TASK MODE TASK NAME DURATION START FINISH PREDECESSOR
gathering information Pre-production 95DAYS TUE1/8/18
requirement analysis Pre-production begins 0DAYS TUE1/8/18
design Review screenplay 3WKS Tue/1/8/18 22/8/18 2
coding Develop scene blocking and schedule 1WK 23/8/18 30/8/18 3
coding Develop production layouts 1MON 30/8/18 30/8/18 4
implementation Identify and reserve locations 5WKS 1/9/18 4/10/18 5
testing Book musicians 2 wks. Wed Tues 19/10/18 6
5/10/16
testing Book dancers 2wks WED 20/10/2018 3/11/18 7
maintainance Reserve audio recording equipment 1WK 4/11/18 11/11/18 8
maintainance Reserve video recording equipment 5DAYS 12/11/18 17/11/18 9
maintiance Pre-Production complete 0 DAYS 18/11/18 18/11/18 10