098 | $ | |||||||
| Systems Administration | 17,472 | 1.056 | $ 41.91 | $ 732,194 | $ 17,472 | 1.056 | $ 41.91 | $ 732,194 | $ | |||||||
| On-Call Support | $ | |||||||||||||||
| Application Systems Analyst II | 960 | $ 42.53 | $ 40,828 | 480 | $ 42.53 | $ 20,414 | $ | |||||||||
| Programmer Analyst II | 1,080 | $ 44.39 | $ 47,941 | 360 | $ 44.39 | $ 18,980 | $ | |||||||||
| Database Analyst II | 960 | $ 28.05 | $ 26,930 | 360 | $ 28.05 | $ 10,099 | $ | |||||||||
| Total Labor | 80,376 | $ 2,636,695 | 74,416 | $ 2,489,693 | $ | |||||||||||
| Fringe | $ 1.47 | $ 113,743 | $ 1.47 | $ 107,628 | $ | |||||||||||
| Overhead | 50% | $ 1,260,498 | 47% | $ 1,148,304 | $ | |||||||||||
| $ | ||||||||||||||||
| Material Growth Factors | $ | |||||||||||||||
| Scheduled | 0.93 | $204,514 | 0.93 | $ 204,514 | $ | |||||||||||
| Unscheduled | 1.284 | $245,082 | 1.087 | $ 128,844 | $ | |||||||||||
| Minor Enhancements | 1.383 | $76,525 | 0.247 | $ 6,972 | $ | |||||||||||
| Misc | 1.087 | $9,898 | 1.037 | $ 8,609 | $ | |||||||||||
| Total Material | $ 536,020 | $ 348,939 | $ | |||||||||||||
| Total Support Cost | $ 4,546,956 | $ 4,094,564 | $ | |||||||||||||
| $ | ||||||||||||||||
| G&A | 25% | $ 1,136,739 | 23% | $ 941,750 | $ | |||||||||||
| $ | ||||||||||||||||
| Target Cost | $ 5,683,695 | $ 5,036,313 | $ | |||||||||||||
| Target Fee | 11% | $ 625,207 | 9% | $ 453,268 | $ | |||||||||||
| Target Price | $ 6,308,902 | $ 5,489,582 | $ | |||||||||||||
| Minimum Fee | 90/10 | $ 568,370 | 80/20 | $ 302,179 | $ | |||||||||||
| Maximum Fee | 70/30 | $ 898,024 | 8020 | $ 614,430 | $ | |||||||||||
| Optimistic Cost | 84% | $ 4,774,304 | 84% | $ 4,230,503 | $ | |||||||||||
| Pessimistic Cost | 110% | $ 6,252,065 | 115% | $ 5,791,760 | $ | |||||||||||
| Contractor Share Ratio Over | 10% | 20% | % | |||||||||||||
| Contractor Share Ratio Under | 30% | 20% | % |
Proposed
Hrs./Yr.
Proprosed Elements
Optimistic
Hrs/Yr.
Proposed Elements
Objective
Hrs/Yr.
Proposed Elements
Pessimestic
Hrs/Yr.
Proposed Elements
8,320
2080hrs/yr. x 2 persons
x 2 sites
8,320
2080hrs/yr. x 2 persons
x 2 sites
8,320
2080hrs/yr. x 2 persons
x 2 sites
34,944
((2080hrs/yr. + (16hrs x
52wks)) x 2 persons x 2
sites x 3 shifts
17,472
((2080hrs/yr. + (16hrs x
52wks)) x 2 persons x 2
sites x 3 shifts
77,376
On-Site Labor Hours
| Position | Proposed Hrs./Yr. | Proprosed Elements | Optimistic Hrs/Yr. | Proposed Elements | Objective Hrs/Yr. | Proposed Elements | Pessimestic Hrs/Yr. | Proposed Elements |
| Applications Systems Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | ||||||
| Programmer Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | ||||||
| Database Analysis II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | ||||||
| Computer Support/Operations II | 34,944 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | ||||||
| Systems Administration | 17,472 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | ||||||
| Total Hours per year | 77,376 |
On-Site Labor Costs
| Position | 1999 Rate | 2000 Rate | 2001 Rate | Proposed Hrs./Yr. | Proposed Costs | Optimistic Hrs/Yr. | Optimistic Target | Objective Hrs/Yr. | Objective | Pessimestic Hrs/Yr. | Pessimistic |
| Applications Systems Analyst II | $ 25.40 | $ 26.85 | $ 28.35 | 8,320 | $ 670,592.00 | 6,240 | 8,320 | 8,320 | |||
| Programmer Analyst II | $ 26.51 | $ 28.02 | $ 29.59 | 8,320 | $ 699,878.40 | 6,240 | 8,320 | 8,320 | |||
| Database Analysis II | $ 16.75 | $ 17.71 | $ 18.70 | 8,320 | $ 442,291.20 | 6,240 | 6,240 | 8,320 | |||
| Computer Support/Operations II | $ 29.51 | $ 31.19 | $ 32.94 | 34,944 | $ 3,272,156.16 | 34,944 | 34,944 | 34,944 | |||
| Systems Administration | $ 37.54 | $ 39.68 | $ 41.91 | 17,472 | $ 2,081,439.36 | 17,472 | 17,472 | 17,472 | |||
| TOTAL / VARIANCE | $ 7,166,357.12 |
Sheet3
Position1998 Rate
Proposed
Esc.
1999 Rate
Proposed
Esc.
2000 Rate
Proposed
Esc.
2001 Rate
Applications Systems Analyst II $ 24.05 1.056 $ 25.40 1.057 $ 26.85 1.056 $ 28.35
Programmer Analyst II $ 25.11 1.056 $ 26.51 1.057 $ 28.02 1.056 $ 29.59
Database Analysis II $ 15.87 1.056 $ 16.75 1.057 $ 17.71 1.056 $ 18.70
Computer Support/Operations II $ 27.95 1.056 $ 29.51 1.057 $ 31.19 1.056 $ 32.94
Systems Administration $ 35.55 1.056 $ 37.54 1.057 $ 39.68 1.056 $ 41.91
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Proposed Esc. | 2001 Rate |
| Applications Systems Analyst II | $ 24.05 | 1.056 | $ 25.40 | 1.057 | $ 26.85 | 1.056 | $ 28.35 |
| Programmer Analyst II | $ 25.11 | 1.056 | $ 26.51 | 1.057 | $ 28.02 | 1.056 | $ 29.59 |
| Database Analysis II | $ 15.87 | 1.056 | $ 16.75 | 1.057 | $ 17.71 | 1.056 | $ 18.70 |
| Computer Support/Operations II | $ 27.95 | 1.056 | $ 29.51 | 1.057 | $ 31.19 | 1.056 | $ 32.94 |
| Systems Administration | $ 35.55 | 1.056 | $ 37.54 | 1.057 | $ 39.68 | 1.056 | $ 41.91 |
Position 1998 Rate
Proposed
Esc.
1999 Rate
Proposed
Esc.
2000
Rate
Optimistic
Esc.
2001
Rate
Applications Systems Analyst II $ 24.05
Programmer Analyst II $ 25.11
Database Analysis II $ 15.87
Computer Support/Operations II $ 27.95
Systems Administration $ 35.55
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate |
| Applications Systems Analyst II | $ 24.05 | ||||||
| Programmer Analyst II | $ 25.11 | ||||||
| Database Analysis II | $ 15.87 | ||||||
| Computer Support/Operations II | $ 27.95 | ||||||
| Systems Administration | $ 35.55 |
Position 1998 Rate
Proposed
Esc.
1999 Rate
Proposed
Esc.
2000
Rate
Optimistic
Esc.
2001
Rate
Applications Systems Analyst II24.05$ 1.056 $ 25.40 1.057 $ 26.85 1.056 $ 28.35
Programmer Analyst II25.11$ 1.056 $ 26.51 1.057 $ 28.02 1.056 $ 29.59
Database Analysis II15.87$ 1.056 $ 16.75 1.057 $ 17.71 1.056 $ 18.70
Computer Support/Operations II27.95$ 1.056 $ 29.51 1.057 $ 31.19 1.056 $ 32.94
Systems Administration35.55$ 1.056 $ 37.54 1.057 $ 39.68 1.056 $ 41.91
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate |
| Applications Systems Analyst II | $ 24.05 | 1.056 | $ 25.40 | 1.057 | $ 26.85 | 1.056 | $ 28.35 |
| Programmer Analyst II | $ 25.11 | 1.056 | $ 26.51 | 1.057 | $ 28.02 | 1.056 | $ 29.59 |
| Database Analysis II | $ 15.87 | 1.056 | $ 16.75 | 1.057 | $ 17.71 | 1.056 | $ 18.70 |
| Computer Support/Operations II | $ 27.95 | 1.056 | $ 29.51 | 1.057 | $ 31.19 | 1.056 | $ 32.94 |
| Systems Administration | $ 35.55 | 1.056 | $ 37.54 | 1.057 | $ 39.68 | 1.056 | $ 41.91 |
Position 1998 Rate
Proposed
Esc.
1999 Rate
Proposed
Esc.
2000
Rate
Optimistic
Esc.
2001
Rate
Applications Systems Analyst II24.05$
Programmer Analyst II25.11$
Database Analysis II15.87$
Computer Support/Operations II27.95$
Systems Administration
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate |
| Applications Systems Analyst II | $ 24.05 | ||||||
| Programmer Analyst II | $ 25.11 | ||||||
| Database Analysis II | $ 15.87 | ||||||
| Computer Support/Operations II | $ 27.95 | ||||||
| Systems Administration |
Position
Proposed Total
Costs
Optimistic Total
Objective/Target
(Most Likely)
Pessimestic
Total
Applications Systems
Analyst II
670,620.00$
Programmer Analyst II699,961.00$
Database Analysis II442,331.00$
Computer
Support/Operations II
3,272,426.00$
Systems Administration2,081,535.00$
TOTAL7,166,873.00$
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Proposed Esc. | 2001 Rate | Optimistic Esc. | 1999 Rate | Optimistic Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate | Proposed Hrs./Yr. | Optimistic Hrs/Yr. | 1999 Proposed Total | 2000 Proposed Total | 2001 Proposed Total | Proposed Total Costs | 1999 Optimistic Total | 2000 Optimistic Total | 2001 Optimistic Total | Check | Optimistic Total | Objective Hrs/Yr. | 1999 Most Likely Total | 2000 Most Likely Total | 2001 Most Likely Total | Check | Objective/Target (Most Likely) | Pessimestic Hrs/Yr. | 1999 Proposed/ Pessimesitc Total | 2000 Proposed/ Pessimesitc Total | 2001 Proposed/ Pessimesitc Total | Check Total | Pessimestic Total | Pessimistic Total |
| Applications Systems Analyst II | $ 24.05 | 1.056 | $ 25.40 | 1.057 | $ 26.85 | 1.056 | $ 28.35 | 1.051 | $ 25.28 | 1.052 | $ 26.59 | 1.051 | $ 27.95 | 8,320 | 6,240 | $ 211,339.00 | $ 223,386.00 | $ 235,895.00 | $ 670,620.00 | $ 157,725.67 | $ 165,927.41 | $ 174,389.70 | $ 498,042.78 | $ - 0 | |||||||||||||
| Programmer Analyst II | $ 25.11 | 1.056 | $ 26.51 | 1.057 | $ 28.02 | 1.056 | $ 29.59 | 1.051 | $ 26.39 | 1.052 | $ 27.76 | 1.051 | $ 29.18 | 8,320 | 6,240 | $ 220,586.00 | $ 233,159.00 | $ 246,216.00 | $ 699,961.00 | $ 164,677.41 | $ 173,240.63 | $ 182,075.90 | $ 519,993.94 | $ - 0 | |||||||||||||
| Database Analysis II | $ 15.87 | 1.056 | $ 16.75 | 1.057 | $ 17.71 | 1.056 | $ 18.70 | 1.051 | $ 16.68 | 1.052 | $ 17.55 | 1.051 | $ 18.44 | 8,320 | 6,240 | $ 139,396.00 | $ 147,342.00 | $ 155,593.00 | $ 442,331.00 | $ 104,079.27 | $ 109,491.39 | $ 115,075.45 | $ 328,646.11 | $ - 0 | |||||||||||||
| Computer Support/Operations II | $ 27.95 | 1.056 | $ 29.51 | 1.057 | $ 31.19 | 1.056 | $ 32.94 | 1.051 | $ 29.38 | 1.052 | $ 30.90 | 1.051 | $ 32.48 | 34,944 | 34,944 | $ 1,031,273.00 | $ 1,090,055.00 | $ 1,151,098.00 | $ 3,272,426.00 | $ 1,026,495.72 | $ 1,079,873.50 | $ 1,134,947.05 | $ 3,241,316.28 | $ - 0 | |||||||||||||
| Systems Administration | $ 35.55 | 1.056 | $ 37.54 | 1.057 | $ 39.68 | 1.056 | $ 41.91 | 1.051 | $ 37.36 | 1.052 | $ 39.31 | 1.051 | $ 41.31 | 17,472 | 17,472 | $ 655,975.00 | $ 693,366.00 | $ 732,194.00 | $ 2,081,535.00 | $ 652,807.21 | $ 686,753.18 | $ 721,777.60 | $ 2,061,337.99 | $ - 0 | |||||||||||||
| TOTAL | $ 2,258,569.00 | $ 2,387,308.00 | $ 2,520,996.00 | $ 7,166,873.00 | $ 2,105,785.28 | $ 2,215,286.12 | $ 2,328,265.71 | $ 6,649,337.11 | $ - 0 | ||||||||||||||||||||||||||||
| OVERHEAD | 35% | 50% | 50% | 35% | 47% | 47% | 35% | 47% | 47% | 35% | 50% | 50% | |||||||||||||||||||||||||
| $ 790,499.15 | $ 1,193,654.00 | $ 1,260,498.00 | $ 3,244,651.15 | $ 737,024.85 | $ 1,041,184.47 | $ 1,094,284.88 | $ 2,872,494.21 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
1999
Basic
2000
Option
1
2001
Option
2
1999
Basic
Delta
2000
Option1
Delta
2001
Option2
Delta
1999
Basic
Delta
2000
Option
1
Delta
2001
Option
2
Delta
1999
Basic
Delta
2000
Option
1
Delta
2001
Option
2
Delta
Applics Sys
Anal II
720840960360360480
Progr Analyst
II
8409601080240240360
Database
Anal/Prog II
720840960240240360
PESSIMISTICPROPOSEDOPTIMISTIC
Position
OBJECTIVE/TARGET
On-Call Labor
| Position | PROPOSED | OPTIMISTIC | OBJECTIVE/TARGET | PESSIMISTIC | |||||||||||||||||
| 1999 Basic | 2000 Option1 | 2001 Option2 | 1999 Basic | Delta | 2000 Option1 | Delta | 2001 Option2 | Delta | 1999 Basic | Delta | 2000 Option1 | Delta | 2001 Option2 | Delta | 1999 Basic | Delta | 2000 Option1 | Delta | 2001 Option2 | Delta | |
| Applics Sys Anal II | 720 | 840 | 960 | 360 | 360 | 480 | |||||||||||||||
| Progr Analyst II | 840 | 960 | 1080 | 240 | 240 | 360 | |||||||||||||||
| Database Anal/Prog II | 720 | 840 | 960 | 240 | 240 | 360 |
1999
Rate
2000
Rate
2001
Rate
1999
Rate
2000
Rate
2001
Rate
1999
Rate
2000
Rate
2001
Rate
Applics Sys
Anal II
Progr Analyst
II
Database
Anal/Prog II
Position
OPTOMISTICPESSIMISTIC OBJECTIVE/ TARGET
On-Call Labor
| Position | OPTOMISTIC | OBJECTIVE/ TARGET (MOST LIKELY) | PESSIMISTIC | ||||||||||||||||||||||||||||||
| 1999 Basic | 1999 Rate | Total | 2000 Option1 | 2000 Rate | Total | 2001 Option2 | 2001 Rate | Total | 1999 Basic | Delta | 1999 Rate | Total | 2000 Option1 | Delta | 2000 Rate | Total | 2001 Option2 | Delta | 2001 Rate | Total | 1999 Option1 | Delta | 1999 Rate | Total | 2000 Option1 | Delta | 2000 Rate | Total | 2001 Option2 | Delta | 2001 Rate | Total | |
| Applics Sys Anal II | 720 | $ - 0 | 360 | 50% | $ - 0 | ||||||||||||||||||||||||||||
| Progr Analyst II | 840 | $ - 0 | 240 | 71% | $ - 0 | ||||||||||||||||||||||||||||
| Database Anal/Prog II | 720 | $ - 0 | 240 | 67% | $ - 0 |
1999 Total2000 Total2001 Total1999 Total2000 Total2001 Total1999 Total2000 Total2001 Total
Applics Sys Anal II
Progr Analyst II
Database Anal/Prog II
Yearly Totals
3 Year Totals
Position
OPTIMISTICPESSIMISTICOBJECTIVE/TARGET (MOST LIKELY)
On-Call Labor
| Position | OPTIMISTIC | OBJECTIVE/TARGET (MOST LIKELY) | PESSIMISTIC | ||||||||||||||||||||||||||||||
| 1999 Basic | 1999 Rate | 1999 Total | 2000 Option1 | 2000 Rate | 2000 Total | 2001 Option2 | 2001 Rate | 2001 Total | 1999 Basic | Delta | 1999 Rate | 1999 Total | 2000 Option1 | Delta | 2000 Rate | 2000 Total | 2001 Option2 | Delta | 2001 Rate | 2001 Total | 1999 Option1 | Delta | 1999 Rate | 1999 Total | 2000 Option1 | Delta | 2000 Rate | 2000 Total | 2001 Option2 | Delta | 2001 Rate | 2001 Total | |
| Applics Sys Anal II | 720 | $ 38.10 | |||||||||||||||||||||||||||||||
| Progr Analyst II | 840 | $ 39.77 | |||||||||||||||||||||||||||||||
| Database Anal/Prog II | 720 | $ 25.13 | |||||||||||||||||||||||||||||||
| Yearly Totals | |||||||||||||||||||||||||||||||||
| 3 Year Totals |
Position
Proposed On-
Site Hrs./Yr.
Optimistic
Hrs/Yr.
Objective/
Target (Most
Likely) Hrs/Yr.
Pessimistic
Applications Systems Analyst II8,320
Programmer Analyst II8,320
Database Analysis II8,320
Computer Support/Operations II34,944
Systems Administration17,472
Total Hours77,376
3 Year Total232,128
Fringe Rate1.47$
Total Fringe113,742.72$
3 Year Total341,228.16$
Total Hours
| Position | Proposed On-Site Hrs./Yr. | Optimistic Hrs/Yr. | Objective/ Target (Most Likely) Hrs/Yr. | Pessimistic |
| Applications Systems Analyst II | 8,320 | |||
| Programmer Analyst II | 8,320 | |||
| Database Analysis II | 8,320 | |||
| Computer Support/Operations II | 34,944 | |||
| Systems Administration | 17,472 | |||
| Total Hours | 77,376 | |||
| 3 Year Total | 232,128 | |||
| Fringe Rate | $ 1.47 | |||
| Total Fringe | $ 113,742.72 | |||
| 3 Year Total | $ 341,228.16 |
1999
Optimistic
Total
2000
Optimistic
Total
2001
Optimistic
Total
Optimistic
Total
1999
Target/Obje
ctive (Most
Likely)
2000
Target/Obje
ctive (Most
Likely)
2001
Target/Object
ive (Most
Likely)
Objective/Tar
get (Most
Likely) Total
1999
Pessimistic
Total
2000
Pessimistic
Total
2001
Pessimistic
Total
Pessimistic
Total
Total Labor Cost 2,218,164$ 2,344,599$ 2,489,693$
OVERHEAD35%47%47%
OVERHEAD TOTALS766,105$ 1,087,409$ 1,148,304$
On-Site Labor Costs
| 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Proposed Esc. | 2001 Rate | Optimistic Esc. | 1999 Rate | Optimistic Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate | Proposed Hrs./Yr. | Optimistic Hrs/Yr. | 1999 Optimistic Total | 2000 Optimistic Total | 2001 Optimistic Total | Optimistic Total | 1999 Target/Objective (Most Likely) | 2000 Target/Objective (Most Likely) | 2001 Target/Objective (Most Likely) | Check | Objective/Target (Most Likely) Total | Objective Hrs/Yr. | 1999 Pessimistic Total | 2000 Pessimistic Total | 2001 Pessimistic Total | Proposed Optimisti Costs | Pessimistic Total | Pessimestic Hrs/Yr. | 1999 Pessimesitc Total | 2000 Pessimesitc Total | 2001 Pessimesitc Total | Check Total | Pessimestic Total Costs | Pessimistic Total | |
| Total Labor Cost | $ 2,218,164 | $ 2,344,599 | $ 2,489,693 | $ - 0 | 0% | 0% | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||||||||||||||||||||||||
| OVERHEAD | 35% | 47% | 47% | 35% | 50% | 50% | |||||||||||||||||||||||||||||||
| OVERHEAD TOTALS | $ 766,105 | $ 1,087,409 | $ 1,148,304 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
Overhead
Cost Description
Optimistic
Shared Ratio
1999
Optimistic
2000
Optimistic
2001
Optimistic
Most Likely
Shared Ratio
1999
Target/Objecti
ve ( Most
Likely )
2000
Target/Objecti
ve ( Most
Likely )
2001Target/Ob
jective ( Most
Likely )
Pessimistic
Shared Ratio
1999
Pessimistic
2000
Pessimistic
2001
Pessimistic
Target Costs3,962,376$ 4,822,253$ 5,036,313$
Target Fee9%356,614$ 434,003$ 453,268$
Optimist Costs84%3,328,396$ 4,050,693$ 4,230,503$
Pessimistic Costs115%4,556,732$ 5,545,591$ 5,791,760$
Optimistic Fee (Po)20%483,410$ 588,315$ 614,430$
Pessimistic Fee20%237,743$ 289,335$ 302,179$
Fees & Ratio's
| Cost Description | Optimistic Shared Ratio | 1999 Optimistic | 2000 Optimistic | 2001 Optimistic | Most Likely Shared Ratio | 1999 Target/Objective ( Most Likely ) | 2000 Target/Objective ( Most Likely ) | 2001Target/Objective ( Most Likely ) | Pessimistic Shared Ratio | 1999 Pessimistic | 2000 Pessimistic | 2001 Pessimistic |
| Target Costs | $ 3,962,376 | $ 4,822,253 | $ 5,036,313 | |||||||||
| Target Fee | 9% | $ 356,614 | $ 434,003 | $ 453,268 | ||||||||
| Optimist Costs | 84% | $ 3,328,396 | $ 4,050,693 | $ 4,230,503 | ||||||||
| Pessimistic Costs | 115% | $ 4,556,732 | $ 5,545,591 | $ 5,791,760 | ||||||||
| Optimistic Fee (Po) | 20% | $ 483,410 | $ 588,315 | $ 614,430 | ||||||||
| Pessimistic Fee | 20% | $ 237,743 | $ 289,335 | $ 302,179 |
PROPOSEDTARGET/OBJECTIVEOPTIMISTIC PESSIMISTIC
P
A
= S
CU
(C
T
-C
F
)$210,000
S
CU
Contractors Under Ratio 30%20%
C
T
Target cost15,212,720$ 13,820,342$
C
F
Final Cost14,512,720$ 13,120,342$
P
F
= P
A
+ P
T
$1,883,399
P
T
Target Fee1,673,399$ 1,243,885$
MaxMaximum Fee2,403,610$ 1,686,155$
K
F
C
F +PF
$16,396,119
Contract Total
C
F +Max
$16,916,330
Formula's
On-Site Labor Hours
| Position | Proposed Hrs./Yr. | Proprosed Elements | Optimistic Hrs/Yr. | Variance | Comments | Most Likely to Negotiate Hrs/Yr. | Variance | Comments | Pessimestic Hrs/Yr. | Variance |
| Applications Systems Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Programmer Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Database Analysis II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% |
| Computer Support/Operations II | 34,944 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% |
| Systems Administration | 17,472 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% |
| Total Hours per year | 77,376 | 71,136 | 8% | 75,296 | 3% | 77,376 | 0% |
Final Cost
| Formula's | PROPOSED | TARGET/OBJECTIVE | OPTIMISTIC | PESSIMISTIC | |||
| PA = | SCU(CT-CF) | $210,000 | |||||
| SCU | Contractors Under Ratio | 30% | 20% | ||||
| CT | Target cost | $ 15,212,720 | $ 13,820,342 | ||||
| CF | Final Cost | $ 14,512,720 | $ 13,120,342 | ||||
| PF = | PA + PT | $1,883,399 | |||||
| PT | Target Fee | $ 1,673,399 | $ 1,243,885 | ||||
| Max | Maximum Fee | $ 2,403,610 | $ 1,686,155 | ||||
| KF | CF +PF | $16,396,119 | |||||
| Contract Total | CF +Max | $16,916,330 | |||||
| ` |
Cost Description
PROPOSED
TOTALS
OPTIMISTIC
OBJECTIVE/
TARGET
REF.
PESSIMISTIC
Target Cost15,212,720$ 13,820,942$
Target Fee1,673,399$ 1,243,885$
Target Price16,886,119$ 15,064,827$
Minimum Fee 1,521,272$ 829,257$
Maximum Fee 2,403,610$ 1,686,155$
Optimistic Cost12,778,685$ 11,609,591$
Pessimistic Cost 16,733,992$ 15,894,084$
Contractor Share Ratio Over10%20%
On-Site Labor Hours
| Position | Proposed Hrs./Yr. | Proprosed Elements | Optimistic Hrs/Yr. | Variance | Comments | Most Likely to Negotiate Hrs/Yr. | Variance | Comments | Pessimestic Hrs/Yr. | Variance |
| Applications Systems Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Programmer Analyst II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% | Accept as proposed, but use as an incentive to lower the costs | 8,320 | 0% |
| Database Analysis II | 8,320 | 2080hrs/yr. x 2 persons x 2 sites | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 6,240 | 25% | Take away one person and have one person float between the 2 sites. | 8,320 | 0% |
| Computer Support/Operations II | 34,944 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% | Accept as proposed, but use as an incentive to lower the costs | 34,944 | 0% |
| Systems Administration | 17,472 | ((2080hrs/yr. + (16hrs x 52wks)) x 2 persons x 2 sites x 3 shifts | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% | Accept as proposed, but use as an incentive to lower the costs | 17,472 | 0% |
| Total Hours per year | 77,376 | 71,136 | 8% | 75,296 | 3% | 77,376 | 0% |
On-Site Labor Costs
| Position | 1998 Rate | Proposed Esc. | 1999 Rate | Proposed Esc. | 2000 Rate | Proposed Esc. | 2001 Rate | Optimistic Esc. | 1999 Rate | Optimistic Esc. | 2000 Rate | Optimistic Esc. | 2001 Rate | Proposed Hrs./Yr. | Optimistic Hrs/Yr. | 1999 Proposed Total | 2000 Proposed Total | 2001 Proposed Total | Proposed Total Costs | 1999 Optimistic Total | 2000 Optimistic Total | 2001 Optimistic Total | Check | Optimistic Total Target | Objective Hrs/Yr. | 1999 Most Likely Total | 2000 Most Likely Total | 2001 Most Likely Total | Check | Most Likely to Negotiate Total | Pessimestic Hrs/Yr. | 1999 Pessimesitc Total | 2000 Pessimesitc Total | 2001 Pessimesitc Total | Check Total | Pessimestic Total Costs | Pessimistic Total |
| Applications Systems Analyst II | $ 24.05 | 1.056 | $ 25.40 | 1.057 | $ 26.85 | 1.056 | $ 28.35 | 1.051 | $ 25.28 | 1.052 | $ 26.59 | 1.051 | $ 27.95 | 8,320 | 6,240 | $ 211,339.00 | $ 223,386.00 | $ 235,895.00 | $ 670,620.00 | $ 157,725.67 | $ 165,927.41 | $ 174,389.70 | $ 498,042.78 | $ 498,042.78 | 8,320 | $ 211,328.00 | $ 223,392.00 | $ 235,872.00 | $ 670,592.00 | $ 670,592.00 | 8,320 | $ 211,328.00 | $ 223,392.00 | $ 235,872.00 | $ 670,592.00 | $ 670,592.00 | $ 670,592.00 |
| Programmer Analyst II | $ 25.11 | 1.056 | $ 26.51 | 1.057 | $ 28.02 | 1.056 | $ 29.59 | 1.051 | $ 26.39 | 1.052 | $ 27.76 | 1.051 | $ 29.18 | 8,320 | 6,240 | $ 220,586.00 | $ 233,159.00 | $ 246,216.00 | $ 699,961.00 | $ 164,677.41 | $ 173,240.63 | $ 182,075.90 | $ 519,993.94 | $ 519,993.94 | 8,320 | $ 220,563.20 | $ 233,126.40 | $ 246,188.80 | $ 699,878.40 | $ 699,878.40 | 8,320 | $ 220,563.20 | $ 233,126.40 | $ 246,188.80 | $ 699,878.40 | $ 699,878.40 | $ 699,878.40 |
| Database Analysis II | $ 15.87 | 1.056 | $ 16.75 | 1.057 | $ 17.71 | 1.056 | $ 18.70 | 1.051 | $ 16.68 | 1.052 | $ 17.55 | 1.051 | $ 18.44 | 8,320 | 6,240 | $ 139,396.00 | $ 147,342.00 | $ 155,593.00 | $ 442,331.00 | $ 104,079.27 | $ 109,491.39 | $ 115,075.45 | $ 328,646.11 | $ 328,646.11 | 6,240 | $ 104,520.00 | $ 110,510.40 | $ 116,688.00 | $ 331,718.40 | $ 331,718.40 | 8,320 | $ 139,360.00 | $ 147,347.20 | $ 155,584.00 | $ 442,291.20 | $ 442,291.20 | $ 442,291.20 |
| Computer Support/Operations II | $ 27.95 | 1.056 | $ 29.51 | 1.057 | $ 31.19 | 1.056 | $ 32.94 | 1.051 | $ 29.38 | 1.052 | $ 30.90 | 1.051 | $ 32.48 | 34,944 | 34,944 | $ 1,031,273.00 | $ 1,090,055.00 | $ 1,151,098.00 | $ 3,272,426.00 | $ 1,026,495.72 | $ 1,079,873.50 | $ 1,134,947.05 | $ 3,241,316.28 | $ 3,241,316.28 | 34,944 | $ 1,031,197.44 | $ 1,089,903.36 | $ 1,151,055.36 | $ 3,272,156.16 | $ 3,272,156.16 | 34,944 | $ 1,031,197.44 | $ 1,089,903.36 | $ 1,151,055.36 | $ 3,272,156.16 | $ 3,272,156.16 | $ 3,272,156.16 |
| Systems Administration | $ 35.55 | 1.056 | $ 37.54 | 1.057 | $ 39.68 | 1.056 | $ 41.91 | 1.051 | $ 37.36 | 1.052 | $ 39.31 | 1.051 | $ 41.31 | 17,472 | 17,472 | $ 655,975.00 | $ 693,366.00 | $ 732,194.00 | $ 2,081,535.00 | $ 652,807.21 | $ 686,753.18 | $ 721,777.60 | $ 2,061,337.99 | $ 2,061,337.99 | 17,472 | $ 655,898.88 | $ 693,288.96 | $ 732,251.52 | $ 2,081,439.36 | $ 2,081,439.36 | 17,472 | $ 655,898.88 | $ 693,288.96 | $ 732,251.52 | $ 2,081,439.36 | $ 2,081,439.36 | $ 2,081,439.36 |
| TOTAL | $ 2,258,569.00 | $ 2,387,308.00 | $ 2,520,996.00 | $ 7,166,873.00 | $ 2,105,785.28 | $ 2,215,286.12 | $ 2,328,265.71 | $ 6,649,337.11 | $ 6,649,337.11 | 7% | $ 2,223,507.52 | $ 2,350,221.12 | $ 2,482,055.68 | $ 7,055,784.32 | $ 7,055,784.32 | 2% | $ 2,258,347.52 | $ 2,387,057.92 | $ 2,520,951.68 | $ 7,166,357.12 | $ 7,166,357.12 | $ 7,166,357.12 | |||||||||||||||
| OVERHEAD | 35% | 50% | 50% | 35% | 47% | 47% | 35% | 47% | 47% | 35% | 50% | 50% | |||||||||||||||||||||||||
| OVERHEAD TOTALS | $ 790,499.15 | $ 1,193,654.00 | $ 1,260,498.00 | $ 3,244,651.15 | $ 737,024.85 | $ 1,041,184.47 | $ 1,094,284.88 | $ 2,872,494.21 | $ 778,227.63 | $ 1,104,603.93 | $ 1,166,566.17 | $ 3,049,397.73 | $ 790,421.63 | $ 1,193,528.96 | $ 1,260,475.84 | $ 3,244,426.43 |
On-Call Labor
| Position | PROPOSED | OPTIMISTIC OBJECTIVE | MOST LIKELY TO NEGOTIATE | ||||||||||||||||||||||||||||||
| 1999 Basic | 1999 Rate | 1999 Total | 2000 Option1 | 2000 Rate | 2000 Total | 2001 Option2 | 2001 Rate | 2001 Total | 1999 Basic | Delta | 1999 Rate | 1999 Total | 2000 Option1 | Delta | 2000 Rate | 2000 Total | 2001 Option2 | Delta | 2001 Rate | 2001 Total | 1999 Option1 | Delta | 1999 Rate | 1999 Total | 2000 Option1 | Delta | 2000 Rate | 2000 Total | 2001 Option2 | Delta | 2001 Rate | 2001 Total | |
| Applics Sys Anal II | 720 | $ 38.10 | $ 27,432.00 | 840 | $ 40.27 | $ 33,826.80 | 960 | $ 42.53 | $ 40,828.80 | 360 | 50% | $ 37.91 | $ 13,649.34 | 360 | 57% | $ 39.89 | $ 14,359.10 | 480 | 50% | $ 41.92 | $ 20,121.89 | 720 | 0% | $ 38.10 | $ 27,432.00 | 720 | 14% | $ 40.27 | $ 28,994.40 | 720 | 25% | $ 42.53 | $ 30,621.60 |
| Progr Analyst II | 840 | $ 39.77 | $ 33,406.80 | 960 | $ 42.04 | $ 40,358.40 | 1080 | $ 44.39 | $ 47,941.20 | 240 | 71% | $ 39.59 | $ 9,500.62 | 240 | 75% | $ 41.64 | $ 9,994.65 | 360 | 67% | $ 43.77 | $ 15,756.57 | 840 | 0% | $ 39.77 | $ 33,406.80 | 840 | 13% | $ 42.04 | $ 35,313.60 | 840 | 22% | $ 44.39 | $ 37,287.60 |
| Database Anal/Prog II | 720 | $ 25.13 | $ 18,093.60 | 840 | $ 26.56 | $ 22,310.40 | 960 | $ 28.05 | $ 26,928.00 | 240 | 67% | $ 25.02 | $ 6,004.57 | 240 | 71% | $ 26.32 | $ 6,316.81 | 360 | 63% | $ 27.66 | $ 9,958.45 | 720 | 0% | $ 25.13 | $ 18,093.60 | 720 | 14% | $ 26.56 | $ 19,123.20 | 720 | 25% | $ 28.05 | $ 20,196.00 |
| Yearly Totals | $ 78,932.40 | $ 96,495.60 | $ 115,698.00 | $ 29,154.53 | $ 30,670.57 | $ 45,836.91 | $ 78,932.40 | $ 83,431.20 | $ 88,105.20 | ||||||||||||||||||||||||
| 3 Year Totals | $ 291,126.00 | $ 105,662.01 | $ 250,468.80 |
Total Hours
| Position | Proposed On-Site Hrs./Yr. | Optimistic Hrs/Yr. | Most Likely Hrs/Yr. |
| Applications Systems Analyst II | 8,320 | 6,240 | 8,320 |
| Programmer Analyst II | 8,320 | 6,240 | 8,320 |
| Database Analysis II | 8,320 | 6,240 | 6,240 |
| Computer Support/Operations II | 34,944 | 34,944 | 34,944 |
| Systems Administration | 17,472 | 17,472 | 17,472 |
| Total Hours | 77,376 | 71,136 | 75,296 |
| 3 Year Total | 232,128 | 213,408 | 225,888 |
| Fringe Rate | $ 1.47 | $ 1.47 | $ 1.47 |
| Total Fringe | $ 113,742.72 | $ 104,569.92 | $ 110,685.12 |
| 3 Year Total | $ 341,228.16 | $ 313,709.76 | $ 332,055.36 |
Material
| Material | 1999 Proposed Costs | 2000 Proposed Costs | 2001 Proposed Costs | Proposed Total | 1999 Esc. | 2000 Esc. | 2001 Esc. | 1999 Opt. Rate | 1999 Optimistic Target | 2000 Opt. Rate | 2000 Optimistic Target | 2001 Opt. Rate | 2001 Optimistic Target | Optimistic Total | 1999 MLN Rate | 1999 Most Likely to Negotiate (MLN) | 2000 MLN Rate | 2000 Most Likely to Negotiate (MLN) | 2001 MLN Rate | 2001 Most Likely to Negotiate (MLN) | Most Likely to Negotiate Total |
| Scheduled | $200,000 | $225,816 | $204,514 | $630,330 | 0.930 | 0.941 | 0.930 | 0.930 | $200,000.00 | 0.941 | $225,816.00 | 0.930 | $204,514.00 | $630,330.00 | 0.930 | $200,000.00 | 0.941 | $225,816.00 | 0.930 | $204,514.00 | $630,330.00 |
| Unscheduled | $151,320 | $190,815 | $245,082 | $587,217 | 1.261 | 1.261 | 1.284 | 1.000 | $120,000.00 | 1.050 | $158,886.40 | 1.100 | $209,961.21 | $488,847.61 | 1.150 | $138,000.00 | 1.150 | $174,018.44 | 1.150 | $219,504.91 | $531,523.34 |
| Minor enhancements | $40,740 | $55,325 | $76,525 | $172,590 | 1.358 | 1.358 | 1.383 | 1.000 | $30,000.00 | 1.000 | $40,740.06 | 0.250 | $13,833.15 | $84,573.21 | 1.200 | $36,000.00 | 1.200 | $48,888.07 | 0.575 | $31,816.25 | $116,704.32 |
| Miscellaneous | $8,536 | $9,108 | $9,898 | $27,542 | 1.067 | 1.067 | 1.087 | 1.050 | $8,400.00 | 1.050 | $8,962.89 | 1.050 | $9,561.09 | $26,923.97 | 1.050 | $8,400.00 | 1.050 | $8,962.89 | 1.050 | $9,561.09 | $26,923.97 |
| TOTAL MATERIAL | $400,596 | $481,064 | $536,019 | $1,417,679 | $358,400.00 | $434,405.35 | $437,869.45 | $1,230,674.80 | $382,400.00 | $457,685.40 | $465,396.24 | $1,305,481.64 |
Fees & Ratio's
| Cost Description | Proposed Shared Ratio | 1999 Proposed | 2000 Proposed | 2001 Proposed | Optimistic Shared Ratio | 1999 Optimistic | 2000 Optimistic | 2001 Optimistic | Most Likely Shared Ratio | 1999 Most Likely to Negotiate | 2000 Most Likely to Negotiate | 2001 Most Likely to Negotiate |
| Target Costs | $ 4,188,692.00 | $ 5,340,333.40 | $ 5,409,027.15 | $ 3,835,174.77 | $ 4,706,123.20 | $ 4,916,586.42 | $ 4,109,815.57 | $ 5,051,150.92 | $ 5,304,754.35 | |||
| Target Fee | 11% | $ 460,756.12 | $ 587,436.67 | $ 594,992.99 | 9% | $ 345,165.73 | $ 423,551.09 | $ 442,492.78 | 9% | $ 369,883.40 | $ 454,603.58 | $ 477,427.89 |
| Optimist Costs | 84% | $ 3,518,501.28 | $ 4,485,880.06 | $ 4,543,582.81 | 84% | $ 3,221,546.80 | $ 3,953,143.49 | $ 4,129,932.59 | 84% | $ 3,452,245.08 | $ 4,242,966.77 | $ 4,455,993.65 |
| Pessimistic Costs | 110% | $ 4,607,561.20 | $ 5,874,366.74 | $ 5,949,929.87 | 115% | $ 4,410,450.98 | $ 5,412,041.68 | $ 5,654,074.38 | 115% | $ 4,726,287.91 | $ 5,808,823.55 | $ 6,100,467.50 |
| Optimistic Fee (Po) | 30% | $ 661,813.34 | $ 843,772.68 | $ 854,626.29 | 30% | $ 529,254.12 | $ 649,445.00 | $ 678,488.93 | 30% | $ 567,154.55 | $ 697,058.83 | $ 732,056.10 |
| Pessimistic Fee | 10% | $ 418,869.20 | $ 534,033.34 | $ 540,902.72 | 20% | $ 230,110.49 | $ 282,367.39 | $ 294,995.18 | 20% | $ 246,588.93 | $ 303,069.05 | $ 318,285.26 |
1999 Costs
| On-Site Support | Proposed Hrs./Yr. | Esc. | 1999 Rate | 1999 Proposed Total | PROPOSED TOTALS | Optimistic Hrs/Yr. | Esc. | 1999 Rate | 1999 Optimistic Total | OPTIMISTIC TOTALS | Most Likely to Negotiate Hrs/Yr. | Esc. | 1999 Rate | 1999 Most Likely Total | MOST LIKELY TO NEGOTIATE TOTALS |
| Application Systems Analyst II | 8,320 | 1.056 | $ 25.40 | $ 211,339.00 | 6,240 | 1.051 | $ 25.28 | $ 157,725.67 | 8,320 | 1.056 | $ 25.40 | $ 211,328.00 | |||
| Programmer Analyst II | 8,320 | 1.056 | $ 26.51 | $ 220,586.00 | 6,240 | 1.051 | $ 26.39 | $ 164,677.41 | 8,320 | 1.056 | $ 26.51 | $ 220,563.20 | |||
| Database Analyst II | 8,320 | 1.056 | $ 16.75 | $ 139,396.00 | 6,240 | 1.051 | $ 16.68 | $ 104,079.27 | 6,240 | 1.056 | $ 16.75 | $ 104,520.00 | |||
| Computer Support/Operations II | 34,944 | 1.056 | $ 29.51 | $ 1,031,273.00 | 34,944 | 1.051 | $ 29.38 | $ 1,026,495.72 | 34,944 | 1.056 | $ 29.51 | $ 1,031,197.44 | |||
| Systems Administration | 17,472 | 1.056 | $ 37.54 | $ 655,975.00 | 17,472 | 1.051 | $ 37.36 | $ 652,807.21 | 17,472 | 1.056 | $ 37.54 | $ 655,898.88 | |||
| On-Call Support | |||||||||||||||
| Application Systems Analyst II | 720 | $ 38.10 | $ 27,433.00 | 360 | $ 37.91 | $ 13,649.34 | 720 | $ 38.10 | $ 27,432.00 | ||||||
| Programmer Analyst II | 840 | $ 39.77 | $ 33,406.00 | 240 | $ 39.59 | $ 9,500.62 | 840 | $ 39.77 | $ 33,406.80 | ||||||
| Database Analyst II | 720 | $ 25.13 | $ 18,095.00 | 240 | $ 25.02 | $ 6,004.57 | 720 | $ 25.13 | $ 18,093.60 | ||||||
| Total Labor | 79,656 | $ 2,337,503.00 | 71,976 | $ 2,134,939.81 | 77,576 | $ 2,302,439.92 | |||||||||
| Fringe | $ 1.47 | $ 113,742.72 | $ 1.47 | $ 104,569.92 | $ 1.47 | $ 110,685.12 | |||||||||
| Overhead | 35% | $ 790,499.15 | 35% | $ 737,024.85 | 35% | $ 778,227.63 | |||||||||
| Material Growth Factors | |||||||||||||||
| Scheduled | $200,000 | $200,000.00 | $200,000.00 | ||||||||||||
| Unscheduled | 1.261 | $151,320 | 1.000 | $120,000.00 | 1.150 | $138,000.00 | |||||||||
| Minor Enhancements | 1.358 | $40,740 | 1.000 | $30,000.00 | 1.200 | $36,000.00 | |||||||||
| Misc | 1.067 | $8,536 | 1.050 | $8,400.00 | 1.050 | $8,400.00 | |||||||||
| Total Material | $400,596 | $358,400 | $382,400 | ||||||||||||
| Total Support Cost | $ 3,642,340.87 | $ 3,334,934.58 | $ 3,573,752.67 | ||||||||||||
| G&A | 15% | $ 546,351.13 | 15% | $ 500,240.19 | 15% | $ 536,062.90 | |||||||||
| Target Cost | $ 4,188,692.00 | $ 3,835,174.77 | $ 4,109,815.57 | ||||||||||||
| Target Fee | 11% | $ 460,756.12 | 9% | $ 345,165.73 | 9% | $ 369,883.40 | |||||||||
| Target Price | $ 4,649,448.12 | $ 4,180,340.50 | $ 4,479,698.97 | ||||||||||||
| Minimum Fee | 90/10 | $ 418,869.20 | 80/20 | $ 230,110.49 | 90/10 | $ 246,588.93 | |||||||||
| Maximum Fee | 70/30 | $ 661,813.34 | 80/20 | $ 529,254.12 | 70/30 | $ 567,154.55 | |||||||||
| Optimistic Cost | 84% | $ 3,518,501.28 | 84% | $ 3,221,546.80 | 84% | $ 3,452,245.08 | |||||||||
| Pessimistic Cost | 110% | $ 4,607,561.20 | 115% | $ 4,410,450.98 | 115% | $ 4,726,287.91 | |||||||||
| Contractor Share Ratio Over | 10% | 20% | 20% | ||||||||||||
| Contractor Share Ratio Under | 30% | 30% | 30% |
Summary
| Cost Description | PROPOSED TOTALS | 1999 OPTIMISTIC TOTALS | 2000 OPTIMISTIC TOTALS | 2001 OPTIMISTIC TOTALS | OPTIMISTIC | 1999 MOST LIKELY TO NEGOTIATE TOTALS | 2000 MOST LIKELY TO NEGOTIATE TOTALS | 2001 MOST LIKELY TO NEGOTIATE TOTALS | OBJECTIVE/ TARGET | REF. | PESSIMISTIC |
| Target Cost | $ 15,212,720 | $ 4,188,692.00 | $ 4,706,123.20 | $ 4,916,586.42 | $ 4,109,815.57 | $ 5,051,150.92 | $ 5,304,754.35 | $ 13,820,942 | |||
| Target Fee | $ 1,673,399 | $ 460,756.12 | $ 423,551.09 | $ 442,492.78 | $ 369,883.40 | $ 454,603.58 | $ 477,427.89 | $ 1,243,885 | |||
| Target Price | $ 16,886,119 | $ 4,649,448.12 | $ 5,129,674.29 | $ 5,359,079.19 | $ 4,479,698.97 | $ 5,505,754.50 | $ 5,782,182.24 | $ 15,064,827 | |||
| Minimum Fee | $ 1,521,272 | $ 418,869.20 | $ 282,367.39 | $ 294,995.18 | $ 246,588.93 | $ 303,069.05 | $ 318,285.26 | $ 829,257 | |||
| Maximum Fee | $ 2,403,610 | $ 661,813.34 | $ 649,445.00 | $ 678,488.93 | $ 567,154.55 | $ 697,058.83 | $ 732,056.10 | $ 1,686,155 | |||
| Optimistic Cost | $ 12,778,685 | $ 3,518,501.28 | $ 3,953,143.49 | $ 4,129,932.59 | $ 3,452,245.08 | $ 4,242,966.77 | $ 4,455,993.65 | $ 11,609,591 | |||
| Pessimistic Cost | $ 16,733,992 | $ 4,607,561.20 | $ 5,412,041.68 | $ 5,654,074.38 | $ 4,726,287.91 | $ 5,808,823.55 | $ 6,100,467.50 | $ 15,894,084 | |||
| Contractor Share Ratio Over | 10% | 20% | |||||||||
| Contractor Share Ratio Under | 30% | 20% |
On-Site Support
Proposed
Hrs./Yr.
1999
Rate
1999
Proposed
Total
Proposed
Totals
Optimistic
Hrs/Yr.
1999
Rate
1999
Optimistic
Total
OPTIMISTIC
TOTALS
OBJ
1999
Rate
1999 Obj
Total
OBJECTIVE
Target
TOTALS
Pessimistic
Application Systems Analyst II
8,3201.056 $ 25.40 211,339$ 8,3201.056 $25.40 $ 211,339 $
Programmer Analyst II
8,3201.056 $ 26.51 220,586$ 8,3201.056 $ 26.51 $ 220,586 $
Database Analyst II
8,3201.056 $ 16.75 139,396$ 4,1601.056 $ 16.75 $ 69,698 $
Computer Support/Operations II
34,9441.056 $ 29.51 1,031,273$ 34,9441.056 $ 29.51 $ 1,031,273 $
Systems Administration
17,4721.056 $ 37.54 655,975$ 17,4721.056 $37.54 $ 655,975 $
On-Call Support
$
Application Systems Analyst II
720 $ 38.10 27,433$ 360 $ 38.10 $ 13,717 $
Programmer Analyst II
840 $ 39.77 33,406$ 240 $39.77 $ 9,545 $
Database Analyst II
720 $ 25.13 18,095$ 240 $ 25.13 $ 6,032 $
Total Labor
79,6562,337,503$ 74,0562,218,164$
$
Fringe
$ 1.47
113,743$
$ 1.47
107,628$
$
Overhead
35%
790,499$
35%
766,105$
$
$
Material Growth Factors
$
Scheduled$200,000200,000$
$
Unscheduled1.261$151,3200.970116,400$
$
Minor Enhancements1.358$40,7400.97029,100$
$
Misc1.067$8,5361.0198,148$
$
Total Material$400,596353,648$
$
Total Support Cost3,642,341$ 3,445,545$
$
$
G&A15%546,351$ 15%516,832$
$
$
Target Cost4,188,692$ 3,962,376$
$
Target Fee11%460,756$ 9%356,614$
$
Target Price4,649,448$ 4,318,990$
$
Minimum Fee 90/10418,869$ 80/20237,743$
$
Maximum Fee 70/30661,813$ 80/20183,410$
$
Optimistic Cost84%3,518,501$ 84%483,410$
$
Pessimistic Cost 110%4,607,561$ 115%3,328,396$
$
Contractor Share Ratio Over10%20%%
Contractor Share Ratio Under30%20%%