Week 3

jrob08
PMG640Unit3Assignment_MSProject2.pdf

Due Date: Sunday by 11:59pm Total Points: 100 Instructions:

• Update your project file based on any feedback given last week. If assignment is not correctly updated, then points will be deducted.

• Add Project Management Processes to your WBS if you have not already done so. This will need to include the PM processes that would be consistent with the planning, executing, controlling, and closing activities.

o You will need to create appropriate deliverables (adjective / noun format) o You will need to create appropriate activities (action verb / adjective / noun

format) o Sequence the activities o You will need to estimate times (be sure to differentiate between duration & effort

/ work)

• Sequence all your activities using the predecessors’ column, creating a closed network diagram (please see multimedia video showing you how to ensure you have a closed network diagram). At least 4 of your tasks relationships must be different than Finish to Start (insert a note on these tasks to explain the task relationship that you chose); remember, you should create a closed network diagram

• Add lead time to at least 2 task relationships with explanatory note

• Add lag time to at least 1 task relationship with explanatory note

• Add a constraint to at least 2 tasks and provide a note explaining why the task is constrained (make certain that the constraint does not create a conflict in the project schedule)

• View your critical path

• Create a note in Line 1 of your MS Project file where you tell me what tasks are on the critical path. It must be in this location. Be sure you tell me the correct critical path, which may or may not be the tasks highlighted in MS Project.

• Display your project in Network Diagram view and save it so that it opens automatically in this view

Requirements:

• Use MS Project to complete your assignment.

• Save your files using the following filename convention:

o MSProject2 – FirstName_LastName

Be sure to read the criteria, by which your paper/project will be evaluated, before you write, and again after you write.

PMG640 – Project Scheduling and Cost Planning

Unit 3 Assignment: MS Project #2

Evaluation Rubric for Unit 3: MS Project #2 Assignment

CRITERIA Deficient

Needs

Improvement Proficient

Exemplary

0 – 15 Points 16 – 19 Points 20 – 24 Points 25 Points

Work Breakdown Structure

Work Packages are not fully decomposed but less than the 30 Activities necessary to create the deliverables. Some of the correct naming conventions are missing.

Work Packages are

fully decomposed but

less than the 40

Activities necessary to

create the

deliverables. Some of

the correct naming

conventions are

missing.

Work Packages are

fully decomposed into

the 40 Activities

necessary to create

the deliverables.

Some of the correct

naming conventions

are missing

Work Packages are fully decomposed into the 40 Activities necessary to create the deliverables. Correct naming conventions are used.

Sequence Activities

All activities are Sequenced using the predecessors’ column without a closed network diagram. At least 1-2 of your tasks relationships must be different than Finish to Start.

All activities are Sequenced using the predecessors’ column without a closed network diagram. At least 3 of your tasks relationships must be different than Finish to Start.

All activities are Sequenced using the predecessors’ column with a closed network diagram. At least 3 of your tasks relationships must be different than Finish to Start

All activities are Sequenced using the predecessors’ column with a closed network diagram. At least 4 of your tasks relationships must be different than Finish to Start

Lead & Lag Includes a lead time to at least 1 task relationships with no clear explanatory note and a lag time to at least 1 task relationship with no explanatory note

Includes a lead time to at least 1 task relationships with no clear explanatory note and a lag time to at least 1 task relationship with explanatory note

Includes a lead time to at least 2 task relationships with no clear explanatory note and a lag time to at least 1 task relationship with explanatory note

Includes a lead time to at least 2 task relationships with explanatory note and a lag time to at least 1 task relationship with explanatory note

0 – 15 Points 16 – 17 Points 18 – 19 Points 20 Points

Critical Path Critical Path is not identified and some of the activities on the critical path are clear but not highlighted.

Critical Path is identified and some of the activities on the critical path are clear but not highlighted.

Critical Path is identified and all activities on the critical path are clear but not highlighted.

Critical Path is identified and all activities on the critical path are clear and highlighted.

0 Points 1 – 2 Points 3 – 4 Points 5 Points

Clear and Professional Writing

Writing assignment contains no sense of organization. Paragraphs lack clear ideas. Contains several errors in grammar, spelling and punctuation which detracts from content of the passage.

Writing assignment contains a sense of organization. Some paragraphs have clear ideas. Contains several minor errors in grammar, spelling and punctuation, but does not detract from content of the passage.

Writing assignment contains good overall organization. Most paragraphs have clear ideas and are supported with some examples. Mostly free of errors in grammar, spelling and punctuation.

Writing assignment is well-planned and well-thought out. All paragraphs have clear ideas, are supported with examples and have smooth transitions. Free of errors in grammar, spelling and punctuation.

Copyright Statement Post University’s courses contain copyrighted resources created by the University, licensed from various third

parties, or unless otherwise noted. In compliance with U.S. Copyright Law, these resources may not be

reproduced, revised, or distributed without the written permission of Post University. Students found to be in

violation of this policy are subject to civil and criminal liabilities associated with the Federal Copyright Act and

risk dismissal from the university under the Academic Dishonesty policy. Unless otherwise noted, access to

these materials is limited to the duration of the course. Students should contact the library (library@post.edu)

for information on which resources can be printed.