Project Management - Earned Value Management

Superhero
Planned-Project.pdf

PLANNED VALUE (PV) Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Totals

Work Package A $25 $12 $8 $45 Work Package B $12 $15 $16 $20 $15 $10 $88 Work Package C $15 $12 $13 $8 $48 Work Package D $12 $12 $25 $49

Total for Week, or Planned Value (PV) $25 $24 $23 $16 $35 $27 $23 $20 $12 $25 $230 = BAC

CUMULATIVE % of PLANNED WORK COMPLETE Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10

Work Package A Hours Worked 245 535 300 Work Package B Hours Worked 50 65 225 475 200 225 Work Package C Hours Worked 150 160 600 110 Work Package D Hours Worked 110 120 480

Total Hours Worked for Week 245 585 365 225 625 360 825 220 120 480 Cumulative Total Hours Worked for Week 245 830 1195 1420 2045 2405 3230 3450 3570 4050

Cumulative Percent of Planned Work Completed 6% 20.5% 29.5% 35% 50% 59% 79.8% 85% 88% 100%