Scheduling
For an organization, the following project schedule is given. Assume that all times are in days.
TaskPredecessor
Normal
Time
Crash
Time
Crash Cost Slope
(per day)
A
None
7
7
NA
B
A
3
3
NA
C
A
8
4
600
D
A
4
4
NA
E
B
6
5
600
F
C, D
2
2
NA
G
E, F
6
6
NA
H
F
5
3
400
I
G, H
4
4
NA
J
I
2
2
NA
Address the following:
- Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
- Calculate the slack time for each activity.
- Identify the critical path(s).
- Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.
Submission Details:
- Submit your report in a three- to four-page Word document, using APA style.
- Submit it to the Submissions Area by the due date assigned.
- Name your document SUO_MGT3059_W2_ LastName_FirstInitial.doc.
6 years ago 5
Answer(1)
Purchase the answer to view it
- project77.docx
- report13.pdf
other Questions(10)
- Industrial health and hazards
- Non verbal
- I have three critical thinking essays of two page each to be done. The questions are attached below.
- ultimate_writer
- I-Pace Technology
- need it in 10 hours only 2 page total
- Management Accounting
- Hum 176 Media Convergence*****A++ Rated Tutorial Already***** Use as a Guide Paper*****
- DRAFT FIXES
- Write a 500 word double spaced paper