EarthMover Project
"Current project has a critical path of 30 days. You must complete the job by at least day 26!"
NORMAL CRASH
Activity Time (weeks) Cost Best Time (weeks) Activity Crash Cost ($) Time reduction (weeks) Crash Cost ($/week)
A 6 $ 80,000 5 $ 20,000 1 $ 20,000
B 4 $ 100,000 4 $ - 0 0
C 3 $ 50,000 2 $ 50,000 1 $ 50,000
D 6 $ 150,000 3 $ 150,000 3 $ 50,000
E 3 $ 180,000 2 $ 70,000 1 $ 70,000
F 10 $ 300,000 7 $ 180,000 3 $ 60,000
G 2 $ 100,000 2 $ - 0 0
H 6 $ 450,000 5 $ 350,000 1 $ 350,000
I 8 $ 350,000 4 $ 300,000 4 $ 75,000
Goal to complete by: 30 weeks <---- Change this goal from the currect 30 weeks to the new 26 week target!
Objective Function Then run SOLVER to find the least expensive way to reach your goal !!!
Min cost to CRASH $ - 0
Xi = earliest finish time for activity i EF-limit Yi = the amount of time activity i is crashed Max crash available New time
A 6 = 6 A 0 <= 1 A 6
B 10 = 10 B 0 <= 0 B 4
C 9 = 9 C 0 <= 1 C 3
D 16 = 16 D 0 <= 3 D 6
E 13 = 13 E 0 <= 1 E 3
F 20 = 20 F 0 <= 3 F 10
G 22 = 22 G 0 <= 0 G 2
H 28 = 28 H 0 <= 1 H 6
I 30 = 30 I 0 <= 4 I 8
Note: EF = EF of previous + t Non-negativity constraints
New t = Original t - Crash
New Finish time Goal
H 28 <= 30
I 30 <= 30