Value stream map

Mustan240sx
WSMAssignment-2.pdf

IT184 - Advanced Manufacturing Technology

Fall 2018

Value Stream Mapping Assignment

ABC Inc. is in the business of manufacturing knives. The company works 2

shifts of 8 hours each for 5 days in a week. Each shift has a 30 min lunch

break and two 15 min breaks. ABC Inc’s sole customer is San Diego

Knives. The daily demand for knives is 20,000. ABC, Inc. delivers knives to

San Diego Knives once a day. The MRP system at ABC, Inc. conveys this

daily order to all stages including the supplier. The supplier delivers 20,000

sheets of metal once in two weeks. Each sheet can make 10 knife blades.

● The first step is stamping to obtain the blades from the sheet. 10

blades are produced in 10 seconds. The changeover time is 2 hours.

● The next step is grinding where 10 blades are processed in 30

seconds with a changeover time of 30 minutes. There is an

inventory of 20,000 blades between stamping and grinding.

● The next step in the sequence is cutting to obtain the serrations on

the knife. This process takes 50 seconds for 10 blades. The

changeover time is 15 minutes. There is an inventory of 5,000

blades between grinding and cutting.

● Now, the blades go through a surface treatment operation where 10

blades are process simultaneously in 60 seconds. The changeover

time is 20 minutes. There is an inventory of 5,000 blades between

cutting and surface treatment.

● The blades are now assembled into the handles. This process takes

10 seconds for each knife. There is an inventory of 10,000 blades

between the surface treatment stage and the assembly.

● Once assembled, the knives are packed and shipped. The packing

process takes 20 seconds for each knife. There is an inventory of

10,000 knives between the assembly and packing stages.

Every stage has a single operator. Determine the following:

1. Current-state Map

2. Future-state Map - explain the rationale for the proposed improvements.