answer the 4 question attach
Project Procurement Management Chapter 08: Plan Procurements (2 of 2)
Contract Negotiations Chapter 08: U.S. Federal Government
Contract Negotiations – Best Practices
Week 8
Questions and Issues: Do we have past experience dealing wit similar purchases (procurements)? Will we want to “pre-qualify” potential suppliers prior to sending out the solicitation?
What is the dependability and stability of project funding?
Will there be political pressure on the award of major procurements? Are there special considerations incorporated in the prime contract which must be addressed in selected procurements which will impact solicitation planning?
And… Is there a requirement to place a parentage of procurement awards with a special class of business?
Answers?
Selecting Proper Suppliers
Advertise, Solicit, Negotiate, Compete Advertise – On websites, through trade organizations and journals Solicitation – The Formal ITB / IFB, RFQ, RFP and even an RFI Negotiate – Negotiate the SOW within the RFP for a Price Compete – Seek multiple sellers / “offerors”
The Buying Approach
The Buying Approach
The Buying Approach
The Buying Approach
Two-sided Definition: Business v. Technical The “Business” Definition The Scope of Work (SOW) for what will be procured
“A description of the product or service to be procured under a contract; a statement of requirements,” (PPM, p.149) Considered to be the single-most important document in the procurement process!!!!!! May be the ONLY “official” description of the work.
Terms & Conditions (From Week 4) The collection of language that makes up a written contract A “Term” addresses a specific subject – e.g., price, payment, disputes
Written in / as “Contractual Clauses” A “Condition” either activates or suspends a term
Condition Precedent activates a term Condition Subsequent suspends a term
Whose are used? Do they flow down to subcontractors? What do they include?
Defining the “What” We Plan to Buy
Terms and Condition Categories to Include
Defining the “What” We Plan to Buy
Project Procurement Management, Figure 8.2: Contract/Subcontract Clauses . . . A Small Sampling
Two-sided Definition: Business v. Technical The “Business” Definition The Requirements for Management Oversight
The most critical component: A fully-defined INTERNAL working Schedule (CPM-based)
Require: - An Initial Baseline Schedule
- Monthly Updates
- Tie to the Monthly Progress Payments
Why? Because obtaining an updated schedule is one of the most difficult items to obtain from sellers!
Defining the “What” We Plan to Buy
Two-sided Definition: Business v. Technical The “Technical” Definition The Specifications
“The purpose of technical specifications is to define the features and functions that the purchased product [or service] will perform, the physical attributes, limitations, design requirements, constraints, and the environment in which the product will be used [or service provided].” (PPM, p.155)
Two Types of Specifications: - Detail Design Specification: Of WHAT the product/service is comprised
Example: A new car – e.g., tire size, color, number of seats/doors, engine size, etc.
- Performance Specifications: Statement for HOW the service will function
Example: A new car – e.g., carry certain weight/number of passengers, attain a specific speed, achieve certain MPG, etc.
Defining the “What” We Plan to Buy
Three types of Procurement Competition Full and Open Competition
“Anyone can Bid/Propose”
Preferred by Governmental entities
May increase procurement risk – May end up with unqualified entity Limited Competition
“Among Pre-qualified Bidders”
May require a two-step process: - Determination of qualified bidders
- Pricing competition among those qualified
Procurement Competition
Three types of Procurement Competition Selected [sole] Source(s)
Limited Government Opportunity – requires prior approval and unusual circumstances
Typically a Private Sector vehicle
From a specific category of suppliers, or from a preferred vendor
May increase procurement risk – Monopolistic Pricing????
Procurement Competition
Project Procurement Management Chapter 08: Plan Procurements (2 of 2)
PPM Week 8 Discussion Question
Question 08a: What is the difference between a contract scope of work (SOW) and a project work breakdown structure (WBS)? Which elements are common/disparate to each?
Best Practices for Planning Negotiations with the Federal Government: Understand how to influence Federal Government buying appropriately
and ethically Having an acceptable cost estimating and accounting system
Understanding the legal framework of Federal Government contracts
Understanding the Truth in Negotiation Act (TINA) Knowing the key Federal Government acquisition thresholds
Federal Contract Negotiations
Contract Negotiations, p.173
How to Influence Federal Government Buyers APPROPRIATELY and ETHICALLY:
Influencing the Federal Government
Contract Negotiations, p.173-174
The Do’s: Create a liaison office Hire REGISTERED Lobbyists
Join Professional Advocacy Groups
Participate in Industry Trade Associations
Write articles / Make presentations
Serve on Advisory Boards and NGOs
Perform well on current Contracts
Develop relationships with Small Businesses
Establish Strategic Alliances and Teaming Agreements
Create an advisory group of retires Federal procurement experts
Hire former senior Government procurement professionals
How to Influence Federal Government Buyers APPROPRIATELY and ETHICALLY:
Influencing the Federal Government
Contract Negotiations, p.174
The Don’ts: Offer a job to a Government official
currently involved in a procurement related to your company
Offer BRIBES, Kickbacks, or other inappropriate gratuities to Government employees
Illegally obtain Government procurement planning solicitation or budget information
Illegally obtain CONFIDENTIAL information of any sort – procurement related or not
Make a false statement in the procurement process
Fail to certify the accuracy and/or completeness of cost/pricing information submitted
Make a false claim
Accounting System Audit Questions:
Is the system in accord with GAAP?
Will the system segregate DIRECT fro INDIRECT costs?
Is it integrated with the company General Ledger? Do Timekeeping and Labor Hour [functions] allow for Direct and Indirect
classification(s)?
Can interim (monthly) costs be routinely calculated?
Can it segregate unallowable costs per FAR Part 31 and/or specific contract terms and conditions?
Can it itemize costs by contract line items?
Accounting Systems
Contract Negotiations, Figure 8-1: Government Auditor Accounting System Questionair, p.174
Accounting System Audit Questions (continued):
Can it differentiate pre-contract and/or pursuit costs?
Can the system generate the FAR-required reports and documentation?
Can the system generate cost-based supporting data? Is the system designed, operational, and capable of storing accurate data?
Accounting Systems
Contract Negotiations, Figure 8-1: Government Auditor Accounting System Questionnaire, p.175. From: Beyond an “Adequate” Accounting System, by Jeffrey A. Lubeck, Contract Management Magazine, May 2004.
Adequate Cost Estimating Systems:
Accounting Systems
Contract Negotiations, Figure 8-2: Examples of Verifiable Proposal Supporting Data, p.177, From: Is your Accounting System Asking for Trouble?, by Darryl L. Walker, Contract Management Magazine, May 2004..
Examples of Verifiable Proposal Supporting Data
Direct Labor Hours Labor-hour history of the same or similar projects Company or industry standards
Bill of Direct Materials
Material planning documents Engineering blueprints
Direct Labor Rates Labor cost history for the same or similar project Average labor rates from payroll data Market wage or salary survey information
Direct Materials Purchase history of the same or similar items Vendor quotations Vendor catalogs
Indirect Rate Historical annual indirect rates Budgetary/provisional rates
The Federal Acquisition Regulations:
Developed by Congress to codify and publish existing policies
Established in the Office of Federal Procurement Policy Act of 1974 and amended by Public Law 93-83
Administered / Issues jointly by: - The General Services Administration (GSA) Administrator
- The Secretary of the Department of Defense (DOD)
- The National Aeronautics and Space Administration (NASA) Administrator
FAR Part 15 – Contact Negotiation(s):
“Prescribes policies and procedures governing competitive and non- competitive negotiated acquisitions.”
Legal Framework
The Truth in Negotiations Act (TINA):
Developed by Congress to reduce the number of disputes brought before contract appeals boards
Established in the Truth in Negotiation Act as Public Law 87-653 (10 U.S.C. 2306) in December, 1962
Requires contractors and subcontractors to submit and certify to the Government the data related to the basis of estimated contract cost.
TINA REQUIRES that the information be “Current, Accurate, and Complete.”
Legal Framework
TINA Data Typically Disclosed:
Historical costs, such as material costs, labor hours expended, labor rates paid, or labor union settlements
“Make or Buy” program decisions
Subcontractor and vendor quotations Learning curve projections
Other business base projections
Legal Framework
TINA Required Documentation:
A record of significant events in the procurement
A list of attendees at [any] briefing
The current acquisition situation (status) The previous price history (if any)
A synopsis of offers submitted or received
The analytical methods used to establish the price objectives The delivery objectives
The negotiation plan
Signature blocks for the signatures of approving official(s)
Legal Framework
Contract Negotiations Chapter 08: U.S Federal Government
Contract Negotiations – Best Practices
CN Week 8 Discussion Question
Question 08b: What is the Truth in Negotiating Act (TINA), why was it enacted, and why is it important to the Federal procurement process?
Project Procurement Management Chapter 08: Plan Procurements (2 of 2)
Contract Negotiations Chapter 08: U.S. Federal Government
Contract Negotiations – Best Practices
Week 8
- Slide Number 1
- Slide Number 2
- Slide Number 3
- Slide Number 4
- Slide Number 5
- Slide Number 6
- Slide Number 7
- Slide Number 8
- Slide Number 9
- Slide Number 10
- Slide Number 11
- Slide Number 12
- Slide Number 13
- Slide Number 14
- Slide Number 15
- Slide Number 16
- Slide Number 17
- Slide Number 18
- Slide Number 19
- Slide Number 20
- Slide Number 21
- Slide Number 22
- Slide Number 23
- Slide Number 24
- Slide Number 25