project management w6
5 hours ago 3
w6assignment.docx
w6assignment.docx
W6 Videos
Select the following links and watch your videos for the week.
Project Procurement Management Overview | PMBOK Video Course [09:40]
12.1 Plan Procurement Management | PMBOK Video Course [17:24]
Types of Contracts - Key Concepts in Project Management [06:30]
6.6 Control Schedule | PMBOK Video Course [11:17]
What is Project Risk Control? [04:09]
https://open.umn.edu/opentextbooks/textbooks/project-management chapters 10 and 13
Contract Calculation
1. A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
2. Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption— guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
3. Under option 2, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?
4. In which option did the project assume more of the risk of a cost overrun? Explain.
Rubric Details
Exemplary
Addressed the question completely and thoroughly. Provided additional supporting evidence, demonstrating a full comprehension of subject matter.
18 - 20
Proficient
Addressed the question(s) completely and thoroughly.
16 - 17
Developing
Addressed the majority of the question(s).
14 - 15
Beginning
Addressed minimal portions of the question(s).
12 - 13
Inadequate
Did not address the question(s).
0 - 11
Exemplary
Thorough technical application of course knowledge and content in a complete and concise manner.
18 - 20
Proficient
Technical application of course knowledge and content is mostly accurate, concise and complete.
16 - 17
Developing
Technical application of course knowledge and content is partially accurate, concise and complete.
14 - 15
Beginning
Technical application of course knowledge and content is minimally accurate, concise and complete.
12 - 13
Inadequate
Technical application of course knowledge and content is inaccurate and incomplete.
0 - 11
Exemplary
Original ideas are effectively developed and presented in a logical, sequential order throughout the entire assignment. Includes adequate and appropriate supporting evidence.
18 - 20
Proficient
Original ideas are effectively developed and presented in a logical, sequential order within a majority of the assignment. Includes acceptable supporting evidence
16 - 17
Developing
Original ideas are partially developed and presented in a somewhat logical, sequential order. Inadequate supporting evidence.
14 - 15
Beginning
Original ideas are not present and/or not presented in a logical, sequential order. Organization is difficult to follow throughout the assignment. Lacks supporting evidence.
12 - 13
Inadequate
Little to no original ideas or organization present throughout the entire assignment. Lacks supporting evidence.
0 - 11
Exemplary
Mechanics (spelling, grammar, and punctuation) are flawless, including proficient demonstration of citations and formatting throughout the entire assignment.
18 - 20
Proficient
Mechanics (spelling, grammar, and punctuation) are accurate including demonstration of citations and formatting within a majority of the assignment.
16 - 17
Developing
Partial errors with mechanics (spelling, grammar, and punctuation) including demonstration of citations and formatting within minimal portions of the assignment.
14 - 15
Beginning
Multiple errors with mechanics (spelling, grammar, and punctuation), inaccurate demonstration of citations and formatting.
12 - 13
Inadequate
Assignment is incomprehensible due to multiple errors with mechanics (spelling, grammar, and punctuation). No demonstration of citations or formatting present.
0 - 11
Exemplary
Accurate and applicable use of resources relevant to the subject matter that enhance the overall assignment.
18 - 20
Proficient
Appropriate use of resources relevant to the subject matter.
16 - 17
Developing
Adequate use of resources, not all resources relevant to the subject matter.
14 - 15
Beginning
Minimal use of resources relevant to the subject matter.
12 - 13
Inadequate
No evidence of resources apparent.
0 - 11
w6assignment.docx
W6 Videos
Select the following links and watch your videos for the week.
Project Procurement Management Overview | PMBOK Video Course [09:40]
12.1 Plan Procurement Management | PMBOK Video Course [17:24]
Types of Contracts - Key Concepts in Project Management [06:30]
6.6 Control Schedule | PMBOK Video Course [11:17]
What is Project Risk Control? [04:09]
https://open.umn.edu/opentextbooks/textbooks/project-management chapters 10 and 13
Contract Calculation
1. A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
2. Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption— guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
3. Under option 2, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?
4. In which option did the project assume more of the risk of a cost overrun? Explain.
Rubric Details
Exemplary
Addressed the question completely and thoroughly. Provided additional supporting evidence, demonstrating a full comprehension of subject matter.
18 - 20
Proficient
Addressed the question(s) completely and thoroughly.
16 - 17
Developing
Addressed the majority of the question(s).
14 - 15
Beginning
Addressed minimal portions of the question(s).
12 - 13
Inadequate
Did not address the question(s).
0 - 11
Exemplary
Thorough technical application of course knowledge and content in a complete and concise manner.
18 - 20
Proficient
Technical application of course knowledge and content is mostly accurate, concise and complete.
16 - 17
Developing
Technical application of course knowledge and content is partially accurate, concise and complete.
14 - 15
Beginning
Technical application of course knowledge and content is minimally accurate, concise and complete.
12 - 13
Inadequate
Technical application of course knowledge and content is inaccurate and incomplete.
0 - 11
Exemplary
Original ideas are effectively developed and presented in a logical, sequential order throughout the entire assignment. Includes adequate and appropriate supporting evidence.
18 - 20
Proficient
Original ideas are effectively developed and presented in a logical, sequential order within a majority of the assignment. Includes acceptable supporting evidence
16 - 17
Developing
Original ideas are partially developed and presented in a somewhat logical, sequential order. Inadequate supporting evidence.
14 - 15
Beginning
Original ideas are not present and/or not presented in a logical, sequential order. Organization is difficult to follow throughout the assignment. Lacks supporting evidence.
12 - 13
Inadequate
Little to no original ideas or organization present throughout the entire assignment. Lacks supporting evidence.
0 - 11
Exemplary
Mechanics (spelling, grammar, and punctuation) are flawless, including proficient demonstration of citations and formatting throughout the entire assignment.
18 - 20
Proficient
Mechanics (spelling, grammar, and punctuation) are accurate including demonstration of citations and formatting within a majority of the assignment.
16 - 17
Developing
Partial errors with mechanics (spelling, grammar, and punctuation) including demonstration of citations and formatting within minimal portions of the assignment.
14 - 15
Beginning
Multiple errors with mechanics (spelling, grammar, and punctuation), inaccurate demonstration of citations and formatting.
12 - 13
Inadequate
Assignment is incomprehensible due to multiple errors with mechanics (spelling, grammar, and punctuation). No demonstration of citations or formatting present.
0 - 11
Exemplary
Accurate and applicable use of resources relevant to the subject matter that enhance the overall assignment.
18 - 20
Proficient
Appropriate use of resources relevant to the subject matter.
16 - 17
Developing
Adequate use of resources, not all resources relevant to the subject matter.
14 - 15
Beginning
Minimal use of resources relevant to the subject matter.
12 - 13
Inadequate
No evidence of resources apparent.
0 - 11
- International Assignments
- Organizational Design and Culture
- Diagnotic Techniques NEED QUICK
- 1
- Unless otherwise stated, answer in complete sentences, and be sure to use correct English, spelling and grammar. Sources must be cited in APA format. Your response should be four (4) double-spaced pages; refer to the "Assignment Format" page for specific
- Effects of alcoholism and substance abuse from analysis of different novels
- Assignment 2: Non-for-Profit Financial Reporting Review
- Saint acc303 final exam (Answer 100%)
- BA181 Discussion 1 What is Marketing?
- economic