Problem 5- Planning
Problem:Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted AmountBuild formsApril 1$10,000Pour foundationApril 1$50,000May 1$100,000Frame wallsMay 1$30,000June 1$30,000Remaining tasksJuly 1 and beyond$500,000
Define each term in your own words, calculate these values for the above project, and show your work:
- Budgeted cost baseline (make a graph illustrating this one)
- Budget at completion (BAC)
- Planned value (PV) as of May 1
- Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
- SV as of May 1.
- Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
- Schedule performance index (SPI)
- Cost performance index (CPI)
- Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
- Estimate at completion (EAC)
Text
Title: Project Management
Subtitle: https://opentextbc.ca/projectmanagement/
Authors: Adrienne Watt
Publisher: BCcampus Open Education
Publication Date: 2019
Edition: 2nd Edition
4 years ago 20
Answer(1)
Purchase the answer to view it
NOT RATED
- Problem5Planning1.docx
other Questions(10)
- finance
- SOC 490 - ASHFORD - Please don't message me just post the complete class.
- Franchising and the Entrepreneur
- it w2
- Strategic Management in Healthcare Organization
- hfrewjwljdkwncs
- Review Tenet's characteristics of nursing practice. Pick one area and give an example where you exemplified one of these characteristics. Discuss how your work environment can help or hinder your ability to practice effectively within nursing standards.
- only for wordyWhizz.
- psychology
- Forum: "The Passenger" by Marisa Silver