Project Status Summary (Percentage Complete: 25%) :

• Currently, we are still working on finishing the base chess game. We are finishing up win conditions as well as piece-movement. We have also started getting the web-application setup to host this base chess game. We have also started building out a visual GUI for the website. This week we plan on finishing the game and having the website ready for and or hosting the game.

Lab Time and Accomplishments this week built on last week’s work

• No Lab Time this week.

• Furthered development of base chess game in Unity

• Began developing the front-end interface for the web-application

Next week’s SMART goals:

• Finalize base Chess application in Unity (Robert).

• Continue working on web-application (Michael, Izabella).

• Start updating our report to reflect our recent work (Ali).

Action Plan (task responsibility, timing, help needed):

• Finalize the base chess game

• Continue front-end and back-end development for the web-application

• Write our progress to our report

Open Issues, Risks, Change Requests:

• Finalizing our basic chess game

• Setup webGL with react

Milestones and Deliverables:

Milestones /

Deliverables

Planned Date

Forecasted Date

Actual Date

Status

Note

First prototype of web application

2/6

2/13

3/4

On schedule

Development has started in tandem with the chess application. We already a prototype, we will now begin iterating.

First Chess Game

2/6

2/20

3/4

Behind schedule

We are only missing a few pieces, currently movement and end condition checks