week7-1

slomoallkinatings

When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. 

Complete exercise 2 in chapter 13 of the textbook. Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery, determine the following:

  1. Schedule Variance (SV)
  2. Cost Variance (CV)
  3. Schedule Performance Index (SPI)
  4. Cost Performance Index (CPI)

In 250-300 words, answer the questions provided with the exercise. Reflect on the assessment of this project assessment. Should the project continue to improve? 


chapter13

exercise 2

On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

    • 9 years ago
    • 7
    Answer(2)

    Purchase the answer to view it

    NOT RATED
    • week7-1excelproblem.xlsx

    Purchase the answer to view it

    NOT RATED
    • projectassessment.docx