Project Management Process - Initiation
Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the Greendale Stadium Case located at the end of Chapter 6
Greendale Project ReDux
Project Management
Microsoft Project file Snapshot
When will the project be completed?
Project Completion Date: 12th October, 2018
What is the critical path for the project?
Critical path can be drawn as,
How much slack / float are in your project? What activities have the greatest slack / float?
|
ID |
Duration |
Activity |
Start |
Free Slack |
Total Slack |
|
|
|||||
|
1 |
695 days |
Baseball Stadium |
|
|
|
|
2 |
70 days |
Clear stadium site |
|
0 days |
0 days |
|
3 |
30 days |
Demolish building |
|
0 days |
0 days |
|
4 |
70 days |
Set up construction site |
|
0 days |
0 days |
|
5 |
120 days |
Drive support piling |
|
0 days |
0 days |
|
6 |
120 days |
Pour lower concrete bowl |
|
0 days |
0 days |
|
7 |
120 days |
Pour main concourse |
|
0 days |
0 days |
|
8 |
90 days |
Install playing field |
|
275 days |
275 days |
|
9 |
120 days |
Construct upper steel bowl |
|
0 days |
0 days |
|
10 |
140 days |
Install seats |
|
0 days |
0 days |
|
11 |
90 days |
Build luxury boxes |
|
155 days |
155 days |
|
12 |
30 days |
Install jumbotron |
|
0 days |
0 days |
|
13 |
120 days |
Stadium infrastructure |
|
125 days |
125 days |
|
14 |
75 days |
Construct steel canopy |
|
0 days |
0 days |
|
15 |
30 days |
Light installation |
|
0 days |
0 days |
|
16 |
90 days |
Build roof supports |
|
5 days |
5 days |
|
17 |
180 days |
Construct roof |
|
5 days |
5 days |
|
18 |
90 days |
Install roof tracks |
|
95 days |
95 days |
|
19 |
90 days |
Install roof |
|
5 days |
5 days |
|
20 |
20 days |
Inspection |
|
0 days |
0 days |
Identify the top three (3) activities that you believe could impact the project completion date.
Top three activities are, Build luxury boxes, Stadium infrastructure, and Install playing field
What additional activities you would add to this project to make it more complete, from a project management viewpoint?
Company should give them 700 days to complete the task.