| | banking software |
| | name | duration | start | finish | predecessors | resources |
| | idea generation | 5 days |
| 1 | proposal | 2 days | 1/6/20 | 3/6/20 | 1 | project manager |
| 2 | concept | 2 days | 3/6/20 | 5/6/20 | 2 | project manager |
| 3 | initiation | 1 day | 5/6/20 | 6/6/20 | 3 | project manager |
| | pre-feasibility | 4 days |
| 4 | initial investigation | 1 day | 6/6/20 | 7/6/20 | 4 | project manager |
| 5 | initial assessment | 1 day | 7/6/20 | 8/6/20 | 5 | project manager, software developers |
| 6 | evaluation | 1 day | 8/6/20 | 9/6/20 | 6 | project manager, software developers |
| 7 | research | 1 day | 9/6/20 | 10/6/20 | 7 | software developer |
| | feasibility | 5 days |
| 8 | project definition | 3 days | 10/6/20 | 13/6/2020 | 8 | project manager, business analyst, project sponsors |
| 9 | business case | 1 day | 13/6/2020 | 14/6/2020 | 9 | project manager, business analyst, project sponsors |
| 10 | authorization | 1 day | 14/6/2020 | 15/6/2020 | 10 | project manager, business analyst, project sponsors |
| | development and execution | 17 days |
| 11 | implementation | 5 days | 15/6/2020 | 20/6/2020 | 11 | project manager, software developers |
| 12 | project realization | 2 days | 20/6/2020 | 22/6/2020 | 12 | project manager, software developers |
| 13 | production | 3 days | 22/6/2020 | 25/6/2020 | 13 | project manager, software developers |
| 14 | build | 3 days | 25/6/2020 | 28/6/2020 | 14 | project manager, software developers |
| 15 | develop and testing | 4 days | 28/6/2020 | 2/7/20 | 15 | project manager, software developers |
| | commissioning | 5 days | | | | project manager, software developers |
| 16 | alpha test | 2 days | 2/7/20 | 4/7/20 | 16 | project manager, software developers |
| 17 | beta test | 2 days | 4/7/20 | 6/7/20 | 17 | project manager, software developers |
| 18 | validation | 1 day | 6/7/20 | 7/7/20 | 18 | project manager, project sponsor |
| | launch | 5 days |
| 19 | release | 1 day | 7/7/20 | 8/7/20 | 19 | project manager, project sponsor |
| 20 | implementation | 2 days | 8/7/20 | 10/7/20 | 20 | project owner, project sponsor |
| 21 | handing over | 1 day | 10/7/20 | 11/7/20 | 21 | project owner, project sponsor |
| 22 | acceptance by client | 1 day | 11/7/20 | 12/7/20 | 22 | project owner, project sponsor |
| | post-implementation review | 5 days |
| 23 | business review | 2 days | 12/7/20 | 14/7/2020 | 23 | IT auditor, project owner, project sponsor |
| 24 | audit | 3 days | 14/7/2020 | 17/7/2020 | 24 | IT auditor, project owner, project sponsor |
| 25 | post-project review | 2 days | 17/7/2020 | 19/7/2020 | 25 | IT auditor, project owner, project sponsor |