Project Completion Report
|
Project title and objectives:
Effective interview skills
Develop a set of strategies and actions by 18/11/16 that can assist interns gain full time employment with company though effective interview skills
|
|
Project results overview:
Achieved outcomes as required (accurate, relevant, sufficient strategies and actions) but within the designated time frame but this created intensive work to achieve completion.
|
|
Project Outcomes
|
|
Deliverable
|
Budget cost
|
Final cost
|
Scheduled date from project plan
|
Final date
|
|
3 strategies on how to be competitive in an interview
|
xx
|
xxx
|
xxx
|
xx
|
|
Each strategy to have specific actions on behaviours
|
xx
|
xxx
|
xx
|
xxx
|
|
xxx
|
xx
|
xx
|
xx
|
xx
|
|
|
|
|
|
|
|
Totals
|
xx
|
xx
|
xx
|
xx
|
|
Issues and Risks Summary
|
|
Issues/Risks
(arose during the lifecycle of the project)
|
Action Taken
(how the issue/risk was resolved)
|
|
delays
|
xxxx
|
|
stress
|
Used mentor and discussed issues at planned meetings with all key stakeholders
|
|
xxx
|
xxx
|
|
|
|
|
|
|
|
Sign off by key stakeholders:
|
Project Completion Report Version 1.0 | 10 October 2016 Page 1 of 1