Arabic Food Restaurant PM: Project Summary Schedule As of
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Conceptual Phase | Comp. | ||||||||||
| Feasibility & Preliminary Planning | Comp. | Too much bureaucracy in license acquisition. | |||||||||
| Detail Planning | Comp. | Earlier delays at feasibility affected the project | |||||||||
| Implementation | Blue | project partly running ahead of schedule and implementation time not yet reached | |||||||||
| Conversion / Sustaining / Termination | Green | Time for conversion, sustaining and termination not yet arrived at. |
Arabic Food Restaurant PM: Project Conceptual Phase Sch. As of:
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Conceptual Phase | |||||||||||
| Customer requirements | Comp. | ||||||||||
| Site proposal | |||||||||||
| Vendor acquisition | Green | ||||||||||
| Design plan | Green | ||||||||||
| Conceptual Phase Review | Comp. | Project running smoothly with no interference. | |||||||||
Time Now
Arabic Food Restaurant PM: Project Fea. & Prel. Plng. Phase Sch. As of:
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Feasibility & Preliminary Planning | |||||||||||
| Location Acquisition | Comp. | ||||||||||
| Permits & License | Comp. | ||||||||||
| Kitchen Equipment | Comp. | ||||||||||
| Seat Count | Comp. | ||||||||||
| Fea., Prel. Plng. Rev. | Comp. | Schedule slip was as a result of unavoidable circumstances. Too much bureaucracy involved. Time to be compensated later. | |||||||||
3
Arabic Food restaurant PM: Project Detail Planning Phase Sch. As of:
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Detail Planning | |||||||||||
| Layout option for staff | Comp. | ||||||||||
| Designing | Green | ||||||||||
| Furniture, equipment selection | Green | ||||||||||
| Detail planning. | Comp. | The delays at the feasibility stage caused the slip in this stage. There was no enough time for early recovery |
Arabic Food Restaurant PM: Project Implementation Phase Sch. As of:
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Implementation | |||||||||||
| Constructing essentials | Green | ||||||||||
| equipment installation | Green | ||||||||||
| operational elements | |||||||||||
| Advertising | Comp. | ||||||||||
| Initial testing | Blue |
Green
5
Arabic Food Restaurant PM: Project Conv./Sust./Term. Phase Sch. As of:
| TASK | STATUS | M1 | M2 | M3 | M4 | M5 | M6 | M7 | M8 | M9 | COMMENTS |
| Conversion / Sustaining / Termination | |||||||||||
| Personnel acquisition | Incomp. | ||||||||||
| training materials | Green | ||||||||||
| employee training | |||||||||||
| work schedule | |||||||||||
| Conv/Sus/Term. Rev. | Green | the necessary deliverables not yet agreed upon. To be started later. | |||||||||
| Project Closure | Green | <once the project is complete, closure will be initiated. |