610 Assignment

jsbfg0001
study.pdf

Journal of Industrial Engineering and Management JIEM, 2015 – 8(2): 491-508 – Online ISSN: 2013-0953 – Print ISSN: 2013-8423

http://dx.doi.org/10.3926/jiem.1328

Study on the Project Supervision System Based on

the Principal-Agent Theory

Runtong Zhang, Yang Zhou, Hongnan Zhuang, Xiaomin Zhu

Beijing Jiaotong University (China)

rtzhang@bjtu.edu.cn, 12120678@bjtu.edu.cn, 13120650@bjtu.edu.cn, xmzhu@bjtu.edu.cn

Received: November 2014 Accepted: January 2015

Abstract:

Purpose: In order to solve problems in the current project management system, the paper

presents the asymmetric information games existing in construction projects through

information economics viewpoints.

Design/methodology/approach: The owner has private information about the project

profitability and he exerts an unobservable level of effort in order to increase the feasibility of

successfully completing the project in terms of meeting product specifications. The paper

analyzes the principal-agent relationship between the owner and supervisor with “principal-

agent theory” of the game theory. In addition, the paper validates the model through two

project cases.

Findings: We can conclude that the incentive contract plays an important role in reducing the

moral hazard. The main contribution of this study is to examine the influence of both pre-

contractual private information and the sensitivities between the interrelated performance

measures on the design of an optimal incentive contract.

Social implications: At last, some advices are put forward to advance the project management

system in China, and some external mechanism can effectively inhibit the "moral hazard" and

"adverse selection" to occur.

-491-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Originality/value: A model of principal-agent relationship between the owner and supervisor

is formulated. This model takes consideration of the moral hazard, which is different from

most existing researches in this field.

Keywords: project supervision, asymmetric information, principal-agent

1. Introduction

The project management system of China’s construction market has experienced a long

process of three systems. The first one is the unitary planned economy system; the second

one is the binary model between owner and contractor; the third one is the currently used

triangle model between owner, contractor and supervisor (Liu, 2007). The introduction of the

project supervision system is designed to form the equilibrium among the construction market

participants. However, there are a series of problems in the actual operation of the project

supervision system, which seriously restrict the formation of the market mode (Huang, Cheng

& Tan, 2003). The development of information economics has given a good explanation for the

above problems. The economics of information, which uses the asymmetrical information game

theory, is an application in economics, and it is also a new development of microeconomics.

The hypothesis of information asymmetry is the foundation of the existence of information

economics. In the construction market, the owner and the contractor are the parties of the

information asymmetry game. The introduction of project supervision system can reduce the

information asymmetry, so that the game is becoming fairer. It is in consonance with the

supervising principles of fairness and justice. In China, the supervision market is still in the

period of development. Therefore it is urgent to use a comprehensive and fair bidding system

in construction market to solve this problem.

2. The Principal–Agent Problem

The principal–agent problem or agency dilemma occurs when one person or entity (the

"agent") is able to make decisions that impact, or on behalf of, another person or entity: the

"principal". The dilemma exists because sometimes the agent is motivated to act in his own

best interests rather than those of the principal. The agent-principal relationship is a useful

analytic tool in political science and economics, but may also apply to other areas.

The problem arises where the two parties have different interests and asymmetric information

(the agent having more information), such that the principal cannot directly ensure that the

agent is always acting in its (the principal's) best interests[2], particularly when activities that

are useful to the principal are costly to the agent, and where elements of what the agent does

-492-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

are costly for the principal to observe. Moral hazard and conflict of interest may arise. Indeed,

the principal may be sufficiently concerned at the possibility of being exploited by the agent

that he chooses not to enter into a transaction at all, when that deal would have actually been

in both parties' best interests: a suboptimal outcome that lowers welfare overall. The deviation

from the principal's interest by the agent is called 'agency costs (Hu, 2004).

Various mechanisms may be used to align the interests of the agent with those of the

principal. In employment, employers (principal) may use piece rates/commissions, profit

sharing, efficiency wages, performance measurement (including financial statements), the

agent posting a bond, or the threat of termination of employment.

As a solution to the principal–agent problem, though, tipping is not perfect. In the hopes of

getting a larger tip, a server, for example, may be inclined to give a customer an extra large

glass of wine or a second scoop of ice cream. While these larger servings make the customer

happy and increase the likelihood of the server getting a good tip, they cut into the profit

margin of the restaurant. In addition, a server may dote on generous tippers while ignoring

other customers, and in rare cases harangue bad tippers.

3. The Establishment of the Principal-Agent Model

In the engineering construction, the information asymmetry between the owners and

supervisors often leads to the moral hazard problem, which means the supervision work

performance will be far from the owner’s intended target (Zhu, Zhou & Wu, 2011).

This section will use the "principal-agent theory" to analyze the principal-agent relationship

between the owner and the supervisor in the project supervision system. According to the

different assumptions, there are two different kinds of principal-agent models between the

owner and the supervisor (Qin, 2004). And then, we can get the analysis of the owner and the

supervisor’s choice and behavior.

3.1 The Certain Principal-agent Model of Fixed Compensation

There are three hypotheses, which are the preconditions of this model.

Hypothesis 1: The principal-agent relationship between the owner and supervisor is

based on a kind of standard contract. The owner only chooses whether it provides the

contract,but the owner can't choose to pay the remuneration or functions paid to the

supervisor.

-493-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Hypothesis 2: The supervisor's work is without uncertainty, which means that the output

of the supervisor is a certain function to the degree of efforts. Therefore, the owner can

master supervisor's working condition according to the results.

Hypothesis 3: The supervisor's behavior choice is discrete, only including hard work and

lazy work.

In this model, firstly, the owner decides whether to receive a trust. Besides, the supervisor

determines whether or not to accept the contract. Finally the supervisor chooses how to work

hard after the contract. This is a three-stage game, which can be described by a game tree.

Figure 1. Principal-agent game tree

Now we analyze the game between them under the assumptions closed to the actual situation.

In this game, the two parties know clearly about the profits about the two sides and they can

observe the choices of the opposite side. Therefore, the game is a complete and perfect

information dynamic game, which can be analyzed by the backward induction.

Firstly, analysis of the supervisor's level of efforts plays an important role in the third stage. If

the supervisor tries to work hard, the owner can get a high output R(H) and he must pay for

the supervisor a high wage v(H); the supervisor gets a high v(H), but he has a high negative

utility (cost) -H. Ultimately, the gains of the owner is R(H) - v(H), and the supervisor's profit is

v(H) - H. If the supervisor chooses not to work hard, so the owner gets a low output R(L); the

supervisor gains a low wage v(L), and has a lower negative utility -L. In the end, the benefit of

the both sides respectively is R(L) - v(H) and v(L) - L. According to the principle of rational

game, if:

R(H) - H > v(L) - L (1)

-494-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

At this time, the supervisor will choose to work hard. The inequality (1) is an incentive

compatibility constraint (IC) of the hardworking supervisor. The hardworking supervisor to be

paid can get the basic pay or more than the lazy ones. At the same time, the wage of the

struggling must can compensate for a greater negative effect than the lazy ones. As a

consequence, the supervisor could choose to work hard automatically. If the constraint

conditions cannot be met, the supervisor must choose not to take efforts.

Secondly, it is essential to judge whether the supervisor accepts the commission. For the third

stage the supervisor can choose whether to work hard, corresponding to different benefits. As

the rational game party, in both cases, the conditions for the supervisor choosing to accept the

contract are: v(H) - H > 0 (work hard); v(L) - L > 0 (not work hard).

The two inequalities are the constraint conditions which can decide the supervisor's choice. The

economic meaning is: the supervisor's profit from the contract can't get less than the

maximum of not accepting the contract. This is the basic condition for the supervisor accepting

the commission.

Finally, the choice of the first stage needs a detailed explanation. R(0) stands for the owner's

profit when the owner doesn't entrust a supervisor. If the supervisor chooses to refuse in the

second stage, the owner's choice is without meaning. If the supervisor chooses to accept the

commission in the second stage, the owner makes the decision according to the supervisor's

choice in the third stage. Only when the supervisor’s benefits are positive, can the owner

choose to entrust.

By summarizing the two game parties' choices, we can get the sub-game perfect Nash

equilibrium. This model is a complete process of signing the contract. As rational parties, the

owner must get more profit by the commission. The supervisor demands he should get a

greater benefit than (or at least equal to) the maximum income when not accepting the

contract. While working hard makes greater benefits, the supervisor will naturally choose to

make efforts.

3.2 The Uncertain Principal-Agent Model of Selective Compensation

The above model is under some additional assumptions. The supervisor's work is certain and

observable, which obviously is a simplification of the reality. Now we analyze the game

between them under the assumptions closed to the actual situation.

Hypothesis 1: The supervisor's work is uncertain, which means his output is not only

determined by his own efforts, but also by the outside control of the objective conditions.

Hypothesis 2: The supervisor can choose the reward function, that is, the pay system.

-495-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Hypothesis 3: The supervisor's level of efforts is a continuous variable, assuming e is a

one-dimensional continuous variable.

Hypothesis 4: The owner is risk neutral; however, the supervisor is the type of risk-

averse.

In addition, the supervisor has a positive opportunity cost when he doesn't accept the

commission. Then we analyze the principal-agent model under the above assumptions.

Firstly, assume that the supervisor's output function and the level of effort is linear

relationship:  = e + q. q obeys the normal distribution, where m = 0, Var = s2, standing for the

exogenous uncertain variable. By the formulas: Ep = E (e + q) = e, Var(p) = s2, we can

conclude that the effort of supervisor decides the m, not affecting the Var. Suppose the contract

between the two parties using a linear: s(p) = a + bp, where a is the fixed income of the

supervisor (nothing to do with the p), and b is the project share of the output. b = 0 means

that supervisor doesn't take risk. b = 1 means that the supervisor bears all the risk. Because

the owners are risk neutral, given s(p) = a + bp, the owners' expected utility equals to

expected income:

Ev(p-s(p)) = E(p-a-bp) = - a + E(1-b) p = - a + (1-b) (2)

Assume the utility function of the supervisor is with characteristics of risk-adverse.

That is m = -erv, where r is the absolute measure of risk aversion, v is the real international

monetary income. Assume the supervisor's cost: c(e) = 1 2

be2, where b represents the cost

factor. With the same effort, the larger b is assigned, the greater negative is brought. The

supervisor's actual income is:

v = s(p) - c (e) = a + b(e + q) - 1 2

be2 (3)

Because the supervisor is risk-averse, the certainly equivalent income equals to the mean

income minus the random cost of risk. Therefore, uncertainly equivalent income:

Ev - 1 2

rb2s2 = a + be - 1 2

rb2s2 - 1 2

be2 (4)

-496-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Ev is the supervisor’s expected income. 1 2

rb2s2 is the risk costs of the supervisor. When b = 0,

the supervisor's cost of risk is 0, which means the supervisor doesn't take any risks at this

time. The supervisor's largest expected utility function is equivalent to the certainty equivalent

income, that is:

Em = a + be - 1 2

rb2s2 - 1 2

be2 (5)

Where v stands for the supervisor's retained income levels. Therefore, if the supervisor's

certainly equivalent income is less than v, the supervisor will not accept the contract. As a

consequence, the participation constraint of the supervisor is as follows:

Em = a + be - 1 2

rb2s2 - 1 2

be2  v (IR)

On the incentive constraint (IC), we can carry on the analysis of two cases:

• The owners can observe the effort level of the supervisor. Because the owner can

observe the effort level e, then the incentive constraint does not work. Any level of e

can be achieved by meeting the mandatory contract. Therefore, the owner's problem is

how to determine a, b, e to achieve the maximum benefit.

The mathematical model of optimization is as follows:

max a ,β, e

Ev=−a +(1−β) e (6)

s.t. a + be - 1 2

rb2s2 - 1 2

be2  v (IR)

In the best case, the equation of IR constraint is true, because the owner does not need

to pay more for the supervisor. We can use the constraints to obtain by the

deformation of the equation, namely:

-a = be - 1 2

rb2s2 - 1 2

be2 - v (7)

Take -a into the objective function, getting the most objective optimization function:

max a ,β ,e

(e− 1 2

ρ β2 σ2− b 2

e2−ω) (8)

Derivative of the objective function, the optimal first-order conditions were: e* = 1 b

;

b* = 0.

-497-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Take the results into the IR constraint equation (7):

a ✳=ω̄+

b 2

(e✳)2=ω̄+ 1

2 b (9)

The economic analysis of the solution: b* = 0, the supervisor does not take any risk,

and the income has nothing to do with the output; a✳=ω+ 1

2 b , that the fixed income

that the owner pays to the supervisor equals to the supervisor's retained income plus

the cost of effort; e✳= 1 b

achieving an optimal level, ie 1 = be. When the owner

observes the supervisor's choice of e< 1 b

, he will pay for the supervisor av < a*, so the

supervisor will certainly choose e= 1 b

.

• The supervisor's effort level e can't be observed. The supervisor will choose to

maximize his certainty equivalent income. After derivation calculus to equation (4), we

can get: e= β b

.

At this point the incentive constraint for the supervisor is e= β b

. When the supervisor

does not take any risk (for a given b = 0), e= β b

 e = 0, the supervisor will choose e =

0 instead of e= 1 b

. The problem of the owner is how to determine a, b to achieve the

maximization. The mathematical model of optimization is as follows:

max a ,β, e

Ev=−a+(1−β) e

s. t{(IR) a+β e− 1 2

ρβ2 σ2−1 2

be2≥ω

(IC) e= β b

(10)

Taking constraint (IR) and incentive constraints (IC) into the objective function, then we

can obtain the following objective function:

max β ( βb − 12 ρβ2 σ2−b2 ( βb )

2

−ω) (11) Get a first-order derivative:

1 b

−ρβ σ2− β b

=0 (12)

-498-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

That is

β= 1

1+b ρσ2 >0 (13)

This solution means that the supervisor must take some risks, and b is a decreasing

function about r, s2 and b.

From the perspective of incentive, when there is no information asymmetry, the greater

b is, the smaller e (the optimal e✳= 1 b

) is. From the perspective of risk-sharing, the

greater b is, the bigger β( e= βb) is. The owner prefers a lower risk of cost savings. If the

level of effort can be observed when b = 0, the optimal effort level of e= 1 b

; on the

other side, when b > 0, the supervisor can automatically select the optimal effort level:

e= β b

= 1

b( 1+b ρσ2) < 1 b

(14)

Analysis:

• The optimal level of effort under the asymmetric information strictly less than the level

of effort under the symmetric information. So when the owners can’t observe the

measured e, the supervisor will choose e < e* to improve their welfare. Because the

level of output not only relates to the level of effort with the supervisor, but also by the

impact of exogenous variables q. Attributed to adverse exogenous effects (such as

some non-objective control conditions, including the natural conditions), so the

supervisor can avoid accusations of the owners. This is the so-called "moral hazard"

problem.

• The owner can’t observe the supervisor's effort level e, the supervisor should bear risk

than the symmetric information cases.

Conclusion: When the owner can observe the effort level e of the supervisor, both sides have

the symmetric information. Both Pareto optimal risk-sharing and Pareto optimal level of effort

can be achieved. The Pareto optimal contract: the supervisor doesn’t take any risk, and the

owner pay fixed income a✳=ω+ 1

2b (the supervisor's retained income plus the cost of effort) to

the supervisor. Therefore, the optimal level of effort is e✳= 1 b

.

-499-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

When the owner can’t observe the effort level e of the supervisor, that is, there is asymmetric

information. Both Pareto optimal and Pareto optimal risk-sharing can ‘t be achieved, then the

optimal contract is: to design a given incentive (b* > 0), the supervisor takes some risks,

whose optimal level of effort less than that under the symmetric information. The owner

selects the expected conducts through the selection and designed incentives to maximize their

expected income.

4. Project Case

4.1 Case One

The owner of a construction prepares to seek a supervision unit. There are three units have

the cooperation intention, and the owner can observe the effort level of the supervision unit.

The first supervision unit A requires the owner to pay the minimum wage RMB 2,000 to the

supervisors. The effort cost factor b is 0.0002. The second supervision unit B requires the

owner to pay the minimum wage RMB 2,300 to the supervisors. The effort cost factor b is

0.0003. The third supervision unit C requires the owner to pay the minimum wage RMB 2,500

to the supervisors. The effort cost factor b is 0.0005. According to the optimal linear contract

under the condition that the supervisor’s effort level e can be observed, the results are shown

in the table. From the calculated results in the Table 1, the owner should choose the third

supervisor unit C.

supervisor //RMB b //RMB //RMB //RMB A 2,000 0.0002 5,000 4,500 500 B 2,300 0.0003 3,333.3 3,966.7 -633.4 C 2,500 0.0001 10,000 7,500 2,500

Table 1. The calculated results of game analysis between the owner and the supervisor

4.2 Case Two

One project owner intends to sign a principal-agent contract with a supervisor. The owner can’t

observe the supervisor’s effort level. The cost factor is b=0.0001; the absolute measure of risk

aversion r=0.1; the minimum wage is v=2,000; the exogenous uncertain variable

q~N(0.3002).

-500-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

According the formulas, we can get:

β = 1

1+b ρ σ 2 =

1 1+0.0001x 0.1x 90,000

=0.526

e= β b

= 0.526

0.0001 =5,263.158

a =ω + 1 2

be2+ 1 2

ρ β 2σ 2− β e=2,000 +1,385.042+ 1 2

x 0.1 x 0.5262 x90,000−0.526 x5,263.158

=1,861.496

s (π )=a +β π =a +β (e+θ )=1,861.496+0.526 x5,263.158=4,630

At last, we can get the result: s (π )=4,630 RMB, that is, if the owner signs the above contract

with the supervisor, their profit will achieve balance at the same time.

5. The Impact of the Construction Supervision System

In the economic market, the rights and obligations among economic actors are expressed

through contracts. Once the contract relationship is established, it is difficult to observe the

conduct of the parties, which may result in moral hazard. The principal-agent model is the

basic framework to solve this problem. In the transaction process, the party with information

advantage is called the agent, while the other side is called the principal. The assumption

behind the definition is that the private information will affect the interests of the insiders

(Zheng, 2002). In the construction market, the relationship between the owner and the

supervisor is a typical principal-agent model.

5.1 The Basic Problem

The principal-agent relationship between the owner and the supervisor is the foundation of the

existence of the construction supervision system. The meaning of the construction supervision

is: the supervisor accepts the commission of the owner, and the supervisor should stands for

the owner to conduct the micro-supervision and management according to state-approved

construction, project construction documents, the construction of laws, regulations and

supervisory construction. From the meaning of the term, since the owner commissions the

supervisor, it would depend on the supervisor to implement the construction supervision and

management. The owner of the provisions implements their own rights and obligations within

the scope of supervision. The owner should not be beyond the supervision of the contract

rights. However, in the actual construction, the problem lies in the fact that the owner often

interferes with the supervising supervisor of the construction supervision and management.

-501-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

The destruction of the principal-agent relationship between the owners and the supervisor is

closely related to the potential moral hazard. In the actual construction market, because of the

absence of better incentive system, China's supervision is still in the early stages of

development. The credit of supervision industry is low, and some supervisors are of low

quality. Therefore, the owner often breaks the principal-agent relationship, in order to avoid

potential moral hazard. This destruction between the owner and the supervisor leads to a

direct consequence of more asymmetric information, intensifying the fraud of the construction

market, increasing the costs of society.

In the principal-agent relationship between owners and supervisors, there are two stages of

information asymmetry. As the owner has no knowledge of the ability of supervisors,

knowledge and reputation and other private information before signing the contract, owners

may lead to lower prices over the ability of supervisors out of a competitive market, so that

some low-level supervisors stay. Then the "adverse selection" arises. After signing the

contract, when the supervisors' behavior can’t be observed by owners, the information

asymmetry arises, and leads to "moral hazard". Through the above principal-agent game

analysis between owners and supervisors, we can see that under asymmetric information,

inhibition of "moral hazard" and "adverse selection" by the internal mechanism is designed to

achieve reasonable contract supervision. At the same time some external mechanism can

effectively inhibit the "moral hazard" and "adverse selection" to occur. China has adopted a

supervision system for more than ten years, and the supervision system in the healthy

development of reform and construction industry has played an important role. However, the

low commission fees, inadequate supervision and other issues are increasingly prominent,

which is a serious impact on the further deepening of supervision system. Through the

relationship of the principal-agent game analysis between owners and supervisors, we can

reduce the "moral hazard" and "adverse selection" by well-designed contract, while achieving

the interests of owners and supervisors to maximize the long-term interests, so as to achieve

"win-win" is a matter of concern.

We have studied optimal incentive contracts offered to a research and development (R&D)

manager, who can propose an innovative project and is in charge of conducting this project.

The solution to our optimal contracting model shows that incentives on the basis of the firm’s

market value are stronger for more profitable than for less profitable projects, and incentives

on the basis of efficiency objectives are stronger for less profitable than for more profitable

projects. The reason for the latter counter intuitive result is that strong incentives on the basis

of the firm’s market value place too much risk on the project manager, in particular, for

executing his routine job. These strong incentives are softened by reducing incentives for

efficiency objectives that directly affect the effort in the routine job.

-502-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

5.2 The Current Situation

The introduction of the construction supervision system effectively reduces the asymmetric

information in project construction. However, the degree of the asymmetric information is

related to the ability providing high-quality and high-tech services. After ten years of

development, the project management industry in China has made great progress in

significant quantities, but it varies greatly in quality. The qualified supervision is less than 10%.

The reasons for a lower level of supervision of the industry are various, such as the community

supervision system is not completely. It's also related to the supervision of industry and

personnel structure, training and personnel mechanisms. In our present supervision of

employees in the industry, vast majority of supervisors are from the construction, design

department. This part of the staff has a good supervisory; however, they are not proficient in

the economy, laws, regulations and policies for the economy market of today. Therefore,

developing a number of high-quality supervisory, supervision as soon as possible is urgency.

However, both the social and the current higher education don't have the training on the

supervision industry. Even if the supervisory unit doesn't have a long-term plan and a

complete incentive system, people don't realize that the lack of talent is the bottleneck to

restrict its development. And a supervision of the construction industry of low quality can't

meet the reduction of asymmetric information to the market requirements. As China enters the

WTO, the international market and domestic market opens, as a result, supervision is facing

severe challenges, which also brings opportunities. It is more essential to train a high-quality

supervision team.

6. The Solution of the Asymmetric Information

In summary, the supervision market in China has been improved to a certain extent, but there

are still some problems to solve. In face of the structure of the open market today, it is an

urgent matter for us to strengthen. It is a realistic problem to make the construction industry

in China occupying a place in the international market. The asymmetric information in the

construction industry is common. It is a question for each practitioner and theoretical study to

focus on, which includes how to regulate the behavior of participants and how to eliminate the

asymmetric information. It requires the building practitioners and the market managers to

understand the importance of the asymmetric information in-depth. The parties need to be

aware of the significance of the elimination of asymmetric information. As for the serious

trouble currently in the construction project management, the solutions should be proposed

timely.

-503-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

6.1 For the Owner

• Strengthen the owners' monitoring mechanism. From the analysis of the boundary

function, we can see that the larger the penalties are, the greater the level of its

regulatory efforts is. So the owner can have a greater space of supervision. As a

consequence, it is better to promote the careful supervision of the commissioner of

party choice behavior. Therefore, in the actual operation of the construction, owners

should strengthen supervision and management, and establish a good transport

mechanism, effectively suppressing the third-party misconduct, to ensure the

successful completion of the project.

• Achieve project management are instead of supervision system. Employ professional

project Management Company to manage the entire project. Create new project

management model. Use the consecutive payments incentive mode in stage in the

project management, so that the agent can understand the existence of the incentive,

prompting them to work hard. There are many factors about the supervisor's

performance rewards. Firstly consider the quality of the supervisor, which decides the

ability level, the absolute risk aversion degree and the effort cost. The stronger of the

supervisor's ability is, the greater of the ability with risks is, and the more adventurous

of personality characteristics. The owner of the project chooses a supervisor which

should be suited to the characteristics of the project on quality as the premise of the

incentive mechanism playing its proper efficiency. Under the condition of asymmetric

information, the Pareto optimal linear contract can be achieved. Because of the owner is

a risk neutral party, the agent should be aware of the risk aversion, Pareto risk sharing

requests the supervisor not assuming any risk, and the owner don't need to make any

incentive agent. Under the condition of asymmetric information, the performance

reward that the supervisor gets should reflect the changes in the external environment

condition. The owner's performance reward is scheduled generally according to the

project performance, but the project performance not only completely depends on the

effort level, but also the result of the joint of the external environment factors. When

the risk increases, the owner should reduce the risk level. When the supervisor's risk

reduces, the owner should increase the affordable risk of the supervisor, to motivate the

agent's enthusiasm. Therefore, when making supervisor‘s performance rewards should

exclude more external factors as much as possible.

-504-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

6.2 For the Supervisor

• Strengthen the internal construction of the supervision and establish a scientific and

effective incentive system, such as the bonus incentives about the claimed loss and the

construction process associated with quality. Internal mechanism is through rational

design agent contract to develop an incentive mechanism, so that the supervisors'

target will close to the owners'. Taking this measure can alleviate supervisors to take

opportunistic behaviors and make the dynamic adverse selection, so that moral hazard

and adverse selection can be suppressed. But whether the internal mechanism can play

the expected role depends on owners' choice of supervisors, monitoring and evaluation

of right or wrong, that is, it depends on the correctness of the information obtained. If

owners are in order to provide high effectiveness of the operation of this mechanism, it

needs the appropriate measures and cost, so that they can get the information to

"select the appropriate project division "and" make the supervisor perform accurately".

Therefore, the internal machine system only can reduce the efficiency of the non-

agency relationship to a certain extent, but its validity is subject to the information

costs and the limitation of the imperfect information. Taking the appropriate incentives

to reduce the probability of moral hazard issue can reduce the illegal construction

practices. Owners can sign a contract with the construction side, to meet the quality

requirements of the premise in the case of early completion, giving a certain

percentage reward, which are not more than the additional revenue of the illegal

construction obtained. Thus, it not only can reduce the construction side's cheating

space, and improve the enthusiasm of the construction to choose the normal building,

also promoting the project to put into use in advance, as soon as possible to recover

the investment.

• To solve the "adverse selection" and "moral hazard" in asymmetric information

environment, reputation effects have a valid role. When the game only performs once

or a limited time (for supervisors only exist in the market for a short-term), supervisors

only care about each stage of the current income. However, if the game is infinitely

repeated (the supervisor on the market for a long term), any short-term opportunistic

behavior of the proceeds are negligible.

-505-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

6.3 For the Contractor

Show great strength to increase the punishment to illegal construction parties. Increasing the

punishment can enhance the supervisor to take the work seriously and make up the mistakes

that the asymmetric information has made. As a result, the risk of the moral hazard will be

decreased to a great extent. The solution of the game elements of the relationship between

variables and analysis increases the punishment, which can reduce cheating effectively. Many

construction sites that are in order to achieve maximum self-interest, with this solution, the

probability of the occurrence of moral hazard will be decreased. Although the punishment is

too large to some extent can contain illegal act of construction parties, but may also reduce

their construction initiative. The determination of punishment not only plays a limited role in

illegal construction of the construction sides. And the actual situation should be based on the

relationship between punishment and enthusiasm.

6.4 For other Sides

• Strengthen our building laws and regulations and speed up the construction of the

standardization process of building market. Improve the existing supervision system,

and establish the self-regulatory mechanism of this industry, forming a fair market,

having honest ethics and values. Industry associations should make a series of

information disclosure, clear and workable agreement to improve the transparency of

information, to provide a platform for healthy and orderly for the supervisors.

Meanwhile, the supervisor should take reasonable incentives, improving the supervision

of supervision for serious acts of favorable space to a certain extent, increasing their

motivation and effectiveness.

• Strengthen the education of the perpetrator in the construction market. Ensure they are

aware of information asymmetry prevalent in the construction industry and the

construction supervision system in addressing the role of asymmetric information.

• External mechanism is the introduction of competition between supervisors. Sound and

effective competition in the market plays a self-restraint, self-monitoring role for

supervisors, and has a memory function to the accumulation of the results of their

actions. Reputation can be accurately reflected by the market. For reputation

considerations, supervisors will make a commitment, and always tend to choose to

maximize the effectiveness of the actions of owners, to get the market's trust in order

to better foothold in the market.

-506-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

6.5 Brief Summary

The supervisor will have enthusiasm to build a good reputation to achieve greater benefits for

long term. It is urgent to establish a sound and effective and competitive supervision market in

China. When reputation is no longer a moral issue, but a system, the results will improve the

game balance.

7. Conclusion

Through the above principal-agent game analysis between owners and supervisors, we can see

that under asymmetric information, inhibition of "moral hazard" and "adverse selection" by the

internal mechanism is designed to achieve reasonable contract supervision. At the same time

some external mechanism can effectively inhibit the "moral hazard" and "adverse selection" to

occur. Through two project cases, we validate the model successfully. The solution to our

optimal contracting model shows that incentives on the basis of the firm’s market value are

stronger for more profitable than for less profitable projects, and incentives on the basis of

efficiency objectives are stronger for less profitable than for more profitable projects.

Acknowledgments

This work is partially supported by a major program of the National Social Science Fund of

China (Grant No. 13&ZD026), a Specialized Research Fund for the Doctoral Program of Higher

Education (Grant No. 20120009110009).

References

Hu, R. (2004). The Discussion of Information Economics to Engineering Supervision Institution.

Hongshui River, (23), 97-100.

Huang, B.X., Cheng, Z.H., & Tan, D.M. (2003). The Explanation of Information Economics to

Engineering Supervision Institution. Architecture and Construction, (7), 42-45.

Liu, Y.M. (2007). Study on Project Management System through Information Economics

Viewpoint. Science & Technology Information, (19), 159-160.

Qin, X. (2004). Game Analysis of Principal-agent Relationship under the Supervisoring

Supervision Institution. Soft Science of China, 04, 142-46.

-507-

Journal of Industrial Engineering and Management – http://dx.doi.org/10.3926/jiem.1328

Zhu, L.M., Zhou, J., & Wu, X.L. (2011). The Incentive Supervise Model of Project Supervision

Based on Principle-agent Theory. Operations Research and Management Science, 20(3),

176-179.

Journal of Industrial Engineering and Management, 2015 (www.jiem.org)

Article's contents are provided on a Attribution-Non Commercial 3.0 Creative commons license. Readers are allowed to copy, distribute

and communicate article's contents, provided the author's and Journal of Industrial Engineering and Management's names are included.

It must not be used for commercial purposes. To see the complete license contents, please visit

http://creativecommons.org/licenses/by-nc/3.0/.

-508-

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

  • ICAJNGM_JNGM_v8n2_201501011328.pdf
    • Study on the Project Supervision System Based on the Principal-Agent Theory
    • 1. Introduction
    • 2. The Principal–Agent Problem
    • 3. The Establishment of the Principal-Agent Model
    • 4. Project Case
    • 5. The Impact of the Construction Supervision System
    • 6. The Solution of the Asymmetric Information
    • 7. Conclusion
    • Acknowledgments
    • References