Green computing project

Izzy3110
Templates1.zip

team_contract.docx

Team Contract

Project Name:

Project Team Members Names and Sign-off:

Name

Sign-off on Team Contract

Code of Conduct: As a project team, we will:

·

·

·

Participation: We will:

·

·

·

Communication: We will:

·

·

·

Problem Solving: We will:

·

·

·

Meeting Guidelines: We will:

·

·

·

top_10.xlsx

Sheet1

Top 10 Risk Item Tracking for Project Name
Prepared by: Date:
Risk Event This Month Last Month Number of Months in Top 10 Risk Resolution Progress

Sheet2

Sheet3

wbs.docx

Work Breakdown Structure Template for Project Name

Prepared by: Date:

1.0 Main category 1

1.1 Subcategory

1.2 Subcategory

1.2.1 Sub-subcategory

1.2.2 Sub-subcategory

1.3 Subcategory

1.4 Subcategory

2.0 Main category 2

2.1 Subcategory

2.2 Subcategory

2.2.1 Sub-subcategory

2.2.2 Sub-subcategory

2.3 Subcategory

2.4 Subcategory

3.0 Main category 3

3.1 Subcategory

3.2 Subcategory

3.2.1 Sub-subcategory

3.2.2 Sub-subcategory

3.3 Subcategory

3.4 Subcategory

4.0 Main category 4

4.1 Subcategory

4.2 Subcategory

4.2.1 Sub-subcategory

4.2.2 Sub-subcategory

4.3 Subcategory

4.4 Subcategory

wtd_decision_matrix.xlsx

Sheet1

Weighted Decision Matrix for Project Name
Created by: Date:
Criteria Weight Project 1 Project 2 Project 3 Project 4
A 25% 90 90 50 20
B 15% 70 90 50 20
C 15% 50 90 50 20
D 10% 25 90 50 70
E 5% 20 20 50 90
F 20% 50 70 50 50
G 10% 20 50 50 90
Weighted Project Scores 100% 56 78.5 50 41.5

Weighted Score by Project

Project 1 Project 2 Project 3 Project 4 56 78.5 50 41.5

Sheet2

Sheet3

breakeven.xlsx

Profit Analysis

Units Sold Revenue Expense
0 $0 $25,000
500 6,000 29,000
1,000 12,000 33,000
1,500 18,000 37,000
2,000 24,000 41,000
2,500 30,000 45,000
3,000 36,000 49,000
3,500 42,000 53,000
4,000 48,000 57,000
4,500 54,000 61,000
5,000 60,000 65,000
5,500 66,000 69,000
Sales Price per Unit: $12 6,000 72,000 73,000
6,500 78,000 77,000
7,000 84,000 81,000
Manufacturing Cost per Unit: $8 7,500 90,000 85,000
8,000 96,000 89,000
8,500 102,000 93,000
Fixed Monthly Expense: $25,000 9,000 108,000 97,000
9,500 114,000 101,000
10,000 120,000 105,000
Break-Even Point (Units Sold): 6,250 10,500 126,000 109,000
Revenue at Break-Even Point: $75,000 11,000 132,000 113,000
11,500 138,000 117,000
12,000 144,000 121,000
12,500 150,000 125,000
13,000 156,000 129,000
13,500 162,000 133,000
14,000 168,000 137,000
14,500 174,000 141,000
15,000 180,000 145,000
15,500 186,000 149,000
16,000 192,000 153,000
16,500 198,000 157,000
17,000 204,000 161,000
17,500 210,000 165,000
18,000 216,000 169,000
18,500 222,000 173,000
19,000 228,000 177,000
19,500 234,000 181,000
20,000 240,000 185,000

Profit Analysis

Revenue 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000 8500 9000 9500 10000 10500 11000 11500 12000 12500 13000 13500 14000 14500 15000 15500 16000 16500 17000 17500 18000 18500 19000 19500 20000 0 6000 12000 18000 24000 30000 36000 42000 48000 54000 60000 66000 72000 78000 84000 90000 96000 102000 108000 114000 120000 126000 132000 138000 144000 150000 156000 162000 168000 174000 180000 186000 192000 198000 204000 210000 216000 222000 228000 234000 240000 Expense 0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000 5500 6000 6500 7000 7500 8000 8500 9000 9500 10000 10500 11000 11500 12000 12500 13000 13500 14000 14500 15000 15500 16000 16500 17000 17500 18000 18500 19000 19500 20000 25000 29000 33000 37000 41000 45000 49000 53000 57000 61000 65000 69000 73000 77000 81000 85000 89000 93000 97000 101000 105000 109000 113000 117000 121000 125000 129000 133000 137000 141000 145000 149000 153000 157000 161000 165000 169000 173000 177000 181000 185000 Break-Even

6250 75000

Units Sold

burndownchart.xlsx

Sheet1

Days Tasks Done Remaining Ideal Done Per Day Ideal Velocity
Initial Value 0 0 200 10 200
1 0 200 10 190
2 5 195 10 180
3 3 192 10 170
4 12 180 10 160
5 17 163 10 150
6 9 154 10 140
7 8 146 10 130
8 13 133 10 120
9 15 118 10 110
10 6 112 10 100
11 18 94 10 90
12 15 79 10 80
13 16 63 10 70
14 11 52 10 60
15 8 44 10 50
16 13 31 10 40
17 9 22 10 30
18 6 16 10 20
19 10 6 10 10
20 6 0 10 0

Sprint 1 Burndown Chart

Remaining Initial Value 200 200 195 192 180 163 154 146 133 118 112 94 79 63 52 44 31 22 16 6 0 Ideal Velocity Initial Value 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0

Sheet2

Sheet3

business_case.docx

Business Case for Project Name

Date

Prepared by:

1.0 Introduction/ Background

2.0 Business Objective

3.0 Current Situation and Problem/Opportunity Statement

4.0 Critical Assumption and Constraints

.

5.0 Analysis of Option and Recommendation

6.0 Preliminary Project Requirements

7.0 Budget Estimate and Financial Analysis

8.0 Schedule Estimate

9.0 Potential Risks

10.0 Exhibits

Exhibit A: Financial Analysis

business_case_financials.xlsx

Sheet1

Financial Analysis for Project Name
Created by: Date:
Note: Change the inputs, shown in green below (i.e. interest rate, number of years, costs, and benefits). Be sure to double-check the formulas based on the inputs.
Discount rate 8.00%
Assume the project is completed in Year 0 Year
0 1 2 3 Total
Costs 140,000 40,000 40,000 40,000
Discount factor 1.00 0.93 0.86 0.79
Discounted costs 140,000 37,200 34,400 31,600 243,200
Benefits 0 200,000 200,000 200,000
Discount factor 1.00 0.93 0.86 0.79
Discounted benefits 0 186,000 172,000 158,000 516,000
Discounted benefits - costs (140,000) 148,800 137,600 126,400 272,800 NPV
Cumulative benefits - costs (140,000) 8,800 146,400 272,800
ROI 112%
Payback in Year 1
Assumptions
Enter assumptions here

Sheet2

Sheet3

change_request.docx

Change Request Form

Project Name:

Date Request Submitted:

Title of Change Request

Change Order Number:

Submitted by: (name and contact information)

Change Category: Scope Schedule Cost Technology Other

Description of change requested:

Events that made this change necessary or desirable:

Justification for the change/why it is needed/desired to continue/complete the project:

Impact of the proposed change on:

Scope:

Schedule:

Cost:

Staffing:

Risk:

Other:

Suggested implementation if the change request is approved:

Required approvals:

Name/Title

Date

Approve/Reject

charter.docx

Project Charter

Project Title:

Project Start Date: Projected Finish Date:

Budget Information:

Project Manager: Name, phone, e-mail

Project Objectives:

Main Project Success Criteria:

Approach:

Roles and Responsibilities

Role

Name

Organization/

Position

Contact Information

Sign-off: (Signatures of all above stakeholders. Can sign by their names in table above.)

Comments: (Handwritten or typed comments from above stakeholders, if applicable)

client_acceptance.docx

Client Acceptance/Project Completion Form

Project Name: ________________________________________________

Project Manager: ________________________________________________

I (We), the undersigned, acknowledge and accept delivery of the work completed for this project on behalf of our organization. My (Our) signature(s) attest to my (our) agreement that this project has been completed. No further work should be done on this project.

Name

Title

Signature

Date

1. Was this project completed to your satisfaction? Yes No

2. Please provide the main reasons for your satisfaction or dissatisfaction with this project.

3. Please provide suggestions on how our organization could improve its project delivery capability in the future.

Thank you for your inputs.

comm_plan.docx

Communications Management Plan

Prepared by: Date:

1. Introduction

2. Collection and filing structure for gathering and storing project information

3. Distribution structure (what information goes to whom, when, and how)

4. Format, content, and level of detail of key project information

5. Production schedule and resources for producing key project information

6. Technologies, access methods, and frequency of communications

7. Method for updating the communications management plan

8. Escalation procedures

9. Stakeholder communications analysis

Stakeholders

Document Name

Document Format

Contact Person

Due Date

Comments:

10. Glossary of terms

cost_estimate.xlsx

Sheet1

XXX Project Cost Estimate
Prepared by: Date:
Note: Change the WBS items and other entries to meet your project needs. This data is from Figure 7-1 of Schwalbe's text
Information Technology Project Management, Fourth Edition. Also make sure the formulas work properly based on the data you enter.
# Units/Hrs. Cost/Unit/Hr. Subtotals WBS Level 1 Totals % of Total
WBS Items
1. Project Management $306,300 20%
1.1 Project manager 960 $100 $96,000
1.2 Project team members 1920 $75 $144,000
Contractors (10% of software development and testing) $66,300
2. Hardware $76,000 5%
2.1  Handheld devices 100 $600 $60,000
2.2  Servers 4 $4,000 $16,000
3. Software $614,000 40%
3.1 Licensed software 100 $200 $20,000
3.2 Software development* $594,000
4. Testing (10% of total hardware and software costs) $69,000 $69,000 5%
5. Training and Support $202,400 13%
5.1 Trainee cost 100 $500 $50,000
5.2 Travel cost 12 $700 $8,400
5.3 Project team members 1920 $75 $144,000
6. Reserves (20% of total estimate) $253,540 $253,540 17%
Total project cost estimate $1,521,240
* See software development estimate

Sheet2

* Software development
Contractor labor estimate 3000 $150 $450,000
Project team member estimate 1920 $75 $144,000
Total labor estimate $594,000
Function point estimate Quantity Conversion Factor Function Points
External inputs 10 4 40
External interface files 3 7 21
External outputs 3 5 15
External queries 3 4 12
Logical internal tables 6 10 60
Total function points 148
Java 2 languange equivalency value 46
Source lines of code (SLOC) estimate 6,808
Productivity *KSLOC^Penalty (person months) 30.27
Total labor hours (160 hours/month) 4,842.55
Cost/labor hour ($120/hour) $120
Total software development estimate 581,106

Sheet3

earned_value.xlsx

EV data

Earned Value Calculations for Project Name
Prepared by: Date:
Note: Change the entries to meet your project needs. This data is from Figure 7-4 of Schwalbe's text Information Technology Project Management, Fourth Edition.
Also make sure the formulas work properly based on the data you enter.
To Date Planned Actual
Activity Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec PV % Complete % Complete RV EV
Plan and staff project 4,000 4,000 8,000 100 100 100% 8,000
Analyze requirements 6,000 6,000 12,000 100 100 100% 12,000
Develop ERDs 4,000 4,000 8,000 100 100 100% 8,000
Design database tables 6,000 4,000 10,000 100 100 100% 10,000
Design forms, reports, and queries 8,000 4,000 8,000 75 50 67% 5,333
Construct working prototype 10,000 - 0 - 0
Test/evaluate prototype 2,000 6,000 - 0 - 0
Incorporate user feedback 4,000 6,000 4,000 - 0 - 0
Test system 4,000 4,000 2,000 - 0 - 0
Document system 3,000 1,000 - 0 - 0
Train users 4,000 - 0 - 0
Monthly Planned Value (PV) 4,000 10,000 10,000 10,000 12,000 16,000 10,000 6,000 8,000 4,000 5,000 5,000 43,333
Cumulative Planned Value (PV) 4,000 14,000 24,000 34,000 46,000 62,000 72,000 78,000 86,000 90,000 95,000 100,000
Monthly Actual Cost (AC) 4,000 11,000 11,000 12,000 15,000
Cumulative Actual Cost (AC) 4,000 15,000 26,000 38,000 53,000
Monthly Earned Value (EV) 4,000 10,000 10,000 10,000 9,333
Cumulative Earned Value (EV) 4,000 14,000 24,000 34,000 43,333
Project EV as of May 31 43,333
Project PV as of May 31 46,000
Project AC as of May 31 $ 53,000
CV=EV-AC $ (9,667)
SV=EV-PV $ (2,667)
CPI=EV/AC 81.761%
SPI=EV/PV 94.203%
Estimate at Completion (EAC) $ 122,308 (original plan of $100,000 divided by CPI)
Estimated time to complete 12.74 (original plan of 12 months divided by SPI)

EV chart

Chart1

4000 4000 4000
14000 15000 14000
24000 26000 24000
34000 38000 34000
46000 53000 44000
62000
72000
78000
86000
90000
95000
100000
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Chart4

3 4 3
8 8 8
19 18 19
32 29 31
47 41 41.5
63 56 48.645
91 83 73.045
145
206
233
246
254
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Sheet1

Activity Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Plan % Complete EV
Plan and staff project 4,000 4,000 8,000 100 8,000
Analyze requirements 6,000 6,000 12,000 100 12,000
Develop ERDs 4,000 4,000 8,000 100 8,000
Design database tables 6,000 4,000 10,000 100 10,000
Design forms, reports, and queries 8,000 4,000 12,000 50 6,000
Construct working prototype 10,000 10,000 - 0 - 0
Test/evaluate prototype 2,000 6,000 8,000 - 0 - 0
Incorporate user feedback 4,000 6,000 4,000 14,000 - 0 - 0
Test system 4,000 4,000 2,000 10,000 - 0 - 0
Document system 3,000 1,000 4,000 - 0 - 0
Train users 4,000 4,000 - 0 - 0
Monthly Plan 4,000 10,000 10,000 10,000 12,000 16,000 10,000 6,000 8,000 4,000 5,000 5,000 100,000 44,000
BCWS or Cumulative Plan 4,000 14,000 24,000 34,000 46,000 62,000 72,000 78,000 86,000 90,000 95,000 100,000
Monthly Actual 4,000 11,000 11,000 12,000 15,000
ACWP or Cumulative Actual 4,000 15,000 26,000 38,000 53,000
Monthly EV 4,000 10,000 10,000 10,000 10,000
BCWP or Cumulative EV 4,000 14,000 24,000 34,000 44,000
Project BCWP as of May 31 44,000
Project BCWS as of May 31 46,000
Project ACWP as of May 31 $ 53,000
CV=BCWP-ACWP $ (9,000)
SV=BCWP-BCWS $ (2,000)
CPI=BCWP/ACWP 83%
SVI=BCWP/BCWS 96%
Estimated cost at completion $ 120,455 (original plan of $100,000 divided by CPI of 83%)
Estimated time to complete 12.55 (original plan of 12 months divided by SVI of 96%)
Above for Figure 6-2
Chart below for Figure 6-3

Sheet1

0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0
0
0
0
0
BCWS or Cumulative Plan
ACWP or Cumulative Actual
BCWP or Cumulative EV
Month
$

Sheet2

Sheet3

-

20,000

40,000

60,000

80,000

100,000

120,000

123456789101112

Month

$

Planned Value (PV)

Budget at Completion (BAC)

Actual Cost (AC)

Earned Value (EV)

Estimate at Completion (EAC)

expectations.docx

Expectations Management Matrix

Prepared by: Date:

Measure of Success

Priority

Expectations

Guidelines

Scope

Time

Cost

Quality

Customer Satisfaction

Financial Impact

final_documentation.docx

Final Project Documentation for Project Name

Prepared by: Date:

I. Project description

II. Project proposal and backup data (request for proposal, statement of work, proposal correspondence, and so on)

III. Original and revised contract information and client acceptance documents

IV. Original and revised project plans and schedules (WBS, Gantt charts and network diagrams, cost estimates, communications management plan, etc.)

V. Design documents

VI. Final project report

VII. Deliverables, as appropriate

VIII. Audit reports

IX. Lessons learned reports

X. Copies of all status reports, meeting minutes, change notices, and other written and electronic communications

Gantt_chart.mpp

issue_log.docx

Issue Log

Prepared by: Date:

Issue #

Issue Description

Impact on Project

Date Reported

Reported By

Assigned To

Priority

(M/H/L)

Due Date

Status

Comments

1

2

3

etc.

kick-off_meeting.docx

Just-In-Time Training Project

Kick-off Meeting

Date

Meeting Objective: Get the project off to a great start by introducing key stakeholders, reviewing project goals, and discussing future plans

Agenda:

· Introductions of attendees

· Background of project

· Review of project-related documents (i.e. business case, project charter)

· Discussion of project organizational structure

· Discussion of project scope, time, and cost goals

· Discussion of other important topics

· List of action items from meeting

Action Item

Assigned To

Due Date

Date and time of next meeting:

lessons_learned_report.docx

Lessons Learned Report

Prepared by: Date:

Project Name:

Project Sponsor:

Project Manager:

Project Dates:

Final Budget:

1. Did the project meet scope, time, and cost goals?

2. What was the success criteria listed in the project scope statement?

3. Reflect on whether or not you met the project success criteria.

4. In terms of managing the project, what were the main lessons your team learned?

5. Describe one example of what went right on this project.

6. Describe one example of what went wrong on this project.

7. What will you do differently on the next project based on your experience working on this project?

list_of_risks.docx

List of Prioritized Risks for Project Name

Prepared by: Date:

Ranking

Potential Risk

1

2

3

4

5

6

7

8

9

10

milestone_report.docx

Milestone Report for Project Name

Prepared by: Date:

Milestone

Date

Status

Responsible

Issues/Comments

network_diagram.mpp

pareto_chart.xlsx

Sheet1

Pareto Diagram for Remote Deposit Capture Project
Problem Count % Cumulative %
Allow scanning multiple checks at once 30 30% 30%
Show simple checkbox to select account to make deposit into 25 25% 55%
Make showing check scanned image the default 18 18% 73%
No confirmation message after scanning check 15 15% 88%
Show running total for all checks scanned 9 9% 97%
Add video/animation for instructions 3 3% 100%
Total 100
Allow scanning multiple checks at once Show simple checkbox to select account to make deposit into Make showing check scanned image the default No confirmation message after scanning check 30 25 18 15 Allow scanning multiple checks at once Show simple checkbox to select account to make deposit into Make showing check scanned image the default No confirmation message after scanning check 0.3 0.55000000000000004 0.73 0.88

Sheet2

Sheet3

payback.xlsx

Sheet1

Year Costs Benefits Cum Costs Cum Benefits
0 140,000 0 140,000 0
1 37,200 186,000 177,200 186,000
2 34,400 172,000 211,600 358,000
3 31,600 158,000 243,200 516,000

Payback

cumulative costs 0 1 2 3 140000 177200 211600 243200 cumulative benefits 0 1 2 3 0 186000 358000 516000

Year

$

Sheet2

Sheet3

prob_impact_matrix.pptx

Probability/Impact Matrix for Project Name

Impact

Probability

low

medium

high

low

medium

high

risk 1

risk 4

risk 6

risk 9

risk 2

risk 5

risk 11

risk 3

risk 7

risk 8

risk 10

risk 12

progress_report.docx

Status/Progress Report

Project Name:

Team Member Name:

Date:

Reporting Period:

Work completed this reporting period:

Work to complete next reporting period:

What’s going well and why:

What’s not going well and why:

Suggestions/Issues:

Project changes

project_desc_Gantt.mpp

project_desc_text.docx

Project Name Description

Prepared by: Date:

Objective:

Scope:

Assumptions:

Cost:

Schedule:

project_org_chart.pptx

Organizational Chart for Project Name Prepared by: Date:

qualty_assurance_plan.docx

Quality Assurance Plan for Project Name

Prepared by: Date:

1.0 Draft Quality Assurance Plan

1.1 Introduction

1.2 Purpose

1.3 Policy Statement

1.4 Scope

2.0 Management

2.1 Organizational Structure

2.2 Roles and Responsibilities

2.2.1 Technical Monitor/Senior Management

2.2.2 Task Leader

2.2.3 Quality Assurance Team

2.2.3 Technical Staff

3.0 Required Documentation

4.0 Quality Assurance Procedures

4.1 Walkthrough Procedure

4.2 Review Process

4.2.1 Review Procedures

4.3 Audit Process

4.3.1 Audit Procedures

4.4 Evaluation Process

4.5 Process Improvement

5.0 Problem Reporting Procedures

5.1 Noncompliance Reporting Procedures

6.0 Quality Assurance Metrics

Appendix

Quality Assurance Check List Forms

ram.xlsx

Sheet1

Responsibility Assignment Matrix for Project Name
Prepared by: Date:
WBS Activities 1.1.1 1.1.2 1.1.3 1.2.1 1.2.2 1.2.3 2.1.1 2.1.2 2.1.3
OBS Units
A
B
C
D
E
F
Key:

Sheet2

Sheet3

reqs_matrix.docx

Requirements Matrix for Project Name

Prepared by: Date:

Requirement No.

Name

Category

Source

Status

resource_histogram.xlsx

Sheet1

Resource Histogram for Project Name
Prepared by: Date:
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6
A 1 1 1 1 1 1
B 2 2 2 1 1 1
C 1 1 4 4 4 1
D 0 0 0 1 1 1
A Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 1 1 1 1 1 1 B Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 2 2 2 1 1 1 C Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 1 1 4 4 4 1 D Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 0 0 0 1 1 1

Number of People

Sheet2

Sheet3

rfp_outline.docx

Request for Proposal (RFP) Outline

for Project Name

Prepared by: Date:

I. Purpose of RFP

II. Organization’s Background

III. Basic Requirements

IV. Hardware and Software Environment

V. Description of RFP Process

VI. Statement of Work and Schedule Information

VII. Possible Appendices

A. Current System Overview

B. System Requirements

C. Volume and Size Data

D. Required Contents of Vendor’s Response to RFP

E. Model Contract

risk_register.xlsx

Sheet1

Risk Register for Project Name
Prepared by: Date:
 No. Rank Risk Description Category Root Cause Triggers Potential Responses Risk Owner Probability Impact Status

Sheet2

Sheet3

scope_statement.docx

Scope Statement (Version xx)

Project Title:

Date: Prepared by:

Project Justification:

.

Product Characteristics and Requirements:

1.

2.

3.

4.

Summary of Project Deliverables

Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final project report, lessons-learned report, and any other documents required to manage the project.

Product-related deliverables: research reports, design documents, software code, hardware, etc.

1.

2.

3.

4.

Project Success Criteria:

stakeholder_register.docx

Stakeholder Register for Project Name

Prepared by: Date:

Name

Position

Internal/External

Project Role

Contact Information

stakeholder_strategy.docx

Stakeholder Management Strategy for Project Name

Prepared by: Date:

Name

Level of Interest

Level of Influence

Potential Management Strategies

statement_of_work.docx

Statement of Work for Project Name

Prepared by: Date:

I. Scope of Work:

Describe the work to be done to detail. Specify the hardware and software involved and the exact nature of the work.

II. Location of Work:

Describe where the work must be performed. Specify the location of hardware and software and where the people must perform the work

III. Period of Performance:

Specify when the work is expected to start and end, working hours, number of hours that can be billed per week, where the work must be performed, and related schedule information.

IV. Deliverables Schedule:

List specific deliverables, describe them in detail, and specify when they are due.

V. Applicable Standards:

Specify any company or industry-specific standards that are relevant to performing the work.

VI. Acceptance Criteria:

Describe how the buyer organization will determine if the work is acceptable.

VII. Special Requirements:

Specify any special requirements such as hardware or software certifications, minimum degree or experience level of personnel, travel requirements, and so on.

sw_project_mgt_plan.docx

Software Project Management Plan (SPMP) Outline

for Project Name

Prepared by: Date:

Introduction

Project Overview

Project Deliverables

Evolution of the SPMP

Reference Materials

Definitions and Acronyms

Project Organization

Process Model

Organizational Structure

Organizational Boundaries and Interfaces

Project Responsibilities

Managerial Process

Management Objectives and Priorities

Assumptions, Dependencies, and Constraints

Risk Management

Monitoring and Controlling Mechanisms

Staffing Plan

Technical Process

Methods, Tools, and Techniques

Software Documentation

Project Support Functions

Work Packages, Schedule, and Budget

Work Packages

Dependencies

Resource Requirements

Budget and Resource Allocation

Schedule