Week 3 Learning Activities
Master Scheduling and Rough-cut Capacity Planning
D
Master Production Scheduling D2
MPS as a Basis of Communication D3
Objectives of Master Scheduling D4
Developing an MPS D4
Rough-Cut Capacity Planning D6
Evaluating and Accepting the MPS D9
Using the MPS D10
Using the ATP Records D11
Stabilizing the MPS D14
Master Production Scheduling and Rough-Cut Capacity Planning within OM: How It All Fits Together D15
Master Scheduling and Rough-cut Capacity Planning
W H AT ’ S I N F O R M E ?OM
S U P P L E M E N T
ACC FIN MKT OM HRM MIS
Before studying this supplement you should know or, if necessary, review
1. Capacity management concepts, Chapter 9, pp. 316–322.
2. Work standards, Chapter 11, pp. 402–409.
3. Relevant inventory costs, Chapter 12, pp. 438–440.
4. Order quantity models, Chapter 12, pp. 446–459.
5. Aggregate Planning, Chapter 13, pp. 485–487.
After completing this supplement you should be able to
L E A R N I N G O B J E C T I V E S
S U P P L E M E N T O U T L I N E
Explain the role of the master production schedule and describe the objectives of master production scheduling.
Develop a master production schedule and project the capacity needed using rough-cut capacity planning.
Calculate available-to-promise quantities.
Describe time fence policies.4
3
2
1
D1
reid_suppD_001-024hr1.qxd 9/11/09 11:53 AM Page D1
D2 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
When planning your social and work-related activities for the upcoming semester,you use the same logic that is used in developing a master schedule and doing rough-cut capacity planning. You have a schedule of activities to do (the master pro-
duction schedule), and you check to see whether you actually have the resources to do
those activities (rough-cut capacity planning). Social activities could include sporting
events, concerts, the movies, clubbing, dinners out, club meetings, shopping, family
commitments, and/or just hanging out. You have work-related activities as well, such
as classes, homework, an outside job, and/or group projects. Each of these activities
requires some of your resources. At the very least, you must reserve time to do the ac-
tivity. In some cases, you must also set aside some cash. Unfortunately, almost every-
one has limited resources. The same is true for companies. You develop a list of the
activities that you plan to do, estimate the resources required, and then determine
whether your proposed list is feasible. Companies do the same thing: they develop a
master production schedule, and then rough-cut capacity planning determines whether
the schedule is feasible.
MASTER PRODUCTION SCHEDULING Your company’s aggregate plan specifies the resources authorized for use by the com- pany’s operations group. These resources include the size of the workforce, level of in- ventory held, number of planned shortages, authorized level of overtime and undertime, aggregate number of units or services to be produced in-house, and num- ber of units or services to be subcontracted.
The master production schedule (MPS) is often stated in product or service speci- fications rather than dollars. It shows how many products or services are planned for each time period, based on the resources authorized in the aggregate plan. In manu- facturing, the master scheduler develops the schedule based on the available capacity. In service companies, the office manager, department manager, or assistant manager might develop the schedule.
The MPS is the anticipated build schedule for manufacturing specific end products or providing specific services. The key distinction here is that the MPS is a statement of production or services and is not a statement of demand—a plan to satisfy cus- tomer demand while considering operational effectiveness and cost. Because of this, individual products can be finished ahead of time and held in inventory rather than finished as needed. The master scheduler or office manager balances customer service and capacity usage.
The aggregate plan shows how many products or services are planned for each time period. The MPS identifies the specific products or services planned for a given time period. Let’s look at an example of how an aggregate plan is linked to the MPS.
Although this example involves manufacturing, think about how an MPS might look in a service operation such as a law firm. The firm knows how many hours of staff time are available (resources) and its current case load (demands). It must now decide how best to use the attorneys and law clerks each period to satisfy the corporate objectives.
� Master production schedule (MPS) The anticipated build schedule.
� Master scheduler The person responsible for managing, developing, reviewing, and maintaining the master schedule.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D2
MPS AS A BASIS OF COMMUNICATION • D3
E X A M P L E D.1Developing the MPS at Amber’s Backpack Company
Amber’s Backpack Company (ABC) produces three models of backpacks: the basic backpack, the urban backpack, and the evening backpack. Each model needs the same amount of production time. ABC’s aggregate production rate is 400 backpacks per week. A possible MPS for ABC is shown here.
The aggregate plan states that ABC should produce 400 units each week. The MPS shows the models and quantities that constitute the 400 units to be produced each week of the schedule. Ro
ss W
hi ta
ke r/
Th e
Im ag
e B an
k/ G et
ty
MPS AS A BASIS OF COMMUNICATION The MPS is a basis for communication between operations and other functional areas. It is stated in product or service specifications rather than dollars. Your company uses an effective MPS in making customer delivery promises, using company capacity wisely, achieving the company’s objectives, and making trade-off decisions between marketing and operations. Figure D-1 shows the connections between the master scheduling role and other parts of the planning process. Let’s examine these connec- tions, beginning with demand management.
Demand management includes a company’s forecasting, order-entry, order-promising, and physical distribution activities. Demand management captures all activities that use capacity. These demands can be customer orders for products or services, a forecast of demand for products and services, interplant requirements, service parts require- ments, and/or distribution requirements. If a demand is excluded, it will not be sched- uled for completion. Communications between the master scheduler and demand management are ongoing.
MKT
� Demand management The function of recognizing all demands for goods and services to support the marketplace.
Production plan
Rough-cut capacity planning
Demand management
Master production schedule
Material requirements
planning
Master production schedule linkages
FIGURE D-1
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D3
OBJECTIVES OF MASTER SCHEDULING
D4 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
The master scheduler considers the following objectives when developing the MPS:
1. Achieve the desired customer service level either by maintaining finished goods inventory or by scheduling completion of the item or service to meet the cus- tomer’s delivery needs.
2. Make the best use of the company’s resources: material, labor, and equipment. 3. Ensure that the inventory investment is at the appropriate level.
To meet these objectives, the master schedule must satisfy customer demand, not ex- ceed operations’ capacity, and work within the constraints of the aggregate plan. Let’s look at how to develop an MPS.
First MPS Record
TABLE D-1
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 60 10 �40
MPS 0 0 0 0 0 0 0 0 0 0 0 0
Week 1 2 3 4 5 6 7 8 9 10 11 12
MKT
DEVELOPING AN MPS The master scheduler develops a proposed MPS, checks the schedule for feasibility in terms of available capacity, modifies as needed, and authorizes the MPS. The master scheduler starts by creating, revising, and finishing an MPS record for each product. The master scheduler uses the finished MPS records to develop a proposed master production schedule, which he or she then checks for feasibility with a rough-cut ca- pacity planning technique.
Consider the following examples of an MPS record for a product built in a make- to-stock environment with inventory held. The product is built in a fixed-order quan- tity of 125 units, and there are 110 units in beginning inventory. Table D-1 is an initial MPS record showing the demand forecasts for the next 12 weeks.
� Material requirements planning (MRP) A technique using the master production schedule, bill of material data, and inventory records to calculate requirements for materials.
The production or aggregate plan supports the marketing plan. The master sched- uler must work within the authorized resources of the plan. The process for develop- ing an MPS is as follows:
1. The master scheduler develops a proposed MPS. 2. The master scheduler uses a rough-cut capacity planning technique to calculate
whether the company has the capacity to meet the proposed MPS. This is done using a rough-cut capacity planning technique.
3. If the proposed MPS is feasible, it is evaluated by the master scheduler in terms of customer service, effective use of resources, and inventory investment.
4. If the proposed MPS is accepted, it becomes the authorized MPS. If capacity is insufficient, either the MPS is modified or capacity is expanded.
The authorized MPS is a critical input into the material requirements planning (MRP) system. The MPS tells the MRP system what the company plans to build and when. The MRP system then calculates the materials needed to build the products in the schedule and plans for the necessary materials. (MRP systems are discussed in depth in Chapter 14.)
ACC
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D4
DEVELOPING AN MPS • D5
The top row of the record shows the time periods (weeks, in our example); the forecast row shows the forecasted demand for the product. The projected available quantity row keeps track of how many units are available at the end of each time pe- riod. The MPS row shows when replenishment shipments need to arrive. MPS ship- ments arrive at the beginning of the time period. To calculate the projected available quantity, we use the following formula:
Period 1 To calculate the projected available quantity at the end of period 1, we take the beginning inventory (110 units), add any MPS shipments arriving that period (0 units), and subtract the forecasted demand for the period (50 units). This leaves the projected available quantity at the end of period 1, or (110 � 0) � 50 � 60 units projected available quantity.
Period 2 The beginning inventory in period 2 is 60 units, no MPS shipment is sched- uled, and the forecast is 50 units. Therefore, the projected available quantity at the end of period 2 is 10 units.
Period 3 In period 3, we have 10 units beginning inventory, no MPS quantity, a fore- cast of 50 units, and a projected available quantity of �40 units; that is, we do not have enough of this product available to satisfy the forecasted demand in period 3. Thus we need to plan an MPS shipment to arrive at the beginning of period 3. We cal- culate the size of the replenishment order by the order quantity rule—in our case, a fixed-order quantity of 125 units. Table D-2 shows the revised MPS record with an MPS quantity of 125 units scheduled to arrive in period 3.
We continue to calculate the projected available quantity until we find the next pe- riod in which the projected available quantity is negative, which is period 5. Therefore, we need to schedule another MPS replenishment for delivery at the start of period 5. At that point, we add another MPS shipment and continue forward. Table D-3 pre- sents the completed MPS record, which shows replenishment orders needed in peri- ods 3, 5, 7, 8, and 11. Each MPS quantity is determined using the given order quantity rule (125 units).
Projected available � beginning inventory � MPS shipment � forecasted demand
First Revised MPS Record
TABLE D-2
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 60 10 85 35 �40
MPS 0 0 125 0 0 0 0 0 0 0 0 0
Week 1 2 3 4 5 6 7 8 9 10 11 12
Completed MPS Record
TABLE D-3
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Projected available 60 10 85 35 85 10 60 110 60 10 85 35
MPS 0 0 125 0 125 0 125 125 0 0 125 0
Week 1 2 3 4 5 6 7 8 9 10 11 12
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D5
D6 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
ROUGH-CUT CAPACITY PLANNING Rough-cut capacity planning (RCCP) calculates a rough estimate of the workload placed on critical resources by the proposed MPS. This workload is compared against demonstrated capacity for each critical resource. This comparison enables the master scheduler to develop a feasible MPS. Among the several approaches to rough-cut ca- pacity planning is capacity planning using overall planning factors (CPOPF).
Capacity planning using overall planning factors (CPOPF) is a simple, rough-cut capacity planning technique. CPOPF develops a planning factor for each critical re- source based on historical data. A planning factor shows how much of a resource is needed for one completed unit. Table D-4 shows the procedure for using CPOPF. Next, we will work through an example using the procedure.
1. Determine the appropriate planning factors using historical data.
2. Multiply the MPS quantities by the appropriate planning factor.
3. Sum capacity requirements for each resource by time period.
4. Allocate capacity requirements to individual work centers based on historical percentages.
5. Evaluate the workload at each resource to validate MPS feasibility.
Procedure for CPOPF
TABLE D-4
Heavenly Ballroom Shoes, Inc. (HBS) produces two models of ballroom dance shoes. One model is for men (Model M) and the other is for women (Model W). Charles, the master sched- uler, has accumulated the following historical data. During the past three years, HBS has pro- duced 72,000 pairs of Model M, using 21,600 hours of direct labor and 5760 machine hours. During that same period, HBS produced 108,000 pairs of Model W, using 43,200 hours of direct labor and 12,960 hours of machine time.
• Before You Begin: To implement capacity planning using overall planning factors (CPOPF), planning factors are needed. In this case, we have two products, Model M and Model W. Each product requires both direct labor and machine time. We have historical data to determine, on average, how much of each resource has been used in the past to build these products. After developing the plan- ning factors, determine how much capacity is needed to satisfy a specific proposed master production schedule. That is, if you know how many Model M’s you plan to produce and you know how much di- rect labor each Model M takes on average, you can calculate the total amount of direct labor needed to build the Model M’s for a particular period. You do the same thing for Model W’s. Then do this for all periods in your plan. Summing these requirements will give you the total amount of direct labor and machine hours you need to build the units in the proposed master production schedule. These data can be further broken down by individual work centers based on historical data.
Je re
m y
W al
ke r/
Th e
Im ag
e B an
k/ G et
ty I
m ag
es , In
c.
E X A M P L E D.2
CPOPF at Heavenly Ballroom Shoes
� Rough-cut capacity planning (RCCP) The process of converting the master production schedule into requirements for key resources such as direct labor and machine time.
� Demonstrated capacity Proven capacity calculated from actual performance data.
� Capacity planning using overall planning factors (CPOPF) A rough-cut capacity planning technique. MPS items are multiplied by historically determined planning factors for key resources.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D6
Step 1 Determine the planning factors. Charles uses two resources, direct labor and ma- chine time, for each of the products. He needs four planning factors: direct labor for Model M, machine time for Model M, direct labor for Model W, and machine time for Model W. Using the historical data, Charles computes the planning factors as follows:
For Model M, this translates to
The planning factor for direct labor for Model M is 0.30 hours. That means he allows for 0.30 hours of direct labor for each pair of Model M shoes. To calculate the planning factor for ma- chine time for Model M, Charles substitutes total machine hours spent building Model M into the numerator as shown.
The planning factor for the Model M machine time is 0.08 hours (5760 hours of machine time divided by 72,000 pairs of Model M). Charles continues the process to calculate the plan- ning factors for Model W. The direct labor planning factor for Model W is 0.40 hours and the machine time planning factor is 0.12 hours. Table D-5 shows the four planning factors.
Given a proposed MPS, how would Charles calculate the workload for the proposed MPS? Table D-6 shows the proposed quarterly MPS for HBS.
Step 2 Calculate the workload generated by this schedule. Charles multiplies the MPS quantity times the appropriate planning factor. For example, Charles begins in Quarter 1 and calculates how much labor is needed to build 6000 pairs of Model M and 10,000 pairs of Model W. He multiplies 6000 pairs of Model M by its labor planning factor of 0.30 hours to arrive at 1800 hours of direct labor needed. He continues for Model W, multiplying 10,000 pairs by its labor planning factor of 0.40 hours to arrive at 4000 hours of direct labor needed. The total number of direct hours needed in Quarter 1 is 5800 hours (1800 for Model M and 4000 for Model W). Charles continues to do this for each time period. Table D-7 shows all the labor needs.
To calculate the machine needs, Charles continues the process. He multiplies the Quarter 1 needs for Model M by its machine time planning factor (6000 Model M’s � 0.08 hours machine time � 480 hours needed). For Model W, 1680 hours of machine time are needed (10,000 Model W’s � 0.12 hours machine time � 1200 hours needed). Table D-8 shows the machine needs for each product in each quarter.
Planning factor for machine time � total machine hours spent building model
number of units of model built
Planning factor for direct labor � 21,600 hours of direct labor
72,000 pairs
Planning factor for direct labor � total direct labor spent building model
number of units of model built
3 4 5 6 7
A B C Planning Factors (hours per pair)
Model M 0.30 0.08 Model W 0.40 0.12
Direct Labor
Machine Time
Planning Factors
TABLE D-5
9 10 11 12
A B C D E F Quarterly Master Production Schedule (MPS) (pairs)
Q1 Q2 Q3 Q4 Totals Model M 6000 5500 9500 6500 27500 Model W 10000 12000 7500 10100 39600
Proposed MPS
TABLE D-6
ROUGH-CUT CAPACITY PLANNING • D7
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D7
13 14 15 16 17 18 19 20
A B C D E F
Direct Labor Hours Required Q1 Q2 Q3 Q4 Totals
Model M 1800 1650 2850 1950 8250 Model W 4000 4800 3000 4040 15840
Totals 5800 6450 5850 5990 24090
B16: =B11*$B6 (copied to B16:E17)
B18: =SUM(B16:B17) F16: =SUM(B16:E16)
30
31 32 33 34 35 36
A B C D E F G Direct Labor Hours Required by Work Center
Historical Allocation Q1 Q2 Q3 Q4 Totals
Center 101 60% 3480 3870 3510 3594 14454 Center 102 40% 2320 2580 2340 2396 9636
Totals 5800 6450 5850 5990 24090
C32: =B$18*$B32 (copied to C32:F33)
C34: =SUM(C32:C33) G32: =SUM(C32:F32)
Direct Labor Hours Required
TABLE D-7
Direct Labor Needs by Work Center
TABLE D-9
D8 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Step 3 Calculate the total capacity needs for each resource for each time period. Charles does this by summing up the individual capacity needs for each of the products. Table D-7 shows the total labor hours needed for each quarter. Table D-8 shows the same information for machine hours needed.
Step 4 Calculate individual work center capacity needs based on historical percentage allocation. Charles calculates that 60 percent of HBS’s direct labor is used in work center 101 and 40 percent is used in work center 102. The same is true for its machine time. How would Charles calculate by quarters how much direct labor and machine time is needed at work centers 101 and 102? Table D-9 shows direct labor needs by work center. To calculate the labor hours needed in work center 101 in Quarter 1, Charles multiplies the total Quarter 1 labor needs by 60 percent (5800 hours of total labor needed by 60 percent equals 3480 hours of labor needed in work center 101 in Quarter 1). The labor in work center 102 in Quarter 1 is 2320 hours (5800 hours � 40 percent). Charles now has an estimate of the direct labor needs by quarter for each of the work centers. He can compare the direct labor hours needed with the available direct labor hours and make adjustments either to the available capacity or to the MPS.
Charles calculates machine hour needs in each department for each quarter in the same way as he calculates labor needs. Table D-10 shows the machine hours needed by each of the work centers for each quarter. Given this information, Charles can decide whether HBS needs additional equip- ment or whether it has adequate machine capacity in each of the work centers. Remember that a
21 22 23 24 25 26 27 28
A B C D E F
Machine Time (Hours) Required Q1 Q2 Q3 Q4 Totals
Model M 480 440 760 520 2200 Model W 1200 1440 900 1212 4752
Totals 1680 1880 1660 1732 6952
B24: =B11*$C6 (copied to B24:E25)
B26: =SUM(B24:B25) F24: =SUM(B24:E24)
Machine Time (Hours) Required
TABLE D-8
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D8
38
39 40 41 42 43 44
A B C D E F G Machine Time Hours Required by Work Center
Historical Allocation Q1 Q2 Q3 Q4 Totals
Center 101 60% 1008 1128 996 1039.2 4171.2 Center 102 40% 672 752 664 692.8 2780.8
Totals 1680 1880 1660 1732 6952
C40: =B$26*$B40 (copied to C40:F41)
C42: =SUM(C40:C41) G40: =SUM(C40:F40)
Machine Hour Needs by Work Center
TABLE D-10
EVALUATING AND ACCEPTING THE MPS • D9
Before You Go On
Be sure that you understand the sequential process of master scheduling:
1. The master scheduler uses a rough-cut capacity planning technique to calculate whether the company has the capacity to meet the proposed MPS.
2. If the proposed MPS is feasible, it is evaluated in terms of customer service, effective use of resources, and inventory investment.
3. If the proposed MPS is accepted, it becomes the authorized MPS. If capacity is insufficient, either the MPS is modified or capacity is expanded.
MKT
EVALUATING AND ACCEPTING THE MPS
To evaluate the MPS in terms of customer service, the master scheduler checks that promised customer delivery dates are met. He or she also makes sure that the MPS provides enough flexibility to respond to new customer orders.
To evaluate the MPS for effective use of resources, the master scheduler checks that enough capacity is available to meet the schedule in each time period. This capacity includes short-term changes such as overtime, subcontracting, and temporary employees.
To evaluate the MPS in terms of cost, the master scheduler compares the MPS to the aggregate plan, which specifies available resources. If the MPS needs additional re- sources, the company may not achieve the objectives of the marketing plan and, con- sequently, the business plan.
When the master scheduler has evaluated and accepted the MPS, this authorized MPS is input into the MRP system, which is discussed further in Chapter 14.
company can increase its capacity with overtime, temporary workers, subcontracting, or by using alternative manufacturing processes. When Charles is certain that the proposed MPS is feasible, he evaluates the MPS in terms of customer service, effectiveness of resource usage, and cost.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D9
� Order promising The process of making order- delivery commitments.
� Available-to-promise (ATP) The uncommitted portion of a company’s inventory and planned production, maintained in the MPS to support order promising.
D10 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Extended MPS Record
TABLE D-11
� Action bucket The current period.
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer orders 35 25 25 20 0 15 0 0 10 0 0 10
Projected available
ATP
MPS 0 0 125 0 125 0 125 125 0 0 125 0
Period 1 2 3 4 5 6 7 8 9 10 11 12
USING THE MPS One use of the authorized MPS is order promising. When a customer places an order for a product but does not expect immediate delivery, the delivery date is negotiated. The customer typically requests delivery at a future date and the company decides whether it can promise delivery on that date. This is called order promising. For ex- ample, your parents order a new car custom-built for you at the factory for delivery on graduation day. The company is order promising when it decides whether it can pro- duce the car and deliver it on that date. By extending the MPS records we began using in Table D-1, we can do order promising. Let’s look at an extended MPS record in Table D-11.
The table now has two additional rows, one for customer orders and the other for available-to-promise quantity. The customer orders row has orders promised to cus- tomers for delivery in that time period. For example, the company has promised 35 units to be delivered in period 1, 25 units for delivery in period 2, and so forth.
The available-to-promise (ATP) row shows how many uncommitted units the company has available for delivery at a given time. Next, we look at an example of how to calculate the ATP quantity and the projected available balances.
E X A M P L E D.3
Filling in the MPS Record
Using the data shown in Table D-11, let’s look at how we get the numbers. In this case, both the fore- cast numbers and the customer orders are already filled in. The first calculations we need to do are in the projected available row: we take the beginning inventory, add to it any MPS shipment, and sub- tract the greater of the forecast quantity or the customer orders. For example, in period 1, the begin- ning inventory is 110 units, there is no MPS shipment, and since the forecast of 50 is greater than the customer orders (35), we have 110 units � 0 units � 50 units � 60 units projected available at the end of period 1.
We calculate the projected available quantity as
Table D-12 shows the appropriate projected available quantities. We calculate the ATP quantity for the current period or, as it is called, the action bucket, and each time an MPS replenishment order is scheduled. In our example, that means we compute the ATP quantity in periods 1, 3, 5, 7, 8, and 11.
forecast or the actual customer orders promised for delivery that period Projected available � beginning inventory � MPS shipment � the greater of the period’s
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D10
USING THE ATP RECORDS • D11
We calculate the ATP quantity in the current period differently from how we calculate it in the future replenishment periods. In the current period (the action bucket), the ATP quantity equals the beginning inventory, plus any MPS quantity. These two represent the available inventory we have to work with. In period 1, this is 110 units plus 0, or 110 total units available. From this amount, we subtract the customer orders promised for delivery between now and the next replenishment order (period 3 in our case). The number of units already promised is 60 (35 units for delivery in period 1 and 25 units for delivery in period 2). After subtracting the 60 units promised from the 110 units available, we still have 50 ATP units for delivery either in period 1, period 2, or at some future date. We calculate ATP in the action bucket as
As we said, we calculate the ATP differently at future replenishment periods. In these cases, the ATP equals the MPS replenishment quantity less any customer orders promised for delivery between the date of the replenishment received and the next replenishment scheduled. For example, a replen- ishment order of 125 units is arriving in period 3. The customer orders already promised for delivery before the next replenishment order (period 5) total 45 units (25 units in period 3 and 20 units in period 4). Of those 125 units arriving, we have already committed 45, leaving 80 units still available to promise. We calculate the ATP at periods other than the action bucket as
In periods other than the action bucket, we do not include the beginning inventory since it is not clear what the available amount will be. Remember that we subtracted the greater of the forecast or customer orders promised for delivery each period. Thus, if the forecast is greater than the customer orders, we end up with more units in inventory than are reflected on the MPS record. Table D-12 shows the completed ATP quantities.
replenishment ATP � MPS shipment � customer orders between current MPS shipment and next scheduled
� customer orders before next replenishment ATPAction Bucket � beginning inventory � MPS shipment
Period 1 2 3 4 5 6 7 8 9 10 11 12 Forecast 50 50 50 50 75 75 75 75 50 50 50 50 Customer orders 35 25 25 20 0 15 0 0 10 0 0 10 Projected available 110 60 10 85 35 85 10 60 110 60 10 85 35 Available-to-promise 50 80 110 125 115 115 MPS 125 125 125 125 125
The ATP records show how much inventory is available to satisfy customer demand, so your company bases its delivery promises to customers on these records. Using the completed ATP record in Table D-12, let’s look at whether or not your company can promise delivery of a new order.
Suppose that marketing has a customer willing to purchase 200 units if your com- pany can deliver the units in period 5. Using the ATP record, we need to see whether that delivery is possible. One way to do this is to adjust the ATP record as if the order had al- ready been accepted. Table D-13 shows a revised ATP record including the new order.
MKT
USING THE ATP RECORDS
Completed ATP MPS Record
TABLE D-12
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D11
D12 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Second Revised ATP Record
TABLE D-14
1These quantities have changed in order to account for the additional 90 units needed to satisfy the order of 200 units for de- livery in period 5. We commit 80 units from the period 3 replenishment order and 10 units from the ATP quantity in period 1.
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer orders 451 25 1051 20 1101 15 0 0 10 0 0 10
Projected available 110 60 10 30 �20 �5 �80 �30 20 �30 �80 �5 �55
Available-to- promise 40 0 0 125 115 115
MPS 125 125 125 125 125
�1996 Ted Goff Cartoons
In the customer orders row, 200 units are now scheduled for customer delivery in period 5. This changes the projected available quantities from period 5 onward and changes the ATP quantity in period 5. The two rules to remember here are the following.
1. A negative number in the projected available row is sometimes a problem. We calculate the projected available quantity by sub- tracting the greater of the forecast or the customer orders promised for delivery each period. If the forecast is subtracted because it is larger as in period 1 (50 units forecast compared to 35 units of customer orders), the company may not sell any more units for delivery in period 1. In that case, the ending in- ventory for period 1 would be 75 units (110 units to start with, less 35 units delivered).
2. A negative number in the available-to-promise row is always a problem. This means your company does not have enough inventory to cover the delivery. In our example, the company needs an additional 90 units to cover the new order scheduled for delivery in period 5.
One way to handle this problem is to look at earlier ATP quantities to see whether any inventory is available from earlier shipments. Period 1 has 50 uncommitted units and period 3 has an additional 80 available units. If we set 90 of these units aside for the period 5 order, we can agree to the new customer order. Look at the revised ATP record in Table D-14.
Revised ATP MPS Record
TABLE D-13 Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer orders 35 25 25 20 200 15 0 0 10 0 0 10
Projected available 110 60 10 85 35 �40 �115 �65 �15 �65 �115 �40 �90
Available-to- promise 50 80 �90 125 115 115
MPS 125 125 125 125 125
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D12
Think of it this way: We set 10 units aside in period 1 and put the customer’s name on the boxes for delivery in period 5. In period 3, we put names on an additional 80 boxes of units. Then in period 5, we use the 90 boxes of units already set aside plus 110 of the new units to total the 200 units needed. In this way, we can promise delivery of 200 units in period 5.
After we agree to the order for 200 units for delivery in period 5, the next order ar- rives requesting an additional 50 units for period 4 delivery. We put this order into the record and see the results in Table D-15.
The ATP quantity in period 3 is now �50. Since a negative number in the ATP row is always a problem, we must check to see whether there is a way we can change that quantity to zero and accept the order. The only available inventory before delivery is requested is the 40 units available in period 1. Everything else has been promised. Therefore, we cannot ac- cept this order for delivery in period 4. The earliest we can promise delivery is in period 7. Unless the customer is willing to agree with this delivery date, we cannot accept the order. We delete the 50 units from the period 4 customer orders and recalculate the other quanti- ties. The ATP record reverts back to the numbers previously shown in Table D-14.
Let’s look at a couple of additional orders and calculate whether they can be ac- cepted for delivery at the requested time. The first new order is for an additional 50 units to be delivered in period 8; the second order is for 30 additional units in period 12. When we put these orders into the customer order row, the ATP record is updated, as shown in Table D-16. Since there are no negative values in the ATP row, we can promise both of these orders for delivery.
USING THE ATP RECORDS • D13
Third Revised ATP Record
TABLE D-15
1These quantities have changed to account for the additional 90 units needed to satisfy the order of 200 units for delivery in period 5. We commit 80 units from the period 3 replenishment order and 10 units from the ATP quantity in period 1.
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer orders 451 25 1051 70 1101 15 0 0 10 0 0 10
Projected available 110 60 10 30 �40 �25 �100 �50 0 �50 �100 �25 �75
Available-to- promise 40 �50 0 125 115 115
MPS 125 125 125 125 125
Final Revised ATP Record
TABLE D-16
1These quantities have changed to account for the additional 90 units needed to satisfy the order of 200 units for delivery in period 5. We commit 80 units from the period 3 replenishment order and 10 units from the ATP quantity in period 1.
Period 1 2 3 4 5 6 7 8 9 10 11 12
Forecast 50 50 50 50 75 75 75 75 50 50 50 50
Customer orders 451 25 1051 20 1101 15 0 50 10 0 0 40
Projected available 110 60 10 30 �20 �5 �80 �30 20 �30 �80 �5 �55
Available-to- promise 40 0 0 125 65 85
MPS 125 125 125 125 125
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D13
The key requirement for using ATP is that manufacturing delivers the MPS replenish- ment on the scheduled date. For your company to meet these critical dates, operations must have the capacity specified in the MPS, and therefore the MPS itself must be feasible.
D14 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Time fences
FIGURE D-2 Demand time fence
Planning time fence
FROZEN (Changes made
by plant manager or above)
SLUSHY (Product mix
changes made by master scheduler)
LIQUID (Regular processing
by planners)
Current time
Final assembly lead time
Cumulative manufacturing lead timeTime
STABILIZING THE MPS
The master scheduler tries to minimize the number of changes made to an authorized MPS because each proposed change can affect the feasibility of the MPS. To deal with MPS changes, companies sometimes use time fence policies. Figure D-2 illus- trates the MPS and time fences. The figure shows the demand time fence and the planning time fence, which split the MPS into three parts. The portion of the master schedule from the current time up to the demand time fence is frozen and any changes are kept to a minimum.
Companies typically require these changes to be authorized by a person other than the master scheduler because they may need additional resources. This portion of the MPS normally uses all available capacity to produce customer orders. Adding any orders without adding resources results in a delay of the currently scheduled jobs.
The third portion of the MPS starts at the planning time fence and extends into the fu- ture. This portion of the MPS is considered liquid because all orders requested during this portion are accepted as long as the resources authorized by the aggregate plan are ade- quate. The planning time fence is typically placed far enough into the future so that there is enough time to order any necessary materials and complete the normal manufacturing process. Production planners, discussed in Chapter 14, generally place these orders.
� Time fence policies Partition the MPS into areas requiring different operating procedures.
� Demand time fence Establishes that point of time in the future inside of which changes to the MPS must be approved by a higher authority.
� Planning time fence Establishes a point of time in the future inside of which changes must be made by the master scheduler and changes outside of which can be changed by system planning logic.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D14
MASTER PRODUCTION SCHEDULING AND ROUGH-CUT CAPACITY PLANNING WITHIN OM • D15
E X A M P L E D.4
Time Fences at HBS
Heavenly Ballroom Shoes (HBS) has frozen the first month of its MPS. Quarter 1 is shown in monthly time periods. The HBS marketing director, Marilee, has gotten an endorsement from this year’s national ballroom champions for HBS shoes. Because of this endorsement, marketing needs two new, more upscale shoe models (Model WC and Model MC) for use in major competitions. The new models must be available by the end of January or HBS will lose market share. Marilee has asked Charles, the master scheduler, to schedule production of 500 pairs of each of these new models in January. The endorsement represents a major business opportunity for HBS, but HBS does not have the capacity to accept the order for the new shoes. HBS can accept the order only by authorizing more resources for manufacturing or by delaying the shoes that are currently scheduled.
HBS has set up its MPS so that a decision to change the frozen portion has to be authorized by a manager who is also authorized to provide resources. In this way, HBS protects against jeopardizing existing orders to satisfy new ones.
The second portion of the MPS is the time between the demand time fence and the planning time fence. This is called the slushy portion of the MPS, during which it is the master scheduler’s re- sponsibility to negotiate changes in the MPS. For example, if Marilee in HBS marketing needs a product other than what is scheduled, Charles, the HBS master scheduler, first calculates whether the materials are available to make the other product. Then Charles asks Marilee which items marketing would be willing to do without. This is necessary to free up capacity so that the other product can be made.
In this portion of the MPS, changes in the product mix are possible, but changes needing addi- tional resources are not. Thus, HBS will produce 5333 pairs of shoes during a month, but the mix of the shoe models may vary. A revised MPS for February might look like the following. The product mix has changed but the total number of pairs produced remains constant.
MKT
MASTER PRODUCTION SCHEDULING AND ROUGH-CUT CAPACITY PLANNING WITHIN OM: HOW IT ALL FITS TOGETHER
In most companies, the operations manager develops the aggregate plan, which deter- mines the resources available to operations to execute the master production schedule. The plan will clearly indicate the size of the workforce and the aggregate production rate. The master production scheduler then develops the master production schedule. The only feasible plan that can be developed is one by the scheduler working with marketing, operations, demand management, and the customers. The master sched- uler’s job is to develop an MPS that achieves the company’s desired customer service level, uses capacity effectively, and minimizes the inventory investment. To make sure that the master production schedule is feasible, rough-cut capacity planning is done.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D15
D16 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Supplement Highlights The MPS shows how the resources authorized by the aggregate plan will be used to satisfy the objectives of the organization. The MPS specifies the products and quantities to be built in each time period. The MPS is a common organizational document used to facilitate communication between different functional areas. The master scheduler develops a proposed MPS based on input received from the aggregate plan and demand management. This MPS is checked for feasibility using a rough-cut capacity planning technique.
The objectives of master scheduling are to satisfy customer service objectives, use resources effectively, and minimize costs. An MPS is developed by looking at individual MPS records and calculating when replenishment quantities are needed. The individual MPS records are summed together to show the total proposed workload.
2
1 Available-to-promise logic is used when promising order delivery dates to customers. ATP logic allows the company to make viable delivery promises.
Time fence policies stabilize the MPS. The demand time fence and the planning time fence divide the MPS into three portions: frozen, slushy, and liquid. Changes in the frozen portion are infrequent and must be authorized by a manager with authority to release additional resources to operations. Changes to the slushy portion are negotiated between the master scheduler and marketing. Changes in the product mix can occur but not changes in total volume. Changes in the liquid portion are made by planners since adequate lead time is available.
4
3
Key Terms master production schedule (MPS) D2 master scheduler D2 demand management D3 material requirements planning
(MRP) D4 rough-cut capacity planning
(RCCP) D6
demonstrated capacity D6 capacity planning using overall
planning factors (CPOPF) D6 order promising D10 available-to-promise (ATP) D10 action bucket D10
time fence policies D14 demand time fence D14 planning time fence D14
Formula Review 1. Calculating the projected available quantity:
Projected available � beginning inventory � MPS shipment � forecasted demand
2. Calculating a planning factor for direct labor:
Planning factor for direct labor
3. Calculating a planning factor for machine time:
Planning factor for machine time
� total machine time spent building model
number of units of model built
� total direct labor spent building model
number of units of model built
4. Calculating projected available quantity when using ATP MPS records:
Projected available � beginning inventory � MPS shipment � the greater of the period’s forecast or
the actual customer orders promised for delivery that period
5. Calculating ATP quantity in the action bucket:
ATPAction Bucket � beginning inventory � MPS shipment � customer orders before next replenishment
6. Calculating ATP quantity at future replenishment periods:
ATP � MPS shipment � customer orders between current MPS shipment
and next scheduled replenishment
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D16
Solved Problems • Problem 1 Complete the following MPS records. The beginning inventory is 20 units and the order quantity is an FOQ � 50 units in part (a) and a POQ � two periods in part (b).
• Before You Begin: This problem compares two different replenishment policies, an FOQ � 50 units with a POQ � two periods. Calculate the projected available quantity to determine when a replenish- ment order is needed. When the projected available quantity is negative, a replenishment order is needed in that period. Note that different policies can have orders due in different periods. The number of orders and the inventory levels can vary based on replenishment policy.
• Solution a Begin by calculating the projected available quantities. At the end of period 1, the projected available should be 0 (20 units of be- ginning inventory less 20 units forecasted demand). If no order is received, the projected available row is negative at the end of pe- riod 2. When this row turns negative, we need a replenishment order for that period. The replenishment order in this case is 50 units. The updated MPS record is shown in Table D-17.
When spreadsheeting this problem, you can include a con- ditional statement to check whether the projected available quantity is negative. When the projected available is negative, an MPS quantity is then entered into the appropriate cell. The program then recalculates the projected available quantity and continues on to the next negative result.
(See student companion site for Excel template.)
1
2 3 4 5 6 7 8 9
10 11 12 13 14 15 16
A B C D E F G H I J K L M N
Master Production Scheduling
Beginning Inventory 20 Order Quantity 50
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 Forecast 20 20 20 20 10 10 10 10 10 10 20 20 20
Projected Available 0 30 10 40 30 20 10 0 40 30 10 40 20 MPS 0 50 0 50 0 0 0 0 50 0 0 50 0
B9: =B4+B10-B8 C9: =B9+C10-C8 (copy right)
B10: =IF($B$4-B8<0,$B$5,0)
C10: =IF(B9-C8<0,$B$5,0) (copy right)
Solution to Solved Problem 1a
TABLE D-17
Period 1 2 3 4 5 6 7 Forecast 20 20 20 20 10 10 10 Projected available MPS
Period 8 9 10 11 12 13 Forecast 10 10 10 20 20 20 Projected available MPS
Period 1 2 3 4 5 6 7 Forecast 20 20 20 20 10 10 10 Projected available 0 30 10 MPS 50
Period 8 9 10 11 12 13 Forecast 10 10 10 20 20 20 Projected available MPS
SOLVED PROBLEMS • D17
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D17
D18 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
When you are solving the problem manually, continue cal- culating the projected available quantities until the next nega- tive. At that point, we need another replenishment order. The completed MPS is shown here.
• Problem 2 Tim’s Wire Shop builds two different, complicated wiring as- semblies. Production of the WA-1001 model has averaged 50,000 units annually. Historically, Tim’s Wire Shop has used 12,000 direct labor hours and 5000 hours of machine time an- nually to build the WA-1001 wiring harness. The other wiring assembly, WA-5005, has an average annual production of 40,000 units. Annual direct labor used on the WA-5005 is 26,000 hours and 2000 hours of machine time.
Develop the following four planning factors:
Planning factor for direct labor for WA-1001 Planning factor for direct labor for WA-5005 Planning factor for machine time for WA-1001 Planning factor for machine time for WA-5005
• Before You Begin: In this problem, you need to calculate planning factors. Use the historical data to determine on average how much direct labor
• Solution b
Period 1 2 3 4 5 6 7 Forecast 20 20 20 20 10 10 10 Projected available 0 30 10 40 30 20 10 MPS 50 50
Period 8 9 10 11 12 13 Forecast 10 10 10 20 20 20 Projected available 0 40 30 10 40 20 MPS 50 50
Period 1 2 3 4 5 6 7 Forecast 20 20 20 20 10 10 10 Projected available 0 20 MPS 40
Period 8 9 10 11 12 13 Forecast 10 10 10 20 20 20 Projected available MPS
Once again, we need an MPS replenishment in period 2. To cal- culate the quantity, we sum the forecasted demand for the next two periods and subtract any beginning inventory. We need 20 units in both periods 2 and 3 for a total of 40 units; we have no beginning inventory, so we order 40 units. Look at the final MPS record that follows.
We need the next replenishment order in period 4, which should be for 30 units (20 demanded in period 4 and 10 units for period 5). The completed MPS record is shown above.
Note that replenishment orders are now scheduled for peri- ods 2, 4, 6, 8, 10, and 12.
was used to make a model WA-1001 and a model WA-5005. Do the same for machine time.
• Solution To calculate the planning factor for direct labor for WA-1001, divide the annual direct labor hours by the annual number of units produced.
Planning factor for direct labor for WA-1001 � 12,000 direct labor hours/50,000 units, or 0.24 hour per unit
Planning factor for direct labor for WA-5005 � 26,000 direct labor hours/40,000 units, or 0.65 hour per unit
Planning factor for machine time for WA-1001 � 5000 hours of machine time/50,000 units, or 0.10 hour per unit
Planning factor for machine time for WA-5005 � 2000 hours of machine time/40,000 units, or 0.05 hour per unit
Period 1 2 3 4 5 6 7 Forecast 20 20 20 20 10 10 10 Projected available 0 20 0 10 0 10 0 MPS 40 30 20
Period 8 9 10 11 12 13 Forecast 10 10 10 20 20 20 Projected available 10 0 20 0 20 0 MPS 20 30 40
D18 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D18
• Problem 3 Given the proposed MPS shown here and the planning factors from Solved Problem 2, calculate the needed capacity for each pe- riod for direct labor and machine time.
• Before You Begin: Use the planning factors developed in Solved Problem 2. Calculate the amount of capacity needed to satisfy the master production schedule shown. Determine the quarterly requirements for both direct labor and machine time.
• Solution To find the direct labor hours needed, multiply the MPS quantity for each item by its planning factor. Do this for each period.
• Problem 4 Tim’s Wire Shop uses three different departments to produce these wire assemblies. Each of these departments uses direct labor and machine time. Historically, Department 101 uses 25 percent of the direct labor time and machine time for these products, Department 102 uses 35 percent and Department 103 uses 40 percent. Calculate the direct labor and machine time needs for each department for each quarter.
• Before You Begin: In this problem, allocate the capacity requirements calculated in Problem 3 among three different departments. Use the given
historical averages to allocate the direct labor and machine hours needed each period by each department.
• Solution To calculate the direct labor hours needed for each department, take the total direct labor needed for the quarter and multiply it by the appropriate percentage for each work center. For exam- ple, in Quarter 1, the total direct labor needed is 12,150 hours. Multiply that by 25 percent to allocate the appropriate amount of labor to Department 101. The same approach is used for al- locating machine time among departments. The completed al- locations are shown here.
SOLVED PROBLEMS • D19
reid_suppD_001-024hr3.qxd 9/23/09 4:20 PM Page D19
D20 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
• Problem 5 Jeannette’s Cashmere Sweaters has authorized the following MPS for her exclusive line of cashmere sweaters. She wants to use the MPS record for promising future orders. Current order promises are included. The MPS order quantity is 60 units. Be- ginning inventory is 0. Complete the following MPS record.
• Before You Begin: Complete the MPS record. Calculate the projected available quantity by subtracting the greater of the forecast or the actual customer orders from the sum of the previous period’s pro- jected available quantity plus any MPS order being received this period. Remember that a negative value in this row does not necessarily mean that you have a shortage. Calculate the avail- able-to-promise quantity in the action bucket (period 1) and each period when an MPS shipment is due to arrive. Remember
that only in the action bucket calculation is the beginning in- ventory included. In other periods, do not consider the begin- ning inventory since it is not clear what that quantity will be. A negative number in this row is always a problem.
• Solution Projected available quantity is calculated as
Projected available � beginning inventory � MPS shipment � the greater of the period’s forecast or the
customer orders promised for delivery
Therefore, the projected available quantity at the end of period 1 is 45 units (the beginning inventory of 0 plus the MPS ship- ment of 60, less the forecast of 15). The correct projected avail- able quantities are shown here.
Period 1 2 3 4 5 6 Forecast 15 15 15 15 20 20 Customer orders 12 10 8 5 0 0 Projected available Available-to-promise MPS 60 60
Period 7 8 9 10 11 12 Forecast 20 20 25 25 25 25 Customer orders 15 0 30 0 0 0 Projected available Available-to-promise MPS 60 60 60
Period 1 2 3 4 5 6 Forecast 15 15 15 15 20 20 Customer orders 12 10 8 5 0 0 Projected available 45 30 15 0 40 20 Available-to-promise 25 45 MPS 60 60
Period 7 8 9 10 11 12 Forecast 20 20 25 25 25 25 Customer orders 15 0 30 0 0 0 Projected available 0 40 10 45 20 55 Available-to-promise 30 60 60 MPS 60 60 60
D20 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D20
The ATP quantity in the action bucket is 25 units: a beginning inventory of 0 plus an MPS shipment of 60 units, less the cus- tomer orders of 35 units before the next replenishment (12 in period 1, 10 in period 2, 8 in period 3, and 5 in period 4). Use the formula for ATP at MPS replenishments to calculate the other ATP quantities.
• Problem 6 Jeannette has received several additional orders to consider. Using the ATP record calculated in Problem 5, calculate which of the new orders Jeannette should accept. The new orders are (1) 20 units for delivery in period 4, (2) 50 units for delivery in period 8, (3) 40 units for delivery in period 12.
• Before You Begin: In this problem, determine which orders can be promised for delivery. The key is to understand which units are not yet com- mitted and might be used to satisfy a future delivery. Place the new orders into your MPS record and see what problems occur. Then try to determine how to solve these problems.
• Solution The first step is to put the new orders into the MPS record and consider the implications. The updated MPS record is shown here.
Note that Jeannette can accept order 1 for delivery of 20 ad- ditional sweaters in period 4. She can also accept order 3 for 40 units delivered in period 12. However, Jeannette has a problem accepting order 2. The ATP quantity in period 8 is �20, which means Jeannette must ensure that enough sweaters are available to satisfy that order. Since the ATP quantity in period 5 is 25 sweaters, Jeannette can set aside 20 of these sweaters so that she has enough to satisfy order 2. Therefore, she can accept all three orders.
On the revised MPS record, we see that the customer order in period 8 is reduced 20 units, which are transferred to period 5. The 20 units transferred to period 5 are the 20 units that were not available in period 8. Look at the changes in the updated MPS record.
ATP � MPS shipment � customer orders between current MPS shipment and next scheduled replenishment
Compare your answers with those shown.
Period 1 2 3 4 5 6 Forecast 15 15 15 15 20 20 Customer orders 12 10 8 25 20 0 Projected available 45
5 30 15 �10 30 10
Available-to-promise 25 MPS 60 60
Period 7 8 9 10 11 12 Forecast 20 20 25 25 25 25 Customer orders 15 50 30 0 0 40 Projected available �10 0 �30 5 �20 0 Available-to-promise �20 60 20 MPS 60 60 60
Period 1 2 3 4 5 6 Forecast 15 15 15 15 20 20 Customer orders 12 10 8 25 40 0 Projected available 45
4 4 30 15 �10 10 �10
Available-to-promise MPS 60 60
Period 7 8 9 10 11 12 Forecast 20 20 25 25 25 25 Customer orders 15 30 30 0 0 40 Projected available �30 0 �30 5 �20 0 Available-to-promise 0 60 20 MPS 60 60 60
SOLVED PROBLEMS • D21
reid_suppD_001-024hr2.qxd 9/14/09 4:03 PM Page D21
D22 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Discussion Questions 1. Visit a local business and learn how it calculates its resources. 2. Describe the inputs needed to do master production
scheduling. 3. Describe the different sources of demand. 4. Discuss the objectives of the master scheduler and how they
influence master scheduling decisions. 5. Explain the process of developing an authorized MPS. 6. Explain the importance of rough-cut capacity planning in
the MPS process.
7. Describe the role of time fence policies. 8. Explain the changes you can make in the frozen portion of
the MPS and who must authorize such changes. 9. Explain the changes you can make in the slushy portion of
the MPS and who authorizes such changes. 10. Discuss how the MPS might be used in a service
organization.
Problems 1. David’s Delightful Kites Company (DDKC) manufactures
kites. The most popular is David’s Daredevil model. Demand management has prepared forecast estimates for the next six weeks. Beginning inventory is 15 David’s Daredevils. As the mas- ter scheduler for DDKC, you must prepare an MPS. Your MPS order quantity is 72 kites.
(a) Prepare the MPS using an order quantity of 72 kites. (b) Calculate the ending inventory for each period. (c) What is the maximum number of units held in inventory? (d) How many MPS orders are needed? 2. In an effort to reduce setup frequency, DDKC has decided to
use an MPS order quantity of 120 kites. (See Problem 1 for data.) (a) Prepare the MPS using the new order quantity. (b) Calculate the ending inventory for each period. (c) Compare this MPS with the MPS developed in Problem 1. 3. DDKC has decided to change its replenishment policy. In-
stead of producing 72 or 120 kites each order, DDKC has reduced its MPS order quantity to 48 kites.
(a) Develop an MPS using 48 kites as the order quantity. (b) Calculate the ending inventory for each period. (c) Compare this MPS with the schedules developed in Prob-
lems 1 and 2. 4. Wine Accessories Inc. (WAI) produces two models of
corkscrews, the standard model and a deluxe model. WAI follows a level aggregate plan, producing 20,000 corkscrews per month, or 5000 corkscrews per week. The MPS is developed in weekly time periods. The forecasts for each model and the projected available are shown in the next two tables. The replenishment order quantity is 2000 units for the standard model and 1000 units for the deluxe model. Note that you can place multiple or- ders if a single order is insufficient to cover the forecast (you can produce 4000 units of the standard model if necessary, or 2000 or 3000 units of the deluxe model). Remember that total weekly
production is limited to 5000 corkscrews. Develop an MPS for each of the products.
5. WAI uses two resources for each product that it builds: di- rect labor and machine time. From historical records, WAI calcu- lates the following planning factors:
Direct labor for standard corkscrew is 0.20 hour. Direct labor for deluxe corkscrew is 0.50 hour. Machine time for standard corkscrew is 0.10 hour. Machine time for deluxe corkscrew is 0.30 hour.
Calculate the capacity needed for the MPS developed in Problem 4. 6. WAI is evaluating a new machine that reduces the machine
time needed for the standard corkscrew to 0.08 hour, but in- creases the machine time for the deluxe corkscrew to 0.40 hour.
(a) Calculate the machine capacity needed for each period if WAI uses the new machine.
(b) Will the new machine prove beneficial to WAI? 7. WAI knows from historical records that approximately 40
percent of its labor is used in Department 101 and 60 percent is used in Department 102. The reverse is true of machine time; 60 percent is used in Department 101 and 40 percent is used in De- partment 102.
(a) Calculate the labor and machine hours needed in De- partment 101 for each period of the MPS developed in Problem 4.
(b) Calculate the labor and machine hours needed in De- partment 102 for each period of the MPS developed in Problem 4.
8. WAI has developed the following MPS. Calculate the pro- jected available and the available-to-promise quantities for WAI.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D22
CASE: NEWMARKET INTERNATIONAL MANUFACTURING COMPANY (C) • D23
9. WAI, the company in Problem 8, has received the following additional customer orders shown here. You must determine which of the orders the company can accept. If the company must reject any orders, you must explain why.
10. Josh Randall, a sales representative for WAI, has convinced his customer (order #2 in Problem 9) to reschedule. Order #2 has agreed to accept delivery of 25 units in week 2 as long as WAI can also guarantee delivery of an additional 25 units in week 5. If WAI cannot meet both delivery requirements, the customer has threatened to withdraw its entire order. You have already promised orders 1, 3, and 4. Can you assure Josh that WAI will deliver on time? Show your calculations.
CASE: Newmarket International Manufacturing Company (C) Newmarket International Manufacturing Company (NIMCO) was founded by Marcia Blakely only two years after leaving gradu- ate school. Her knowledge of mass customization was the driving force behind starting NIMCO. The company produces three major custom products. Volume on the products is high even though each item is customized specifically for the customer. The products are processed through up to four different work centers. Even though each item is unique, the processing time at each work cen- ter is constant due to the sophisticated equipment used.
Today’s Opportunity Joe Barnes had just left the staffing meeting. The information you provided was quite helpful, and he believes he has ade-
quate resources to accomplish the required manufacturing for the second quarter. Effective capacity levels (including regular time and planned overtime) for each work center are shown here, as is the amount of time required for each product at each work center. The demand forecasts for each product are also shown.
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D23
1. Joe now needs a rough-cut capacity check to determine whether the capacity at each work center is adequate to support the expected demand. Using the forecasted demand as your pro- posed master schedule, calculate the load profile for each work center for each week of the second quarter. Highlight any weeks in which problems might occur.
2. Joe knows from past experience that he has some flexi- bility in his workforce. Therefore, as long as the total capacity
needed does not exceed the total available, the master schedule should be feasible. He also knows that he can increase his ca- pacity total an additional 2.5 percent through extra overtime and still be within his budget. Given this new information, what recommendations do you have for Joe? What weeks are likely to be problems, and how should he use the capacity in those weeks? How important to NIMCO is it to have a flexible work- force?
On-line Resources
Companion Website www.wiley.com/college/reid: • Take interactive practice quizzes to assess your
knowledge and help you study in a dynamic way • Review PowerPoint slides or print slides for
notetaking • Download Excel Templates to use for problem
solving • Find links to Company Tours for this chapter
Motorola, Inc. Ferrara Fire Apparatus, Inc.
• Find links for Additional Web Resources for this chapter
H&R Block, www.hrblock.com United Parcel Service of America, Inc., www.ups.com APICS—Educational Society for Resource Management, www.apics.org
Selected Bibliography Arnold, J.R. Tony, Stephen N. Chapman, and Lloyd M. Clive. In-
troduction to Materials Management, Sixth Edition. Upper Saddle River, N.J.: Pearson Education Limited, 2008.
Blackstone, John H. Jr., Capacity Management. Cincinnati, Ohio: South-Western, 1989.
Cox, James F., III, John H. Blackstone, and Michael S. Spencer, eds. APICS Dictionary, Twelvth Edition. Falls Church, Va.: American Production and Inventory Control Society, Inc., 2005.
Gessner, Robert A. Master Production Schedule Planning. New York: John Wiley & Sons, 1986.
Narasimhan, Sim, Dennis W. McLeavey, and Peter Billington. Production Planning and Inventory Control, Second Edition. Englewood Cliffs, N.J.: Prentice-Hall, 1995.
Plossl, George W. Production and Inventory Control: Principles and Techniques, Second Edition. Englewood Cliffs, N.J.: Prentice- Hall, 1985.
Slack, Nigel, Stuart Chambers, and Robert Johnston. Operations Management, Third Edition. Upper Saddle River, N.J.: Pearson Education Limited, 2001.
Vollmann, Thomas E., William L. Berry, D. Clay Whybark, and F. Robert Jacobs. Manufacturing Planning and Control Systems, Fifth Edition. Burr Ridge, Ill.: McGraw-Hill/Irwin, 2005.
D24 • SUPPLEMENT D MASTER SCHEDULING AND ROUGH-CUT CAPACITY PLANNING
Additional Resources Available Only in WileyPLUS: • Use the e-Book and launch directly to all
interactive resources • Take the interactive Quick Test to check your
understanding of the chapter material and get immediate feedback on your responses
• Check your understanding of the key vocabulary in the chapter with Interactive Flash Cards
• Use the Animated Demo Problems to review key problem types
• Practice for your tests with additional problem sets
• And more!
reid_suppD_001-024hr.qxd 9/4/09 11:19 AM Page D24
<< /ASCII85EncodePages false /AllowTransparency false /AutoPositionEPSFiles true /AutoRotatePages /None /Binding /Left /CalGrayProfile (Gray Gamma 2.2) /CalRGBProfile (sRGB IEC61966-2.1) /CalCMYKProfile (U.S. Web Coated \050SWOP\051 v2) /sRGBProfile (sRGB IEC61966-2.1) /CannotEmbedFontPolicy /Error /CompatibilityLevel 1.4 /CompressObjects /Off /CompressPages false /ConvertImagesToIndexed true /PassThroughJPEGImages true /CreateJDFFile false /CreateJobTicket true /DefaultRenderingIntent /Default /DetectBlends true /ColorConversionStrategy /LeaveColorUnchanged /DoThumbnails true /EmbedAllFonts true /EmbedJobOptions true /DSCReportingLevel 0 /EmitDSCWarnings false /EndPage -1 /ImageMemory 524288 /LockDistillerParams true /MaxSubsetPct 100 /Optimize false /OPM 1 /ParseDSCComments true /ParseDSCCommentsForDocInfo true /PreserveCopyPage true /PreserveEPSInfo true /PreserveHalftoneInfo true /PreserveOPIComments false /PreserveOverprintSettings true /StartPage 1 /SubsetFonts false /TransferFunctionInfo /Preserve /UCRandBGInfo /Preserve /UsePrologue false /ColorSettingsFile () /AlwaysEmbed [ true ] /NeverEmbed [ true ] /AntiAliasColorImages false /DownsampleColorImages false /ColorImageDownsampleType /Bicubic /ColorImageResolution 300 /ColorImageDepth 8 /ColorImageDownsampleThreshold 1.00000 /EncodeColorImages true /ColorImageFilter /FlateEncode /AutoFilterColorImages false /ColorImageAutoFilterStrategy /JPEG /ColorACSImageDict << /QFactor 0.76 /HSamples [2 1 1 2] /VSamples [2 1 1 2] >> /ColorImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /JPEG2000ColorACSImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /JPEG2000ColorImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /AntiAliasGrayImages false /DownsampleGrayImages false /GrayImageDownsampleType /Bicubic /GrayImageResolution 300 /GrayImageDepth 8 /GrayImageDownsampleThreshold 1.00000 /EncodeGrayImages true /GrayImageFilter /FlateEncode /AutoFilterGrayImages false /GrayImageAutoFilterStrategy /JPEG /GrayACSImageDict << /QFactor 0.76 /HSamples [2 1 1 2] /VSamples [2 1 1 2] >> /GrayImageDict << /QFactor 0.15 /HSamples [1 1 1 1] /VSamples [1 1 1 1] >> /JPEG2000GrayACSImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /JPEG2000GrayImageDict << /TileWidth 256 /TileHeight 256 /Quality 15 >> /AntiAliasMonoImages false /DownsampleMonoImages false /MonoImageDownsampleType /Average /MonoImageResolution 1200 /MonoImageDepth -1 /MonoImageDownsampleThreshold 1.00000 /EncodeMonoImages true /MonoImageFilter /CCITTFaxEncode /MonoImageDict << /K -1 >> /AllowPSXObjects false /PDFX1aCheck false /PDFX3Check false /PDFXCompliantPDFOnly false /PDFXNoTrimBoxError true /PDFXTrimBoxToMediaBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXSetBleedBoxToMediaBox true /PDFXBleedBoxToTrimBoxOffset [ 0.00000 0.00000 0.00000 0.00000 ] /PDFXOutputIntentProfile (None) /PDFXOutputCondition () /PDFXRegistryName (http://www.color.org) /PDFXTrapped /False /SyntheticBoldness 1.000000 /Description << /ENU <FEFF00480052> >> >> setdistillerparams << /HWResolution [2400 2400] /PageSize [612.000 792.000] >> setpagedevice