Running head: UNIT VI PROJECT 1
Part 1:
UNIT VI PROJECT 6
Unit VI Project
Your Name
Columbia Southern University
Part 1
· an activity precedence diagram,
· an activity duration table, and
· a network diagram and Gantt charts.
Part 2
Please complete Case Study 10.1: Project Scheduling at Blanque Check Construction on page 360 of the textbook, and answer the three questions at the end.
Part 3
Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project?
|
Activity |
Expected Duration |
Predecessor |
|
A |
5 days |
---- |
|
B |
10 days |
A |
|
C |
8 days |
A |
|
D |
1 day |
A |
|
E |
5 days |
B, C |
|
F |
10 days |
D, E |
|
G |
14 days |
F |
|
H |
3 days |
G |
|
I |
12 days |
F |
|
j |
6 days |
H, I |
Part 4
Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network.
|
Activity |
|
|
Duration |
|
Predecessors |
||
|
A |
|
|
3 |
|
-- |
||
|
B |
|
|
5 |
|
A |
||
|
C |
|
|
7 |
|
A |
||
|
D |
|
|
3 |
|
B, C |
||
|
E |
|
|
5 |
|
B |
||
|
F |
|
|
4 |
|
D |
||
|
G |
|
|
2 |
|
C |
||
|
H |
|
|
5 |
|
E, F, G |
||
|
Activity |
Duration |
ES |
EF |
LS |
|
LF |
Slack |
|
A |
3 |
0 |
3 |
0 |
|
0 |
-- |
|
B |
5 |
3 |
8 |
8 |
|
13 |
5 |
|
C |
7 |
3 |
10 |
3 |
|
10 |
-- |
|
D |
3 |
10 |
13 |
13 |
|
13 |
-- |
|
E |
5 |
8 |
12 |
13 |
|
17 |
5 |
|
F |
4 |
13 |
17 |
13 |
|
17 |
|
|
G |
2 |
10 |
12 |
15 |
|
17 |
5 |
|
H |
5 |
17 |
22 |
17 |
|
22 |
-- |