Earned Value Management (EVM)

Mkrenisky84
NetworkSchedule3.docx

Develop a network schedule for your project using either the arrow diagramming method or the precedence method. Also, your project schedule should illustrate float/slack for each activity.

Table 1.1. Project Tasks details

Activity

Predecessor

Duration

Early start date

A (Retirement and social security benefits)

None

One year

1/1/2019

B (Audit & risk evaluation)

A

11 months

2/1/2019

C (Equipment Maintenance)

B

8 months

2/1/2019

D (Training & Development)

A, B

One year

1/2/2019

E (Logistics, appraisals & rewards)

D, C

One year

1/2/2019

Precedence Diagramming Method:

ES

Duration

EF

Activity Legend

LS

Float/slack

LF

LS= Late start Dependency

LF= Late Finish

ES= Early start

EF= Early finish

F= Float/Slack

08/09/2019

1 year 7 months

03/04/2021

Activity B Audit & Risk Evaluation

12/19/2020

3 months

03/04/2021

07/25/2019

11 months

06/22/2020

Activity C Equipment & Maintenance

08/1/2019

6 months

02/22/2020

12/27/2019

8 months

08/05//2020

Activity A Retirement & social security

03/05/2020

5 days

03/10/2020

07/31/2019

2 months

09/23/2019

Activity E Logistics, Appraisals & Rewards

08/10/2019

15 days

08/25/2019

03/22/2019

1 month

04/09/2019

Activity D Training & Development

03/22/19

11 days

04/02/2019

5 Activities with 6 dependencies