592W2
a year ago 1
592w2.docx
PROJ592_Scope_Statement_Sample_v1.docx
592w2.docx
You will be completing the following components of your Course Project Part 2 deliverables. This deliverable is worth 100 points.
1. Scope Statement (40 points)
2. Detailed Resource Loaded Baseline WBS and Schedule (40 points)
3. RACI Chart (20 points)
|
Component Deliverable |
Tasks |
|
Scope Statement |
1. Create the project scope statement, which is an extended version of your project proposal. It primarily aims to clarify two aspects of the project—setting the acceptance criteria so you can have a smooth closure at the end of the project and rules and regulations to decrease the ambiguity in the team while managing the project. For your convenience, the Project Scope Statement Sample document is available in the Project Resources and Naming Conventions section. 2. Submit the scope statement in a one- to two-page Word document. |
|
Detailed Resource Loaded Baseline WBS and Schedule |
1. This is the part to extend the preliminary tasks (approximately 10 lines) you had in Part 1. Using your scope statement, input your work packages into MS Project. The WBS should be created in MS Project, following standard indent and hanging indent practices used in WBS creation. The WBS and schedule must have proper grouping, indenting, and coding for approximately 25 to 40 line items. Review the Project Sample in the Project Resources and Naming Conventions section for an example of a well-developed work breakdown structure a. Create the WBS column. Hover on the Task Name column and right-click for the drop-down menu so you can select Insert Column, and then type in WBS manually and select the WBS to have your outline numbers. b. Review your duration. (Hint: Please remember, do not touch the bold task. Manage the content of the bold, also known as summary tasks, because those tasks are aggregated automatically.) c. Review your predecessors. This is to mimic the conditional tasks we have in real-life. As seen in the following screenshot, if you put the number 4 as a predecessor for line 5, line 5 cannot start before line 4 finishes first. d. Create the critical path by selecting Gantt Chart Format>Critical Tasks. This is to know which tasks of yours (usually color coded in red bars on the Gantt Chart) are more critical (that means zero free or slack time) so you can be more cautious (with contingency plans) about them. 2. Baseline Resource Plan a. Define your resources by selecting Resource>Team Planner>Resource Sheet. You do not fill each cell. Some are being used as-is. You may want to work on the blue zone. Also, 100% means one person, 200% means two people, so forth. Once you are done, you may want to go back by selecting on Team Planner>Gantt Chart. b. Assign your resources task by task. Hover on the task (not summary task, which are the bold ones) and right-click to select Assign Resources. Then review the units. You will see the cost will be populated automatically. Then select Assign or just close the window. 3. Submit the WBS and Schedule in either a MS Project file or as a screenshot. |
|
RACI Chart |
1. Develop a RACI chart, responsibility assignment matrix, for the project according to the description in Section 10: Tools and Techniques and illustrated in Figure 10-18 of the Process Groups: A Practice Guide. 2. Submit the RACI Chart in a Word or Excel document. |
image1.png
image2.png
image3.png
PROJ592_Scope_Statement_Sample_v1.docx
Project Charter
Project Charter
V 2.0
Scope Statement Sample
|
Project Name |
|
Project Number |
|
|
Project Manager |
|
Prioritization |
|
|
Owner(s) |
|
Statement of Work—Project Description andProject Product |
This section is a detailed amplification of the project statement of work (SOW) and mission from the project charter. This also includes how you intend to accomplish the project. “We intend to do this… And here are the steps we intend to use to accomplish the project.” This section is a detailed amplification of the SOW product description from the project charter. What will the product of the project look like, or what should it be able to do when completed? |
|
|
|
Project Deliverables |
What are the tangible outputs or services of this project? What big picture items will have to be created or performed in order to accomplish the statement of work? These are the deliverables to be found in the work breakdown structure (WBS). |
|
|
|
||
|
Project Objectives |
What are the cost, schedule, and quality objectives of this project? |
|
|
Project Assumptions |
What are the assumptions on which the project is based on? |
|
|
Project Constraints |
What are the major limiting factors that affect the project? |
|
|
Exclusions |
What are the boundaries of the project? What is to be included, and what is to be excluded from the project? |
|
|
Acceptance Criteria |
What must the product be able to do when completed to be acceptable to the customer? What standards or regulations must the product meet? What performance specifications must the product meet to be acceptable to the customer? |
|
|
|
||
|
|
||
592w2.docx
You will be completing the following components of your Course Project Part 2 deliverables. This deliverable is worth 100 points.
1. Scope Statement (40 points)
2. Detailed Resource Loaded Baseline WBS and Schedule (40 points)
3. RACI Chart (20 points)
|
Component Deliverable |
Tasks |
|
Scope Statement |
1. Create the project scope statement, which is an extended version of your project proposal. It primarily aims to clarify two aspects of the project—setting the acceptance criteria so you can have a smooth closure at the end of the project and rules and regulations to decrease the ambiguity in the team while managing the project. For your convenience, the Project Scope Statement Sample document is available in the Project Resources and Naming Conventions section. 2. Submit the scope statement in a one- to two-page Word document. |
|
Detailed Resource Loaded Baseline WBS and Schedule |
1. This is the part to extend the preliminary tasks (approximately 10 lines) you had in Part 1. Using your scope statement, input your work packages into MS Project. The WBS should be created in MS Project, following standard indent and hanging indent practices used in WBS creation. The WBS and schedule must have proper grouping, indenting, and coding for approximately 25 to 40 line items. Review the Project Sample in the Project Resources and Naming Conventions section for an example of a well-developed work breakdown structure a. Create the WBS column. Hover on the Task Name column and right-click for the drop-down menu so you can select Insert Column, and then type in WBS manually and select the WBS to have your outline numbers. b. Review your duration. (Hint: Please remember, do not touch the bold task. Manage the content of the bold, also known as summary tasks, because those tasks are aggregated automatically.) c. Review your predecessors. This is to mimic the conditional tasks we have in real-life. As seen in the following screenshot, if you put the number 4 as a predecessor for line 5, line 5 cannot start before line 4 finishes first. d. Create the critical path by selecting Gantt Chart Format>Critical Tasks. This is to know which tasks of yours (usually color coded in red bars on the Gantt Chart) are more critical (that means zero free or slack time) so you can be more cautious (with contingency plans) about them. 2. Baseline Resource Plan a. Define your resources by selecting Resource>Team Planner>Resource Sheet. You do not fill each cell. Some are being used as-is. You may want to work on the blue zone. Also, 100% means one person, 200% means two people, so forth. Once you are done, you may want to go back by selecting on Team Planner>Gantt Chart. b. Assign your resources task by task. Hover on the task (not summary task, which are the bold ones) and right-click to select Assign Resources. Then review the units. You will see the cost will be populated automatically. Then select Assign or just close the window. 3. Submit the WBS and Schedule in either a MS Project file or as a screenshot. |
|
RACI Chart |
1. Develop a RACI chart, responsibility assignment matrix, for the project according to the description in Section 10: Tools and Techniques and illustrated in Figure 10-18 of the Process Groups: A Practice Guide. 2. Submit the RACI Chart in a Word or Excel document. |
image1.png
image2.png
image3.png
PROJ592_Scope_Statement_Sample_v1.docx
Project Charter
Project Charter
V 2.0
Scope Statement Sample
|
Project Name |
|
Project Number |
|
|
Project Manager |
|
Prioritization |
|
|
Owner(s) |
|
Statement of Work—Project Description andProject Product |
This section is a detailed amplification of the project statement of work (SOW) and mission from the project charter. This also includes how you intend to accomplish the project. “We intend to do this… And here are the steps we intend to use to accomplish the project.” This section is a detailed amplification of the SOW product description from the project charter. What will the product of the project look like, or what should it be able to do when completed? |
|
|
|
Project Deliverables |
What are the tangible outputs or services of this project? What big picture items will have to be created or performed in order to accomplish the statement of work? These are the deliverables to be found in the work breakdown structure (WBS). |
|
|
|
||
|
Project Objectives |
What are the cost, schedule, and quality objectives of this project? |
|
|
Project Assumptions |
What are the assumptions on which the project is based on? |
|
|
Project Constraints |
What are the major limiting factors that affect the project? |
|
|
Exclusions |
What are the boundaries of the project? What is to be included, and what is to be excluded from the project? |
|
|
Acceptance Criteria |
What must the product be able to do when completed to be acceptable to the customer? What standards or regulations must the product meet? What performance specifications must the product meet to be acceptable to the customer? |
|
|
|
||
|
|
||
- can i get help with that ??
- ACC 220 Week 7 CheckPoint Budgets Matrix
- Critical Thinking in an Online Course
- BUS 303 Week 5 Human Resources Management
- geo 100 Q&A Format
- CJA 394 Week 3 Learning Team Assignment Court Management Executive Summary
- CJA 394 Week 1 Individual Assignment Criminal Justice Trends Evaluation
- BIS 155 Week 4 iLab (Create Address Labels 1,2,3) Discussion and Quiz
- ACCT 300 - Problem 6-18 guide
- Biographical Sketch of Howard Thurman