1 PJM Template Repository 98 days Wed 7/1/20 Fri 11/13/20 0 days

2 Initation/ Plan 43 days Wed 7/1/20 Fri 8/28/20 0 days

3 Create project charter 5 days Wed 7/1/20 Tue 7/7/20 0 days

4 Approve project charter 5 days Wed 7/8/20 Tue 7/14/20 3 0 days

5 Create requirements document 10 days Wed 7/15/20Tue 7/28/20 4 0 days

6 Approve requirements document 5 days Wed 7/29/20Tue 8/4/20 5 0 days

7 Create project management plan 10 days Wed 8/5/20 Tue 8/18/20 6 0 days

8 Review/revise project management plan 5 days Wed 8/19/20Tue 8/25/20 7 0 days

9 Approve project management plan 3 days Wed 8/26/20Fri 8/28/20 8 0 days

10 Project Execution 53 days Mon 8/31/20Wed 11/11/20 1 day

11 Manage issues, risks, changes 53 days Mon 8/31/20Wed 11/11/20 9 1 day

12 Communicate project status 53 days Mon 8/31/20Wed 11/11/20 9 1 day

13 Design and Development 42 days Mon 8/31/20Tue 10/27/20 0 days

14 Technology procurement 18 days Mon 8/31/20Wed 9/23/20 0 days

15 Research available technologies/vendors 10 days Mon 8/31/20Fri 9/11/20 9 0 days

16 Negotiate Contract 5 days Mon 9/14/20Fri 9/18/20 15 0 days

17 Sign Contract/Obtain license 3 days Mon 9/21/20Wed 9/23/20 16 0 days

18 SIte Wireframe 10 days Thu 9/24/20 Wed 10/7/20 0 days

19 Create site requirements 5 days Thu 9/24/20 Wed 9/30/20 17 0 days

20 Create site Wireframe 2 days Thu 10/1/20 Fri 10/2/20 19 0 days

21 Revew/ revise site wireframe 3 days Mon 10/5/20Wed 10/7/20 20 0 days

22 Developed website application 4 days Thu 10/8/20 Tue 10/13/20 0 days

23 Create Repository Site 3 days Thu 10/8/20 Mon 10/12/20 21 0 days

24 Review/revise/approve respository site 1 day Tue 10/13/20Tue 10/13/20 23 0 days

25 Templates collection 40 days Mon 8/31/20Fri 10/23/20 9 days

26 Request templates 15 days Mon 8/31/20Fri 9/18/20 9 9 days

27 Review/ revise templates 20 days Mon 9/21/20Fri 10/16/20 26 9 days

28 Upload approved Templates 5 days Mon 10/19/20Fri 10/23/20 27 , 24 9 days

29 Project Product Evaluation 2 days Mon 10/26/20Tue 10/27/20 9 days

30 Repository Testing 2 days Mon 10/26/20Tue 10/27/20 9 days

31 Test Repository Site 1 day Mon 10/26/20Mon 10/26/20 28 9 days

Page 1

ID Task

Mode

Task Name Duration Start Finish Predecessors Total Slack

32 Revise/ approve Repository Site 1 day Tue 10/27/20Tue 10/27/20 31 9 days

33 Final Version Release 53 days Mon 8/31/20Wed 11/11/20 2 days

34 Create Alumni Communication Plan 3 days Mon 8/31/20Wed 9/2/20 9 44 days

35 Create Student Communication Plan 3 days Mon 8/31/20Wed 9/2/20 9 45 days

36 Communicate to alumni 5 days Thu 9/3/20 Wed 9/9/20 34 44 days

37 Communicate to students 5 days Thu 9/3/20 Wed 9/9/20 35 45 days

38 Provide access to alumni 3 days Mon 11/9/20Wed 11/11/20 40 , 36 2 days

39 Provide access to students 2 days Mon 11/9/20Tue 11/10/20 40 , 37 3 days

40 Release Final Version of the Website 1 day Fri 11/6/20 Fri 11/6/20 32 , 41 , 47 2 days

41 Create operational/ support plan 5 days Wed 10/14/20Tue 10/20/20 24 14 days

42 Lessons learned 5 days Fri 11/6/20 Thu 11/12/20 0 days

43 Collect Lessons Learned 3 days Fri 11/6/20 Tue 11/10/20 47 0 days

44 Review Lessons Learned 2 days Wed 11/11/20Thu 11/12/20 43 0 days

45 Co-op/Intern onboard process plan 23 days Wed 10/14/20Fri 11/13/20 0 days

46 Create Co-op/Intern onboard process plan 7 days Wed 10/14/20Thu 10/22/20 24 0 days

47 Execute Co-op/Intern onboard process plan 10 days Fri 10/23/20 Thu 11/5/20 46 0 days

48 Project End 1 day Fri 11/13/20 Fri 11/13/20 44 , 40 , 11 , 12 0 days

Page 2

Resource Initials

Project Team

Sponsor

Project Team

Sponsor

Project Team

Project Team

Sponsor

Project Team

Project Team

Procurement

Procurement

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Page 3

Resource Initials

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Project Team

Page 4