Week 3 Assignment Quiz
QUESTION 1
1. Failure to quantify project objectives raises the risk that the project won’t achieve the?
|
|
|
Statement of work |
|
|
|
Project plan |
|
|
|
Customer’s expectations |
|
|
|
Project control |
QUESTION 2
1. How do we know if the project is successful. One aspect is validating scope. Scope validation is the process of the project customer accepting?
|
|
|
Project deliverables |
|
|
|
Project scope |
|
|
|
Project WBS |
|
|
|
Project inspection |
QUESTION 3
1. The change control system should do several things for the project management team including document all change requests, track each change requests document approval levels required for change, and
|
|
|
Restate scope requirements |
|
|
|
Indicate how change impacts communications |
|
|
|
Provide the status of each change request |
|
|
|
How change impacts quality |
QUESTION 4
1. The approach maps ideas to show the relationship among requirements and the difference between requirements.
|
|
|
Mind Mapping |
|
|
|
Context Diagram |
|
|
|
Network Diagram |
|
|
|
Funding limits |
QUESTION 5
1. These diagram shown the relationship between elements of an environment.
|
|
|
Mind Mapping |
|
|
|
Context Diagram |
|
|
|
Network Diagram |
|
|
|
Funding limits |
QUESTION 6
1. There are seven key processes associated with project time management. The seven processes are interdependent on one another and on the _________ of the project?
|
|
|
Schedule |
|
|
|
Activities |
|
|
|
Estimations |
|
|
|
Life cycle |
QUESTION 7
1. The planning technique that focuses on the immediate while considering the big picture and utilizes iterations of planning is called?
|
|
|
Waterfall method |
|
|
|
Rolling wave |
|
|
|
Agile project management |
|
|
|
Scrum |
QUESTION 8
1. Part of the process of sequencing events is the development of network diagrams. A network diagram shows the relationship of the work activities and how the activities progress start to finish. What is the most common method for arranging work visually into a network diagram?
|
|
|
Activity on node |
|
|
|
Activity on arrow |
|
|
|
Precedence diagramming method |
|
|
|
Activity sequencing |
QUESTION 9
1. These dependencies are the natural order of activities.
|
|
|
Mandatory dependencies |
|
|
|
Discretionary dependencies |
|
|
|
External dependencies |
|
|
|
Internal dependencies |
QUESTION 10
1. What is the most accurate project estimating methods for time and cost?
|
|
|
Published estimating data |
|
|
|
Bottom-up estimating |
|
|
|
Parametric estimating |
|
|
|
Sequencing estimation |