| TASK MODE | TASK NAME | DURATION | START | FINISH | PREDECESSOR |
| gathering information | Pre-production | 95DAYS | TUE1/8/18 |
| requirement analysis | Pre-production begins | 0DAYS | TUE1/8/18 |
| design | Review screenplay | 3WKS | Tue/1/8/18 | 22/8/18 | 2 |
| coding | Develop scene blocking and schedule | 1WK | 23/8/18 | 30/8/18 | 3 |
| coding | Develop production layouts | 1MON | 30/8/18 | 30/8/18 | 4 |
| implementation | Identify and reserve locations | 5WKS | 1/9/18 | 4/10/18 | 5 |
| testing | Book musicians | 2 wks. | Wed | Tues 19/10/18 | 6 |
| | | | 5/10/16 |
| testing | Book dancers | 2wks | WED 20/10/2018 | 3/11/18 | 7 |
| maintainance | Reserve audio recording equipment | 1WK | 4/11/18 | 11/11/18 | 8 |
| maintainance | Reserve video recording equipment | 5DAYS | 12/11/18 | 17/11/18 | 9 |
| maintiance | Pre-Production complete | 0 DAYS | 18/11/18 | 18/11/18 | 10 |