| Mobile Inventory Tracker Applications |
| Name | Duration | Start | End | Predecessors | Resources |
| Mobile app plan | 34 days | 2/5/20 | 3/17/20 |
| Project set-up | 7 days | 2/1/20 | 2/9/20 |
| assess user requirements | 2 days | 2/1/20 | 2/2/20 | | project manager, product owner |
| Set up working environment | 4 days | 2/3/20 | 2/8/20 | 3 | technical administrator |
| Determine initial sprint velocity | 1 day | 2/9/20 | 2/9/20 | 4 | lead developer |
| budget allocation to sprints | 0 days | 2/9/20 | 2/9/20 | | project manager |
| select project tem | 1 day | 2/9/20 | 2/9/20 | 6 | project manager |
| Project setup complete | 0 days | 2/9/20 | 2/9/20 | 5 |
| Sprint 1 User interface | 6 days | 2/10/20 | 2/17/20 | 2 |
| Sprint 1 plan | 0.5 days | 2/10/20 | 2/10/20 |
| Select sprint 1 user stories | 0.25 days | 2/10/20 | 2/10/20 | | product owner |
| Assign user stories | 0.25 days | 2/10/20 | 2/10/20 | 9 | product owner, lead developer |
| Sprint 1 plan complete | 0 days | 2/10/20 | 2/10/20 | 10 |
| User Interface | 5 days | 2/10/20 | 2/16/20 |
| Design User Interface | 2 days | 2/10/20 | 2/11/20 | | UX developer |
| Build User Interface | 2 days | 2/12/20 | 2/15/20 | 13 | UX developer |
| Test User Interface | 1 day | 2/16/20 | 2/16/20 | 14 | test engineer |
| UAT of user Interface | 1 day | 2/17/20 | 2/17/20 | 12 | test engineer, product owner |
| Correct Issues From UAT UI | 1 day | 2/26/20 | 2/26/20 | 25 | UX developer |
| Sprint 2 functionalities implementation | 10 days | 2/10/20 | 2/22/20 |
| Sprint 2 plan | 4 days | 2/10/20 | 2/13/20 | | scrum manager |
| selecting sprint 2 stories | 2 day | 2/10/20 | 2/12/20 | | scrum manager |
| Assign user stories | 1 day | 2/12/20 | 2/13/20 | 22 |
| Sprint 2 completion | 1 day | 2/12/20 | 2/13/20 | 23 |
| Testing product modules functionalities | 6 days | 2/14/20 | 2/2/20 |
| Developing functionalities | 3 days | 2/14/20 | 2/18/20 | 24 | project team |
| Testing programs | 2 days | 2/20/20 | 2/22/20 | 26 | back end tester |
| Approval | 1 day | 2/22/20 | 2/22/20 | 26 |
| Sprint 3 project reports | 15 days |
| Sprint 3 plan | 0.5 days | 2/18/20 | 2/18/20 |
| Select sprint 3 user stories | 0.25 days | 2/18/20 | 2/18/20 | | lead developer |
| Assign user stories | 0.25 days | 2/18/20 | 2/18/20 | 19 | lead developer |
| Sprint 3 plan completion | 0 days | 2/18/20 | 2/18/20 | 20 |
| Client Specified Reports | 7 days | 2/18/20 | 2/26/20 |
| Design Reports | 2 days | 2/18/20 | 2/19/20 | | reporting developer |
| Build Reports | 2 days | 2/22/20 | 2/23/20 | 23 | reporting developer |
| Test Reports | 2 days | 2/24/20 | 2/25/20 | 24 | test engineer |
| UAT of Reports | 1 day | 2/29/20 | 2/29/20 | 22 | test engineer, product owner |
| Correcting of Issues From UAT of Reports | 1 day | 3/8/20 | 3/8/20 | | reporting developer |
| Sprint 4 Platform | 7 days | 3/1/20 | 3/9/20 | 17 |
| Sprint 4 plan | 0.5 days | 3/1/20 | 3/1/20 |
| Select sprint 4 user stories | 0.25 days | 3/1/20 | 3/1/20 | | lead developer |
| Assign user stories | 0.25 days | 3/1/20 | 3/1/20 | 30 | lead developer |
| Sprint 4 plan completion | 0 days | 3/1/20 | 3/1/20 | 31 |
| Cross Platform Support | 6 days | 3/1/20 | 3/8/20 |
| Design Cross Platform Support | 2 days | 3/1/20 | 3/2/20 | | technical administrator |
| Build Cross Platform Support | 2 days | 3/3/20 | 3/4/20 | 34 | technical administrator |
| Test Cross Platform Support | 1 day | 3/7/20 | 3/7/20 | 35 | technical administrator |
| UAT of Cross Platform Support | 1 day | 3/9/20 | 3/9/20 | 33 | technical administrator, test engineer |
| Project End | 2 days | 3/16/20 | 3/17/20 | 44 |
| client signing off | 1 day | 3/16/20 | 3/16/20 | | project manager, product owner |
| issue project report | 0.5 days | 3/17/20 | 3/17/20 | 48 | project manager, product owner |
| Project End | 0.5 days | 3/17/20 | 3/17/20 | 49 | project manager, product owner |