Objective: Unit 2 Written Assignment -  Weekly topics:  Expected time for activities/ Outline of an information systems plan

I:  Time estimates (10 points)

Calculate the expected time for the following activities.

              

   Activity  

   Optimistic Time  

   Most Likely Time  

   Pessimistic Time  

   Expected Time  

A

3

7

11

 

B

5

9

13

 

C

1

2

9

 

D

2

3

16

 

E

2

4

18

 

F

3

4

11

 

G

1

4

7

 

H

3

4

5

 

I

2

4

12

 

J

4

7

9

 

 

II:  Project diagrams (20 points)

 

A project has been defined to contain the following list of activities along with their required times for completion.

           

   Activity No.  

   Immediate Activity  

   Time (weeks)  

   Predecessors  

1

Collect requirements

3

 

2

Analyze processes

2

1

3

Analyze data

2

2

4

Design processes

6

2

5

Design data

3

3

6

Design screens

2

3,4

7

Design reports

4

4,5

8

Program

5

6,7

9

Test and document

7

7

10

Install

2

8,9

Specific tasks for exercise II project diagrams.

1. Draw a network diagram for the activities. 

2. Construct a Gantt chart for the project.

3. Calculate the earliest expected completion time. 

4. Show the critical path. 

III.  Preliminary outline of an information systems plan (20 points)

· Create a preliminary outline of an information systems plan. 

· Choose a company that you are familiar with (or research one that you are note). 

· Follow the “Outline of an information systems plan” shown in and complete a short information systems plan for the organization you chose.

· Write at least one brief paragraph for each of the seven categories in the outline.

FIGURE 4-15 Outline of an information systems plan

Located in: Hoffer, J, George, J, Valacich, J (2016). Modern Systems Analysis and Design. Upper Saddle River, NJ. Prentice Hall