Network Diagram

Complete Exercise 3, a through d, on page 229 of the course textbook. Consider Figure 5-28. All duration estimates are in days, and the network proceeds from Node 1 to Node 9. A. Draw an AOA network diagram representing the project.

· Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated duration. Add a tenth node with one day with your last name.

· Identify all the paths on the network diagram and note how long they are.

· What is the critical path for this project, and how long is it?

· What is the shortest possible time it will take to complete this project?