answer the 4 question attach
Project Procurement Management Chapter 12: Administer Procurements
Week 12
So, Just When Does Administering the Procurement Begin? When the contract signed? That’s the common belief.
But, we know different because . . . Administering the Procurement BEGINS when . . .
“Project procurement management begins at the point WHEN the new project is initiated and detailed decisions are starting to be made as to what portion of the project will be performed with one’s own staff, and what portion will be sent to another company for performance.”
(PPM, p.207)
When Does Procurement Management Begin
BUT . . . “The MOST CRITICAL part of project procurement management is the planning that should take place before any contract is solicited, evaluated, and awarded. If not planned well, procurement management can be a bumpy road. If planned well, procurement management can add immensely to the successful implementation of any project.” (PPM, p.207)
Contract Administration = A [Recognized] Management System
Think EVM, Earned Value Management:
The systematic measurement of Planned and Actual Cost measured in terms of: - “value” – the portion of work completed to date, and
- “time” – the duration used to do so
When Does Procurement Management Begin
The Fundamentals of EVM Established by the Department of Defense (DOD) in 1962 First put in place in the Minuteman Missile program, spanning multiple
years and agencies
Broke the project into “manageable” pieces – easier to track performance
Added respective budget component to each piece
The Results Applied to over 800 LARGE Government programs to date
Found that there is NO improvement in project performance between the 15% to 85% completion period . . . In fact, it declines!
Earned Value Management
The Basics of EVM Planned Value (PV): The approved budget for the work scheduled to be
completed by a specified date - Also referred to as the Budgeted Cost of Work Scheduled (BCWS)
Earned Value (EV): The approved budget for the work actually completed by the specified date - Also referred to as the Budgeted Cost of Work Performed (BCWP)
Actual Cost (AC): The costs actually incurred for the work completed by the specified date - Also referred to as the Actual Cost of Work Performed (ACWP)
Schedule Variance (SV): The difference between the amounts budgeted for the work you actually did and for the work you planned to do - Shows how much work is ahead of or behind approved schedule
Cost Variance (CV): The difference between the amount budgeted and the amount actually spent for the work performed - Shows by how much work is under or over approved budget
Earned Value Management
The Basics of EVM Schedule Performance Index (SPI): The ratio of the approved budget for
the work performed to the approved budget for the work planned - Reflects the relative amount the project is ahead of or behind schedule, A/K/A the project’s schedule efficiency, changes each period!
Cost Performance Index (CPI): The ratio of the approved budget for work performed to what you actually spent for the work. - Reflects the relative value of work done compared to the amount paid, A/K/A the project’s cost efficiency changes each period!
Estimate at Completion (EAC): Current estimate of the total cost of the task/project when finished
Estimate to Complete (ETC): Current estimate of the amount of funds required to complete all work still remaining on the task/project
Earned Value Management
Earned Value Management
Mathematical Definitions of EVM Schedule Variance (SV):
Earned Value (EV) – Planned Value (PV) Cost Variance (CV):
Earned Value (EV) – Actual Cost (AC) Schedule Performance Index (SPI):
Earned Value (EV) / Planned Value (PV) Cost Performance Index (CPI):
Earned Value (EV) / Actual Cost (AC)
Earned Value Management
Analysis of EVM Curves
Problems on ALL Fronts Problem on COST Aspect
Problem on Schedule AspectNO Problems
Cost Estimate Analysis Progress Payments
The periodic payment (generally monthly) for actual work completed
Based upon a predetermined “Schedule of Values”
Reduces the Risk of non-performance or under-performance
Milestone Payments
Payment based upon achieving a “Predetermined Specific Deliverable” which triggers payment
Based upon a predetermined “Schedule of Values” May Increase the Risk of non-performance or under-performance . . .due to lack of cash flow issue
Paying for Things
The “War Room” Space dedicated to the project and its administration
Contains ALL Project Management and Project Procurement Data
Can be used to hold meetings
May be the same as the office of the PM or adjacent thereto
The Churchill Display Wall
Depiction of the following items for all to see and of which to be reminded:
Project War Rooms and Status Walls
- Diagram of the Project (site, system, layout)
- Near-term Objectives List - Work Breakdown Structure (WBS) - Major Critical Supplier Charts - Top 10 Concerns – the “Worry List”
- Project Master Schedule (and other schedules)
- Project “Action Item” List - Personnel Loading/Phasing Charts - Earned Value Metrics
Who is Contracted to Whom “Privity of Contract: That connection or relationship which exists between two or more contracting persons.” (Black’s Law Dictionary. PPM, p.218)
Privity of Contract
Project Procurement Management, Figure 12.3: Privity of Contract Issues
“Changes in project scope are inevitable. Likely, no project could ever expect to completely eliminate all changes . . . the project would never get done.”
(PPM, p.220)
“As the project progresses through the implementation phase, the project management must identify, evaluate, communicate, control, and coordinate all project changes.” (PPM. P.221)
The Cost of Incorporating Changes INCREASES Over Time
The Cost of Changes
Project Procurement Management, Figure 12.4: The Cost of Incorporating Changes
The Cost of Incorporating Changes INCREASES Over Time Another Perspective:
The Cost of Changes
The Cost of Incorporating Changes INCREASES Over Time Another Perspective:
The Cost of Changes
Constructive Changes – The MOST Dangerous Type Definition:
A constructive change is sometimes called a "change by implication" and occurs when the Government, by its actions, changes the contract without specifically adhering to the requirements of the "Changes" clause. A constructive change order has been defined as an oral or written act or omission by the Contracting Officer or other authorized Government official which is of such a nature that it has the same effect as a formal written change order under the Changes clause.
Effect:
Such a constructive change, which increases the burden on the contractor, is compensable. [By means of a Request for Equitable Adjustment]
Why? The contractor has NO Choice but to comply! And, generally has to wait for compensation following the REA process.
Changes
Project Procurement Management Chapter 12: Administer Procurements
PPM Week 12 Discussion Question
Question 12: Is earned value management a procurement management or project management tool? Explain your answer.?
Project Procurement Management Chapter 12: Administer Procurements
Week 12
- Slide Number 1
- Slide Number 2
- Slide Number 3
- Slide Number 4
- Slide Number 5
- Slide Number 6
- Slide Number 7
- Slide Number 8
- Slide Number 9
- Slide Number 10
- Slide Number 11
- Slide Number 12
- Slide Number 13
- Slide Number 14
- Slide Number 15
- Slide Number 16
- Slide Number 17
- Slide Number 18