Risk : Health Concerns

Status: Low

Description: Food Contamination ,Food Allergy

Probability: 30%

Impact: $5000

Total Risk=P(0.3)*$5000= $1500

Mitigation: Wash hands after handling different things and I should put some alerts in the menu.

Comments: Sensitization efforts in place.

Risk : Supply delay

Status: High

Description: Loses

Probability: 50%

Impact: $2000

Total Risk=P(0.5)*$2000= $1000

Mitigation: Confirm delivery dates earlier.

Comments: Having many suppliers is necessary.

Risk : Installation problems and mistakes.

Status: High

Description: They may install something wrong in the restaurant and that considered a damage.

Probability: 60%

Impact: $4000

Total Risk=P(0.6)*$4000= $2400

Mitigation: Highly trained and skilled personal for installation.

Comments: Perfection required.

Risk : Operating kitchen temperatures.

Status: Low

Description: Food Contamination

Probability: 15%

Impact: $1500

Total Risk=P(0.15)*$1500= $225

Mitigation: Abiding by the set operational guidelines.

Comments: This can be achieved easily.

Risk :Restaurant Bankruptcy

Status: High

Description: the restaurant may lose the funds.

Probability: 10%

Impact: 100000

Total Risk=P(0.1)*$100000= $10000

Mitigation: Cost Saving ideas.

Comments: Saving on unnecessary expenditure would be helpful.

Risk : Damaged items needing replacement.

Status: Low

Description: electricity shortage

Probability: 20%

Impact:$8000

Total Risk=P(0.2)*$8000= $1600

Mitigation: Immediate procurement once the items get damaged and I should have a backup power.

Comments: The project manager must be alert.

Probability Vs. Impact

Health Concerns

Supply delay

Installation problems and mistakes

Operating kitchen temperatures

Restaurant Bankruptcy

Damaged items needing replacement

30 50 60 15 10 20 5000 2000 4000 1500 100000 8000

Probability

Impact