operation management
Question 3:
Sequence the jobs shown below by using a Gantt chart. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine Hours Due Date (days)
1
A/3, B/2, C/2
3
2
C/2, A/4
2
3
B/6, A/1, C/3
4
4
C/4, A/1, B/2
3
a) Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 1)
b) What is the makespan? (Marks 0.5)
c) How much machine idle time is there? (Marks 0.5)
d) How much idle time (waiting time) is there for each job? (Marks 0.5)
e) When is each job delivered? (Marks 0.5)
f) Which department is the bottleneck? (Marks 0.5)
g) Calculate the machine utilization? (Marks 0.5)
6 years ago 3
Answer(0)
other Questions(10)
- Week 1 Discussion - Working to Improve Teaching and Learning
- Temperature Inversion Assignment
- Personal and Professional Social Work Values
- 11.3 Semester GPAs are compared for seven randomly chosen students in each class level at Oxnard University ...
- RAEW Analysis
- 4. What are the requirements that must be met for a regression analysis? What happens if these requirements are violated? ...
- Discuss board
- NSSZ
- 11.52 A statistics practitioner wants to test the following hypotheses with σ = 20 and n = 100 ...
- Discussion 6651