Activity 1.1
Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:
ActivityDescriptionPredecessorsDuration (Days)ASite selectionNone4BBuy concessionsA4CRent facilitiesA2DBuild standsA5EGenerator & wiring installationC2FSecurityB4GLighting installationE2HSound system installationE, F2IStage constructionD3JTear downG, H, I4
- Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
- Identify all paths through the network. Which is the critical path?
- Which activities have slack time?
- Identify all burst activities and merge activities.
5 years ago 5
Answer(1)
Purchase the answer to view it
- Activity1.1.edited.docx
other Questions(10)
- professor2013
- response to essay
- You are hired as a consultant in City X and are charged with the responsibility of creating a plan to deal with the multiple daytime robbery attacks in your area. Police officers have been able to obtain limited information for each robbery. Your first or
- ITNA 454 Project 1
- Algorithms Homework - Computer Science
- ethics
- In January 2010, three California Condors died when they accidentally ate lead ammunition used to kill the animals they were...
- Tuition reimbursement - Must be original work
- Harmon Household Products,lnc
- COMPARE THEORIES