Project Proposal: Execution, Control, and Closure
Sheet1
| Deliverable | Start | End | Duration | 44166.00 | 44443.00 | ||||
| Kick-off meeting | 1-Dec-20 | 5-Dec-20 | 4 | ||||||
| Architecture audit | 5-Dec-20 | 7-Dec-20 | 2 | ||||||
| Features, functionality, and strategy development | 5-Dec-20 | 1-Jan-21 | 27 | ||||||
| Strategy presentation | 8-Dec-20 | 9-Dec-20 | 1 | ||||||
| Gather data | 5-Dec-20 | 10-Dec-20 | 5 | ||||||
| Analayze data | 10-Dec-20 | 15-Dec-20 | 5 | ||||||
| Develop business requirement report | 5-Dec-20 | 10-Dec-20 | 5 | ||||||
| Develop Technical requirement Report | 1-Dec-20 | 7-Dec-20 | 6 | ||||||
| Develop Site Map | 1-Dec-20 | 15-Dec-20 | 14 | ||||||
| Develop Storyoard | 1-Dec-20 | 15-Dec-20 | 14 | ||||||
| Develop Nevigation Map | 1-Dec-20 | 15-Dec-20 | 14 | ||||||
| Deveop and submit design | 13-Dec-20 | 15-Dec-20 | 2 | ||||||
| Choose Handicrafts | 15-Dec-20 | 1-Jan-21 | 17 | ||||||
| Fill inventory with handicrafts | 15-Jan-21 | 13-Feb-21 | 29 | ||||||
| Set up physical store | 20-Jan-21 | 23-Feb-21 | 34 | ||||||
| Inauguration of physical store | 1-Feb-21 | 28-Feb-21 | 27 | ||||||
| Present progress report to sponsors | 20-Feb-21 | 28-Feb-21 | 8 | ||||||
| Hiring team of web developers | 2-Mar-21 | 11-Mar-21 | 9 | ||||||
| Giving requirements to developers | 1-Mar-21 | 20-Mar-21 | 19 | ||||||
| Beginning of website development | 1-Mar-21 | 30-Mar-21 | 29 | ||||||
| Monthly progress report | 26-Mar-21 | 30-Mar-21 | 4 | ||||||
| Feedback to developers | 1-Apr-21 | 5-Apr-21 | 4 | ||||||
| Completion of website | 5-Apr-21 | 30-Apr-21 | 25 | ||||||
| Testing of website | 1-May-21 | 10-May-21 | 9 | ||||||
| Final changes in website | 10-May-21 | 20-May-21 | 10 | ||||||
| Launch of website | 3-May-21 | 1-Jun-21 | 29 | ||||||
| Progress report | 15-May-21 | 1-Jun-21 | 17 | ||||||
| Search engine optimization of website | 1-Jul-21 | 10-Aug-21 | 40 | ||||||
| Marketing on social media | 12-Aug-21 | 4-Sep-21 | 23 | ||||||
| Completion of Project | 1-Sep-21 | 4-Sep-21 | 3 |
Project Schedule
Kick-off meeting Architecture audit Features, functionality, and strategy development Strategy presentation Gather data Analayze data Develop business requirement report Develop Technical requirement Report Develop Site Map Develop Storyoard Develop Nevigation Map Deveop and submit design Choose Handicrafts Fill inventory with handicrafts Set up physical store Inauguration of physical store Present progress report to sponsors Hiring team of web developers Giving requirements to developers Beginning of website development Monthly progress report Feedback to developers Completion of website Testing of website Final changes in website Launch of website Progress report Search engine optimization of website Marketing on social media Completion of Project 44166 44 170 44170 44173 44170 44175 44170 44166 44166 44166 44166 44178 44180 44211 44216 44228 44247 44257 44256 44256 44281 44287 44291 44317 44326 44319 44331 44378 44420 44440 Duration Kick-off meeting Architecture audit Features, functionality, and strategy development Strategy presentation Gathe r data Analayze data Develop business requirement report Develop Technical requirement Report Develop Site Map Develop Storyoard Develop Nevigation Map Deveop and submit design Choose Handicrafts Fill inventory with handicrafts Set up physical store Inauguration of physical store Present progress report to sponsors Hiring team of web developers Giving requirements to developers Beginning of website development Monthly progress report Feedback to developers Completion of website Testing of website Final changes in website Launch of website Progress report Search engine optimization of website Marketing on social media Completion of Project 4 2 27 1 5 5 5 6 14 14 14 2 17 29 34 27 8 9 19 29 4 4 25 9 10 29 17 40 23 3