Project Roles and Responsibilities
Senior Leadership
Design-Build Director
Principal Engineer
Responsible for the following:
· Overall leadership for Business/Construction/Design
· Personnel issues and recruitment
· Coordination among teams
· Mentoring and coaching of team members
· Liaison with Design-Build leadership
· External Communications
· Communication with WSDOT executive-level management
· Dispute resolution and communication within project leadership team
· Forecasting issues before they become issues
Business Group
Business Manager
Responsible for the following:
· Project Management Plan
· Budget reporting and payments
· Schedule analysis and reporting
· Project status reporting
· Risk identification and analysis
· Primary contact with D-B for compliance and payments
· Process and negotiate change orders
· Ensure compliance with State and federal laws and regulations
· Change management
· Project documentation
· Project closeout
Design Oversight
Design Project Engineer
Responsible for the following:
· Design oversight through participation on task force teams
· Design-side quality audits
· Liaison with construction and business groups
· Coordinate environmental support through NEPA and until permits granted
· Coordination with WSDOT support groups, including Bridge & Structures
· Management of design and environmental consultant task orders
Construction Oversight
Construction Project Engineer
Responsible for the following:
· Verification, manage construction quality group
· Providing WSDOT constructabilit y perspective during design phase
· Ensure Design-Builder meets specif ications and work activities are compliant with safety requirements
· Align with Design-Builder whether it’s at task force level or point of contact
· Verify schedule progress in s upport of contractor payments
· Field solutions to problems