PROJECT FAST INVENTORY

Delivered by: The IT Professionals

2

Table of Contents

Company Information ................................................................................................................... 4

Brief History & Background ...................................................................................................... 4

Mission Statement ..................................................................................................................... 4

Organizational Structure ............................................................................................................ 5

Duties & Responsibilities ........................................................................................................... 5

Executive Summary ...................................................................................................................... 7

Project Overview .......................................................................................................................... 8

Project Background ...................................................................................................................... 9

Project Charter ............................................................................................................................10

General Project Information ...................................................................................................10

Project Team .........................................................................................................................10

Stakeholders ..........................................................................................................................10

Project Scope Statement .........................................................................................................10

Communication Strategy ........................................................................................................12

Sign-off ..................................................................................................................................12

Notes .....................................................................................................................................12

Work Breakdown Structure ..........................................................................................................13

Gantt Chart .................................................................................................................................14

SWOT Analysis ..........................................................................................................................15

Network Documentation ..............................................................................................................17

Network Topology ...................................................................................................................17

Network Implementation ..........................................................................................................18

Network Hardware ...................................................................................................................19

Database Documentation ..............................................................................................................21

Entity Relationship Diagram .....................................................................................................21

Database Tables .......................................................................................................................22

Website Documentation ...............................................................................................................25

Website Purpose ......................................................................................................................25

IPO Chart................................................................................................................................26

Navigating the Website .............................................................................................................27

3

Website Sample Code ...............................................................................................................31

Mobile Application Documentation ...............................................................................................34

IPO Chart................................................................................................................................35

Mobile App Navigation ............................................................................................................36

Mobile Application Sample Code ..............................................................................................39

Finance Documentation ................................................................................................................42

Project Budget .......................................................................................................................43

ROI & NPV ............................................................................................................................46

Training and Service Level Agreement ..........................................................................................48

Training ..................................................................................................................................48

Service Level Agreement ..........................................................................................................49

Monitoring and Support ............................................................................................................50

Closing Contract .........................................................................................................................54

Summary ....................................................................................................................................57

4

Company Information

Brief History & Background

The IT Professionals is a technological solutions company that was started in Bronx, NY

in 2016 by a group of Monroe College’s IT Students. It was begun by creating solutions for

business who needed to find a way to make day-to-day operations more efficient and effective.

Currently IT Professionals is still being operated from Bronx, NY and working on a project for

Monroe College’s IT Department.

Mission Statement

To serve our clients by providing quality professional service. We will use the strategy of

innovation and retain knowledgeable professionals as we aim to provide superior end products to

our community.

5

Organizational Structure

Fig. 1

Duties & Responsibilities

Project Manager

● Planning and defining scope

● Activity planning and sequencing

● Resource planning, developing schedules and time estimating

● Cost estimating and developing a budget

● Documentation

● Creating charts and schedules

● Risk analysis and management

● Monitoring and reporting progress

● Team leadership

Network Administrator

● Design and implement network ● Network maintenance ● Provide network security

6

Database Administrator

● Design, develop and implement database systems based on customer requirements

● Establish the needs of users and monitoring user access and security

● Improve database systems to ensure performance efficiency

● Consider the use of database for back-end organization of data and front-end accessibility

for end-users

● Develop database tables and fields.

● Ensure data quality and integrity in databases

● Developing, managing and testing backup and recovery plans

Web Developer

● Write well designed code

● Create website layout

● Integrate data from databases

● Gather requirements based on technical needs

● Create and maintaining web site

Mobile Application Developer

● Write well designed and efficient code

● Create website layout

● Integrate with backend services to ensure delivery of a user friendly mobile application ● Work with the product and design team to understand end-user requirements ● Dive into difficult problems and successfully deliver results within a schedule

Financial Analyst

● Determine cost of operations

● Identify financial status

● Guide cost analysis process

● Calculate employee hourly wages

● Ensure project stays within budget

7

Executive Summary

This document documents all the major components of this project. The company

information focuses on the internal structure of The IT professionals. It outlines each employee

who is working on this project and their roles and responsibilities. The overview and background

of the project gives a detailed summary of the problem needed to be solved and how it will be

solved. It also explains the benefits of the new system to be implemented. The project charter

give details about the project scope (purpose and objective), stakeholders, deliverables,

milestones, risks, constraints and dependencies. The SWOT analysis sums-up the internal and

external strengths, weaknesses, opportunities and threats of the project. In addition the work

breakdown structure is a timeline of how the project will come to fruition. The Gantt chart is a

visual representation of the tasks to be completed that have been outlined in the work breakdown

structure.

The documentation of the functional areas of the project (networking, database, website,

mobile application) all include labeled images for referencing. Each section give a brief, detailed

description about how each section functions. The financial aspect of this project also breaks

down how money allocated to the project has been spent. Also included is the Service Level

Agreement, Training and Closing contract which are legally binding documents that explain how

service is to be maintained between both parties involved and ensuring that all conditions of the

project have been met.

8

Project Overview

The IT Professionals have be contracted by Monroe college to create a quick response

(QR) based system that will automate the asset review process. The system is composed of a

website and mobile application that allows users to scan items into a back-end database. The

information from the database will be presented in the form of reports so that is easier to read.

This project aims to reduce instances of human error that can be caused the by manual counting

of hardware devices. It also aims to reduce the amount of time it takes to perform an asset review

by eliminating redundant counting needed for accuracy. A quick response based system will

enable Monroe College’s IT employees to have an automated inventory system. It will be able to

query those items through a mobile application or website to display the object properties.

This project is only concerned with automating the asset review process of the Monroe

College IT Department. In addition, this project only addresses the IT Department in the Bronx

Campus and will subsequently not include the Queens, New Rochelle or St. Lucia campuses.

9

Project Background

Presently, Monroe College’s IT Department does not have an efficient, digital system to

record the devices they have in each classroom and office. They walk through each classroom

and office and record what they have in a spreadsheet. In order to modernize this process, the IT

Professionals have been contracted to implement a QR based system that will record accurately

what they have and where it is located. This will simplify the process and allow employees’ time

to be invested in other work obligations, especially when they need information for reports. The

website would be an internal website where IT employees use their credentials to login and view

inventory details. The database will hold the information about what type of devices the college

has and where they are exactly located.

.

10

Project Charter

General Project Information

Project Name: Project Fast Inventory

Executive Sponsors: Monroe College

Department Sponsor: Lawrence McGrath

Impact of project: This project will change how the IT Department performs inventory review

Project Team

Name Department Telephone E-mail

Project Manager: Breianna Blair IT Department (646) 512-3010 breiannamblair@gmail.com

Team Members: Jose Ortiz IT Department (347) 483-2645 joselevelsup@gmail.com

Youssef Ballo IT Department (646) 352-3283 youssefb1@gmail.com

Abdullah Hamid IT Department (914) 314-0638 abdullahhizam@gmail.com

Jose Ortiz IT Department (347) 483-2645 joselevelsup@gmail.com

Mark Perez IT Department (914) 409-5429 markperez@live.com

Stakeholders

Monroe College

Lawrence McGrath

IT Department Employees

Project Scope Statement

Project Purpose / Business Justification

The purpose of this project is to create a quick response based system that will automate the asset review

process. The system is composed of a website and mobile application that allows users to scan items into

a backend database.

Objectives

Project Fast Inventory aims to reduce instances of human error that can be caused by manual counting.

Reduce the amount of time it takes to perform an asset review by eliminating redundant counting needed

for accuracy.

11

Deliverables

A quick response based system that enables IT employees to have an automated inventory system by

using a computer/peripheral into a database. They will then be able to query those items through a mobile

application or website to display the object properties.

Scope

This project is only concerned with automating the asset review process of the Monroe College IT

Department. In addition, this project only addresses the IT Department in the Bronx Campus and will

subsequently not include New Rochelle or St. Lucia.

Project Milestones

Inception

Start End

5/16/16 – 5/22/16

Planning

Start End

5/23/16 – 5/31/16

Construction

Start End

6/1/16 – 6/20/16

Delivery

Start End

6/20/16 – 6/30/16

Major Known Risks

Risk Risk Rating (Hi, Med, Lo)

QR Stickers damaged or removed by

students.

Hi

Constraints

Resources such as network equipment. Time in which the application and deployment must be completed.

12

External Dependencies

The project heavily depends on hosting services.

Communication Strategy

The team has agreed to communicate through our mobile devices. Specifically using WhatsApp, a mobile

messeging application, Google Drive to upload individual contributions. Meetings with Monroe College’s

supervisor will be held to ensure the project meets the needs of the IT Department.

Sign-off

Name Signature Date (MM/DD/YYYY)

Executive Sponsor Monroe College Lawrence McGrath 5/15/16

Department Sponsor Lawrence McGrath Lawrence McGrath 5/15/16

Project Manager Breianna Blair Erick Rebolledo 5/15/16

Notes

13

Work Breakdown Structure

The Work Breakdown Structure (WBS) is a document outlining all phases of the project.

The WBS helps the employees working on the project to stay on track with time allocated for

each phase. If the team begins to fall behind, they can reference the chart to see where they need

to put in more work in order to meet deadlines.

Fig. 2

14

Gantt Chart

The Gantt chart is a visual representation of the tasks to be completed that have been

outlined in the work breakdown structure.

Fig. 3

15

SWOT Analysis

Strengths Weaknesses

● Faster and efficient with information

processing

● Low cost of hardware, software,

hosting

● User friendly

● Easily generate inventory count reports

● Does not ensure accuracy

● Data is only as good as the data

entry that created it

Opportunities Threats

● Easy to upgrade

● Ability to code new functionalities like

specialized reports

● Simple to add new devices to the

system

● Budget

● Outsourcing from another

company

● Premature termination of project

Fig. 4

In the SWOT analysis, some strengths have been outlined. Our major strength is that the

system will allow for a faster and efficient way of processing information. This new system has a

low cost of hardware, software, and hosting. Also this system is user friendly as it also allows for

inventory reports to be easily generated.

One of the weaknesses are that this system does not ensure accuracy. This is because the

information inputted is only as good as the entry that created it. If an employee incorrectly inputs

information, then that is what the system will reflect.

One opportunity is that this system is easy to upgrade. There is also the ability to code

new functionalities for specialized reports. One other opportunity is that it is very simple to add

new devices to the system.

16

The threats to this project are the budget, outsourcing from another company and the

premature termination of the project. Monroe College may decide to outsource in order to get the

same service from a different company. The project may face premature termination if the

employees of IT Professionals decide to abandon the project.

Network Documentation

Network Topology

Fig. 5

Network Implementation

This network topology (Fig. 5) will be used to implement Project Fast Inventory. The

network will show external hosting by Heroku, and Monroe College’s network implementation.

On the right side of the topology (Fig. 5), Monroe College’s networking, has a wireless router

where smart phones, QR printers and laptops will connect to gain access to the Wi-Fi. The

firewall software on the wireless router will be activated. The PCs are connected to a switch

which enables for a LAN internet connection. A decision was made to connect the PCs through a

switch because the switch will be able to connect up to 24 devices. If the college wishes to have

additional devices connected, there will be a means of doing so. The database information will

be stored in real-time on Monroe’s server and will be backed up on Heroku’s servers 6pm every

day to prevent the consumption bandwidth at peak hours. As an additional back up, the

information will also be backed up on a 1TB USB drive daily.

The left side of figure 5 is a fictional representation of Heroku’s network topology. It is a

representation of how information will be sent, received and stored to and from Monroe College.

Their network implementation is viewed as follows. The company stores and hosts the college’s

website and database information on a server and is protected with a firewall.

19

Network Hardware

Sierra Wireless AirLink Raven RV50 – gateway

Main Features

● Gateway

● 10Mb LAN

● 100Mb LAN

● GigE

● RS-232

● USB 2.0

● LTE AWS/700/850/1900 / W-CDMA AWS/850/900/1900/2100 / CDMA

800/1700/1900

NETGEAR ReadyNAS 3138 RN31843E - NAS server

Main Features

● 4 bays

● 12 TB

● Rack Mountable

● HDD 3 TB x 4

● RAID 0

● Gigabit Ethernet

NETGEAR AC1900 Nighthawk Smart WiFi Router

Main Features

● C1900 WiFi (600+1300 Mbps)

● 1 WAN & 4 LAN Gigabit Ethernet ports

● Two USB ports

● WPA/WEP2 and WEP Security

● 1GHz dual-core

● 128MB flash and 256 MB RAM

20

NETGEAR ProSAFE 24-Port Gigabit Smart Switch (GS724T)

Main Features

 L3 Lite

 24 Gigabit Ethernet port

 2 SPF Gigabit fiber port

 Rack mountable

Kingston DataTraveler HyperX Predator USB

Main Features

 USB flash drive

 1 TB

 USB 3.0

LabelWorks LW-600P Portable Label Printer

Main Features:

 Built-in Memory

 Tape Cutter

 Open Cover Detection

 Mobile Connectivity

 PC & Mac Connectivity

The vendor for all network hardware components, except the QR printer, is CDW-G. The vendor

for the QR printer is ESPON.

21

Database Documentation

This relational database is used to store inventory and to create, update, and view records

in order to make better managerial decisions. User logins are also handled by the database.

Information will be stored in real-time on Monroe College’s servers. The database will be

backed up at 6pm daily on to Heroku’s servers. The E-R diagram (Figure 6) shows the

relationships between the tables.

Entity Relationship Diagram

Fig. 6

22

Database Tables

Fig. 7

The above table displays the inventory details. It stores the unique item ID, item type, item name,

OS version, room location and the date the item was stocked.

23

Fig. 8

The above table displays the employee information.

Fig. 9

The above table displays the building information.

24

Fig. 10

The above table displays the user account information.

25

Website Documentation

Website Purpose

The main purpose of this site is to allow Monroe College to use a website to graphically

display all of its Database information in an organized, user friendly manner. Employees can

search for specific records and can look up information from different buildings to search for a

particular inventory item. Along with the database, the website will store the QR codes generated

for quick and easy access for future use.

Domain: fast-inventory.com

Hosted By: Heroku

26

IPO Chart

Fig. 11

27

Navigating the Website

From the start when a user first opens the site they will be greeted with the Login Page

being prompted to login. Once the user has logged in they now have access to the Inventory Page

to have an overview of what data has been recorded and filter what they would like to see. Users

can also access to the Add Item page to add new items to the database.

Home Page

Fig. 12

The Home Page is used to serve as an update history page for any fixes or changes to the website

that will be updated by the website administrator. Alongside with any site updates the Home

Page will explain to those visiting the site the main purpose of the site.

28

Login Page

Fig. 13

The user is prompted to supply login information for access to the additional web pages,

the Inventory and Add Item pages. User information is authenticated with the database.

Script is being used to help handle the authentication for users. Passport.js is being used

to make a local login and to help provide a session for the user. The only time the user is logged

out is when the user leaves the site or if they click on the logout link. The username and

password is grabbed from the front end where there are textboxes with names as “username” and

“password”. The two variables are used to query it to the database to check if the user exists and

the password matches with the user. If the query comes out true, a callback is received with the

user’s information from the database.

29

Inventory Page

Fig. 14

The Inventory Page is used to store the data held in the database and allow for those

using the website to filter though the various records that have been recorded with the mobile

application.

This page takes the global variables made from the filter post and puts it in variables and

put those variables in a SQL query. Selecting from the inventory table and just getting all the

necessary data needed. All of the data received from the query is placed into the render data for

inventory. There is a form added to help with the filtering of the data, such as item types, the

building the item is in, and the room number.

30

Add Item

Fig. 15

The Add Item page allows user to input new items into the database.

31

Website Sample Code

var mysql = require("mysql");

var db = mysql.createPool({

host : 'us-cdbr-iron-east-04.cleardb.net',

user : '',

password : '',

database : 'heroku_e330f5bdc6c95f4'

});

module.exports = function(app, passport){

function sessionCheck(request, response, next){

if(request.user == "error"){

console.log("line 13");

} else {

next();

}

};

app.get("/", sessionCheck, function(request, respond){

respond.render("index.ejs",{

title: "Home",

user: request.user

});

});

app.get("/inventory", sessionCheck, function(request, respond){

db.query("select * from inventory", function(err, rows, fields){

if(err){

console.log(err);

}else{

respond.render("inventory.ejs",{

title: "Inventory",

inventory: rows

});

}

});

});

app.get("/login", function(request, respond){

32

respond.render("login.ejs",{

title: "Login"

});

});

app.get("/login/retry", function(request, respond){

respond.render("retry.ejs", {

title: "Retry Login"

});

});

app.get("/qrcodes", function(request, respond){

respond.render("qrcode.ejs", {

title: "QRCodes",

})

});

app.post('/login', passport.authenticate('local-login', {

successRedirect: "/inventory",

failureRedirect: "/login/retry"}),

function(request, respond){

});

app.post("/filter", function(request, respond, next){

var itemData = request.body.itemtype;

var buildData = request.body.buidling;

var roomData = request.body.room;

app.set('item', itemData);

app.set('build', buildData);

app.set('room', roomData);

respond.send({redirect: '/result'});

next();

});

app.get('/result', sessionCheck, function(request, respond){

var itemdata = app.get("item");

var builddata = app.get("build");

var roomdata = app.get("room");

33

db.query("select * from inventory where ItemType='"+itemdata+"' and

RoomNumber='"+roomdata+"'", function(err, rows, fields){

if(err){

console.log(err);

} else{

respond.render("filter.ejs", {

title: "Results",

inventory: rows

});

}

});

});

}

Node.js is being used for the back-end, some modules required to allow the server to do

functions such as GET or POST as well as routing and providing middleware like Body Parser.

This takes any data from the front end that is going to be posted to the back end and turn it into

JSON data. Authentication scripts and routing scripts were added to be with the main server file.

Script used for coding also deals with the routing. If a user were to go to another page,

instead of leaving the pages file name and file type at the end of the link, a route is given. As a

user goes between each route, a session check is being done to see if the user's session is still

active. If not, the user gets redirected to the login page. The “app.get” are the links that will show

any webpage along with any extra data that was added.

34

Mobile Application Documentation

The mobile app is a native hybrid app written in Ionic Framework and Cordova. It uses

native API calls like the camera and others. For the Fast Inventory Application, it is a way to

update the date it was scanned and the quantity of the item. It uses a QR Code scanner to the

scan the QR code attached to the item. Once the scan is made, the app gets the data from the QR

code which is just telling what the item type it is. Depending on the item type and room, it

updates the database with adding quantity, and the date it was scanned. The design was also

based to be for the college so naturally using the Monroe colors.

35

IPO Chart

Fig. 16

36

Mobile App Navigation

Login page

Fig. 17

The login page connects to the database to check if the user exists and the password matches the

same in the database.

37

Home page

Fig. 18

This page has a description of what is going on as well as the buttons to logout and to start

scanning.

38

Fig. 19 Fig. 20

Figure19 and 20 show the viewfinder of where the QR code should be placed to scan and the

report generated.

39

Mobile Application Sample Code

angular.module('starter', ['ionic', 'ngCordova'])

.run(function($ionicPlatform) {

$ionicPlatform.ready(function() {

if(window.cordova && window.cordova.plugins.Keyboard) {

cordova.plugins.Keyboard.hideKeyboardAccessoryBar(true);

cordova.plugins.Keyboard.disableScroll(true);

}

if(window.StatusBar) {

StatusBar.styleDefault();

}

});

})

.config(function($stateProvider, $urlRouterProvider){

$urlRouterProvider.otherwise("/layout/login");

$stateProvider

.state("layout", {

url: "/layout",

abstract: true,

templateUrl: "templates/layout.html"

})

.state("layout.login", {

url: "/login",

views:{

"main-content":{

templateUrl:"templates/login.html",

controller: "mainCtrl"

}

}

})

.state("layout.home", {

url: "/home",

views:{

"main-content":{

templateUrl:"templates/home.html",

controller: "mainCtrl"

}

}

})

.state("layout.result", {

url: "/result",

40

views:{

"main-content":{

templateUrl:"templates/result.html",

controller: "mainCtrl"

}

}

});

})

.controller("mainCtrl", function($scope, $http, $state, $cordovaBarcodeScanner, $ionicLoading,

$ionicPopup, $ionicHistory, $ionicModal){

$scope.user = {

email: "",

password: ""

}

$scope.loginUser = function(){

$ionicLoading.show({

template: 'Loading...'

});

$http.post('http://fastinventory.herokuapp.com/api/ionlogin', $scope.user)

.success(function(data){

console.log(data);

if(data == "pass"){

$ionicLoading.hide();

$ionicHistory.nextViewOptions({

historyRoot: true

});

$state.go("layout.home");

}

if(data == "fail"){

$ionicLoading.hide();

var alertPopup = $ionicPopup.alert({

title: 'Error',

template: 'Wrong Username or Password'

});

}

})

.error(function(err){

console.log(err);

});

}

$scope.dataToSend = {

roomNumber: "",

quantity: "",

itemModel: ""

41

};

$ionicModal.fromTemplateUrl('templates/result.html', {

scope: $scope,

animation: 'slide-in-up'

}).then(function(modal) {

$scope.modal = modal;

});

$scope.scan = function(){

$cordovaBarcodeScanner

.scan()

.then(function(barcodeData) {

var count = 1;

$ionicLoading.show({

template: 'Sending to Database...'

});

console.log("Starting...");

$scope.dataToSend.quantity = count;

$scope.dataToSend.itemModel = barcodeData.text;

$http.post('http://fastinventory.herokuapp.com/api/ionpost', $scope.dataToSend)

.success(function(data){

console.log(data);

$scope.someData = data;

if(data){

$ionicLoading.hide();

$scope.modal.show();

}

})

.error(function(err){

$ionicLoading.hide();

console.log(err);

var alertPopup = $ionicPopup.alert({

title: 'Error',

template: 'Something Went Wrong'

});

});

}, function(error) {

alert("Messed Up");

});

}

$scope.logoutUser = function(){

$state.go("layout.login");

}

})

42

Finance Documentation

The IT Professionals have been contracted by Monroe College to develop an inventory

application to improve efficiency with information processing and easily generate inventory

counts reports. This project must be completed within a three month span. The total budget

allocated for this project is $48,000. The budget includes monies to cover the expenses the

employee salaries, website, and mobile application development, database development, network

implementation, risks (20%) and, IT Professionals profit set at 45% of the total cost. As shown in

Figure 21 the total hardware costs throughout the duration of the project is $4,951. There was

only a $12 software fee for yearly hosting. Employee salaries totaled $8,197.96, while an extra

$1,500 yearly maintenance service fee to the college was added. Refer to figure 21 for a more

detailed outline of each expense.

43

Project Budget

FUNDING Budget

Monroe College Funding

Department Budget $40,000.00

Company Reserves $8,000

Total Budget Figure $48,0000

Budget Total $48,000

EXPENSES Costs

Hardware

Wireless Router [1] $310.33

Modern [1] $589.00

Cabling [1000 ft] $100.00

Switch [1] $249.99

Server [1] $3,743.83

QR Printer [1] $390.00

1TB USB [1] $866.00

Subtotal $6,249.15

Software

Ionic[1] Free

FireBase [1] Free

Heroku ClearDB [1] Free

Host [1] Free

Domain(fastinventory.com) $12/year[1] $12

Subtotal $12

Employees

Website Developer $1,206.44

Project Manager $2,584.10

Finance Manager $1,720.16

Database Administrator/Senior

Programmer $3,060.51

Network Administrator $1,202.52

Subtotal $9,773.73

Total Budget

Hardware/Software Total $6,261.15

Employee’s Salaries Total $9,773.73

Maintenance $1,500.00

Training $1,000.00

Risks (20%) $3,706.98

Project Total $22,241.86

Project Total with Profit (45%) $32,250.70

Subtotal

Total EXPENSES

$32,250.70

NET (Budget Total - Expenses) $15,749.30 Fig. 21

44

Figure 22 displays the pay rates for each employee. These rates were determined by

referencing the Bureau of Labor Statistics. It also displays the Employee Wages which shows

how much each employee is paid hourly. The total hours worked by each employee is calculated

by each employee rate which gives the gross pay of each employee. The gross pay represents the

total payment earned by each employee (Figure 24).

Fig. 22

45

Fig. 23

Fig. 24

46

ROI & NPV

As represented in figure 25 the cost of the project is $25,073.86 as represented in year

one. In years 2-5 the $1,500 represents the maintenance cost that will be charged on a yearly

basis. The benefits was calculated by subtracting the projected cost to do inventory with the new

system from how much it would cost two person to manually count the devices. Figure 26 shows

that in two and a half years the college will be starting to save money by using this system.

Fig. 25

47

Fig. 26

$0.00

$10,000.00

$20,000.00

$30,000.00

$40,000.00

$50,000.00

$60,000.00

$70,000.00

$80,000.00

$90,000.00

1 2 3 4 5

RIO & NPV

Cummulative Cost Cummulative Benefits

48

Training and Service Level Agreement

Training

The objective of the Training Plan is to define the strategies, tasks, and methods that will

be used to meet the training requirements.

This document defines the Training Plan for Project Fast Inventory. Monroe College’s

employees who will be involved with the day to day use of the system will be trained on the use

of the new system. Training will occur over a one-week period with two sessions in the period

and will be supplemented with the user manual. Training will focus on:

 Website usage

 Mobile Application Usage

 Navigation and Content

49

Service Level Agreement

This service level agreement (SLA) between the IT Professionals, Office of Information

Technology (OIT), and Monroe College establishes a commitment for support services. This

document describes the services provided, financial impact, processes for reporting issues and

making requests, and responsibilities of the department and IT Professionals.

Services and Support

Supported services include:

 Mobile Application

 Website Development

 Databases

 Training

Agreement Period

This agreement is in effect from 6/30/16 to 6/29/17. Agreements should be reviewed each year,

or when either Monroe College or IT Professionals deems it necessary.

Cost

The total cost of services for the current fiscal year 2016/2017 is $1,500. See Financial

Documentation for details.

Service Details

The IT Professionals supports the system components as listed above (see Services and Support).

We are responsible for maintenance and support of all Monroe College network connectivity and

switches, virtual servers, physical servers, and on-campus cable related to Project Fast Inventory.

50

Monitoring and Support

During Business Hours

During normal business hours (8am-5pm, M-F), if the customer experiences an issue and has

taken steps to rule out root causes under their control, they should report the incident to IT

Professionals, indicating that appropriate measures have been taken to identify the issue. Issues

may be reported using the methods below.

For non-urgent issues (Response within 8 hours of reported issue):

 Create a ticket in support@professionals.com. Visit https://professionals.service-

now.com. Under Can We Help You? Click Create a New Incident. Under Urgency, select

the appropriate level (Low, Medium, High). In the Details box, describe the issue.

 Call the Service Desk at 555-012-7268; the Service Desk will create an incident in

support@professionals.com.

 Send email to support@professionals.com. The email will automatically create a ticket

containing the contents of the email. If you know which support group the ticket should

be assigned to, indicate this in the email.

For urgent issues (Response within 1 hour of reported issue):

Call the Service Desk at 555-012-7268. Advise the Service Desk to assign the ticket

Widespread Impact and High Urgency (automatically assigns the ticket a Priority of

Critical).

For urgent issues, customer should create an incident in support@professionals.com and

assign it a High Urgency and Widespread Impact (automatically assigns the ticket a

Priority of Critical).

After Hours

After hours is defined as 5pm-8am, Monday through Friday; all day Saturday and Sunday; and

all day on public holidays.

For non-urgent issues: Submit a support@professionals.com incident or send email to the

Service Desk as above.

51

For urgent issues: Call the OIT Service Desk at 555-012-7268, select the option for reporting

a critical issue/service interruption, and leave a voice mail message. This creates a ticket with

a Priority of Critical. The Service Operations Center (SOC) will listen to the message and

assign it to the appropriate support group. There will be a response within one hour.

For urgent issues: Submit a Critical Priority incident or call the SOC at 555-012-7268.

Response Time

OIT responds to incidents according to the Priority assigned to the ticket. Priority is

automatically assigned as a result of the issues assigned Urgency and Impact:

 Low or Moderate Priority: Assigned group responds within 8 hours (8a-5p, M-F)

 High or Critical Priority: Assigned group responds within 1 hour (24x7)

Service Enhancements

Service enhancements are requests for planned changes in service or functionality, and are

managed as requests as opposed incidents/issues. Enhancements typically apply to software

applications, but may apply to interfaces between systems. The customer is welcome to submit

requests for enhancements, with the understanding that these may warrant a separate project and

funding proposal. Customer should request changes or enhancements to the current environment

by contacting the IT Professionals contact for this SLA.

Responsibilities

Both the customer and IT Professionals are involved in the successful resolution of issues. By

following standard issue-reporting processes and providing timely and comprehensive

information, the customer can help ensure that we have the information required to resolve the

issue in a timely fashion.

Customer Responsibilities

The customer agrees to:

 Follow procedures for reporting issues and requesting support as described.

 Provide a timely response to IT Professionals when issues are being

investigated/resolved.

52

 Engage IT Professionals contact when/if a change in this agreement is desired.

IT Professionals Responsibilities

IT Professionals agrees to:

 Meet or exceed response times associated with the urgency/priority associated with

reported customer issues.

 Maintain operational support for the services covered under this SLA. Communicate to

customer any expected change in support processes.

 Coordinate scheduled and unscheduled maintenance (downtime) with the customer in

order to minimize interruptions to the business and services.

 Attend and participate in meetings with the customer regarding services and support as

requested.

 Coordinate to:

 Maintain enterprise-level operating system and application software licenses.

 Manage software updates (releases and patches) for enterprise OS and

applications and coordinate updates with the customer.

 Escalate customer issues to appropriate second- and third-level support (beyond

the Service Desk) when necessary.

 Perform preventive maintenance on system hardware.

 Perform scheduled backups and coordinate data recovery when needed.

 Monitor system utilization and performance; report and resolve issues.

53

Signatures

By signing below, the customer and IT Professionals agree to the terms of this agreement. To

submit the signed agreement, scan and email it to the OIT contact below.

Customer IT Professionals

Jerry Smith, CIO

Information Technology

jerry@monroecolleg.edu

555-789-6325

Breianna Blair, Project Manager

Information Technology

breianna@professionals.com

555-012-7268

Signature Signature

Date Date

54

Closing Contract

Approval of this Project Closeout indicates an understanding and formal agreement that

the project is ready to be closed. By signing this document, each individual agrees all

administrative, financial, and logistical aspects of the project should be concluded, executed, and

documented as described herein.

Approver Name Title Signature Date

Jerry Smith CIO

Lawerence McGrath Desktop Support Supervisor

Breianna Blair Project Manager

Section 1. General Information

Project Name

Project Fast Inventory

Project Start Date Project End Date

5/16/16 6/30/16

Project Sponsor(s)

Monroe College

Project Manager

Breianna Blair

Section 2. Final Deliverable/Deployment Checklist

Item Question Response

2.1 Do you agree that the product and/or service is ready to be deployed? Yes No

2.2 Do you agree the product and/or service has sufficiently met the stated

business goals and objectives?

Yes No

55

Item Question Response

2.3 Do you fully understand and agree to accept all operational

requirements, operational risks, maintenance costs, and other limitations

and/or constraints imposed as a result of ongoing operations of the

product and/or service?

Yes No

2.4 Do you agree the project should be closed? If no, please explain: Yes No

Rate your level of satisfaction with regards to the project outcomes

listed below

2.5 Project Quality Yes No

2.6 Product and/or Service Performance Yes No

2.7 Scope Yes No

2.8 Cost (Budget) Yes No

2.9 Schedule Yes No

56

Section 3. Project Documentation Checklist

Item Question Response

3.1 Have project documentation and other items been prepared, collected,

filed, and/or disposed?

Yes No

3.3 Were documents completed and results documented for future

reference?

Yes No

Section 4. Project Team

Name Role Type

Breianna Blair Project Manager Employee

Abdullah Hamid Network Engineer Employee

Jose Ortiz Mobile Application Developer &Database Administrator Employee

Mark Perez Website Developer Employee

Youseff Ballo Financial Analyst Employee

THE PARTIES, INTENDING TO BE LEGALLY BOUND, have executed this agreement on

the date first set in the contract/Service Level Agreement.

In honor of this agreement I hereby declare closure:

Signature: ________________________ Date: ______________________

(Monroe College, CIO)

57

Summary

In summary, Monroe College can now be able to solve the problem of inventory tracking.

Employees will no longer have to go through a tedious process in order to gain information about

inventory. The IT Professionals have delivered a working system and all specified deliverables.

Lessons learned include following the project plan timeline in order to deliver the project

in a timely manner. Constant communication among employees in the IT Professionals is also

vital for completing a well-integrated project. Testing and revisions of the mobile application and

website should be done in an incremental stage in order find and fix bugs as soon as they become

know.

The college will continue to receive training and system maintenance from the IT

Professionals. The project has officially come to a close as all deliverables have been handed

over to Monroe College.