ID Task

Mode

Task Name Duration Start Finish Predecessors Resource Names Work

1 Project Kick Off 6 days? Fri 5/14/21 Fri 5/21/21 56 hrs

2 Create Meeting 1 day? Fri 5/14/21 Fri 5/14/21 Cedrick Greer 8 hrs

3 Meet With Clients1 day? Mon 5/24/21Mon 5/24/212 Cedrick Greer 8 hrs

4 Discuss All Needs 1 day? Mon 5/17/21Mon 5/17/21 Cedrick Greer 8 hrs

5 Hire SME 4 days Tue 5/18/21 Fri 5/21/21 4 Cedrick Greer 32 hrs

6 Planning 10 days Mon 5/24/21Fri 6/4/21 80 hrs

7 Scope 1 day Mon 5/24/21Mon 5/24/21 Adam Rose 8 hrs

8 Gather Clients Req3 days Tue 5/25/21 Thu 5/27/21 Adam Rose 24 hrs

9 Create Plan 5 days Fri 5/28/21 Thu 6/3/21 Adam Rose 40 hrs

10 Meet With Clients1 day Wed 6/2/21 Wed 6/2/21 Cedrick Greer 8 hrs

11 Accept Plan 2 days Thu 6/3/21 Fri 6/4/21 0 hrs

12 Design Application 28 days? Mon 6/7/21 Wed 7/14/21 192 hrs

13 Develop Application

21 days Mon 6/7/21 Mon 7/5/21 Software 0 hrs

14 Test Application 6 days Tue 7/6/21 Tue 7/13/21 13 Software,Adam Rose,Cedrick Greer,Kris Greenwood,Moe Johnsons (SME)192 hrs

15 Deploy Application

1 day? Wed 7/14/21

Wed 7/14/21

14 Software 0 hrs

16 Post Implementation

14 days? Wed 7/14/21

Tue 8/3/21 15 40 hrs

17 Support 5 days Thu 7/15/21 Wed 7/21/21 Moe Johnsons (SME) 40 hrs

18 Documentation 8 days Thu 7/22/21 Mon 8/2/21 17 Software 0 hrs

19 Project Complete 1 day? Tue 8/3/21 Tue 8/3/21 18 0 hrs

Cedrick Greer

Cedrick Greer

Cedrick Greer

Cedrick Greer

Adam Rose

Adam Rose

Adam Rose

Cedrick Greer

Software

Software,Adam Rose,Cedrick Greer,Kris Greenwood,Moe Johnsons (SME)

Software

Moe Johnsons (SME)

Software

Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3

2021 2022 2023

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: Course_project_Cedric

Date: Mon 6/21/21