Prepare an evening meal at home. This would include a multicourse dinner with varying times for course preparation. All items are to be done at a certain time with limited resources (microwave, stove, etc.). Prepare a Gantt chart and/or network diagram to list the critical path and dependencies to the solution.
Hint: MS project and visio will be helpful in this solution.
Attached is an example of how It should be when its fully done.