Mike was hired as a project manager to install hardwood floors for the company Awesome Floor and Tile. They will be installing new flooring into a local office building. Mike comes up with the list of work and estimates the time. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) are estimated in a given table. Following are the activities that are required to install the hardwood floor in the offices:

  • Activity 1: Measure      office room dimensions
  • Activity 2: Estimate      cost
  • Activity 3: Material      requisition
  • Activity 4: Workforce      requisition
  • Activity 5: Special      tool requisition
  • Activity 6: Installation
  • Activity 7: Inspection      and customer acceptance

Activity 2 starts immediately after Activity 1.
 

Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2.
 

Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed.
 

The carpet installation project is complete after Activity 7 is completed.
 

Your assignment is to write a report that addresses the following:
 

If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

  

Activities


OT


MT


PT

 

Activity 1


2


3


4

 

Activity 2


3


6


9

 

Activity 3


4


8


12

 

Activity 4


6


8


10

 

Activity 5


8


10


12

 

Activity 6


10


14


18

 

Activity 7


4


6


8

You must also do the following:

  • Determine and explain the expected completion time and      the variance for each activity.
  • Determine and explain the total project completion time      and the critical path for the project.
  • Determine and explain Early Start (ES), Early Finish      (EF), Late Start (LS), and slack for each activity.
  • What is the probability that this project will be      finished in 40 days or less? Explain.
  • Define how to gather the project requirements.
  • Analyze whether there are any potential changes      that could impact overall project schedule and project finishing time.
  • Explain the best methods for managing the change      requests and what kind of process this project should involve.
  • Analyze implications of changes in project scheduling.
  • Explain the best methods for managing the      change requests and what kind of process this project should involve.
  • Evaluate applications of project management techniques      in terms of the firm’s business operational goals and requirements
    • 6 years ago
    MGMT412 Unit 5 Assignment
    NOT RATED

    Purchase the answer to view it

    • MGMT412Unit5Assignment.docx