| Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Weighted Average Duration (days) |
| Initiating |
| Finalize project team | 2 | 4 | 10 | 5 |
| Develop project charter | 2 | 3 | 13 | 5 |
| Planning |
| Develop scope statement | 4 | 8 | 14 | 8 |
| Develop and refine other plans | 10 | 20 | 29 | 20 |
| Executing |
| Concept |
| Conduct research for income mechanism into Global Treps | 10 | 20 | 30 | 20 |
| Evaluate current systems | 2 | 4 | 10 | 5 |
| Define requirements | 4 | 16 | 22 | 15 |
| Define user requirements | 8 | 10 | 23 | 12 |
| Define content requirements | 4 | 16 | 29 | 16 |
| Define system requirements | 7 | 17 | 33 | 18 |
| Define server owner requirements | 4 | 18 | 20 | 16 |
| Define specific functionality | 10 | 20 | 33 | 21 |
| Define risks and risk management approach | 7 | 13 | 21 | 13 |
| Develop project plan | 9 | 18 | 32 | 19 |
| Brief web development team | 1 | 1 | 2 | 1 |
| Web Site Design |
| Create templates and guidelines for running events | 4 | 16 | 22 | 15 |
| Design donation portal for potential investors | 7 | 19 | 33 | 19 |
| Design a submission page for new ideas on products/services | 8 | 10 | 27 | 13 |
| Design registration for organizations to develop custom websites | 8 | 10 | 22 | 12 |
| Design tracking system | 5 | 8 | 16 | 9 |
| Design incentive system | 10 | 15 | 22 | 15 |
| Web Site Development |
| Develop donation portal for potential investors | 9 | 22 | 32 | 22 |
| Develop a submission page for new ideas on products/services | 12 | 21 | 37 | 22 |
| Develop a registration page for organizations to develop custom websites | 12 | 21 | 37 | 22 |
| Develop tracking system | 5 | 17 | 21 | 16 |
| Develop incentive system | 5 | 17 | 21 | 16 |
| Upload templates and guidelines | 2 | 4 | 8 | 4 |
| Conduct Verification Testing | 9 | 18 | 27 | 18 |
| Conduct Validation Testing | 4 | 15 | 20 | 14 |
| Conduct Pilot Testing | 2 | 3 | 9 | 4 |
| Roll Out |
| Hold Four Events (in different countries) to Test Site Functionality | 24 | 40 | 80 | 44 |
| Obtain Feedback | 2 | 3 | 5 | 3 |
| Implement Changes | 6 | 11 | 20 | 12 |
| Move site to production server | 2 | 4 | 6 | 4 |
| Determine roll out schedule | 2 | 6 | 10 | 6 |
| Communicate roll out plan to users | 2 | 4 | 8 | 4 |
| Conduct user training | 2 | 4 | 12 | 5 |
| Deploy system | 1 | 1 | 2 | 1 |
| Support |
| Determine what support resources are needed | 2 | 3 | 4 | 3 |
| Make appropriate staffing changes | 2 | 3 | 4 | 3 |
| Determine method that users will attain support | 2 | 3 | 5 | 3 |
| Determine support process | 2 | 5 | 11 | 6 |
| Launch support | 1 | 1 | 2 | 1 |
| Controlling |
| Hold formal customer review | 1 | 1 | 2 | 1 |
| Closing |
| Prepare final report and presentation | 2 | 5 | 10 | 5 |
| Deliver final report and presentation | 1 | 1 | 2 | 1 |