Fun with MS Project Make up (Winter 2022) Duration: 2 hours

Important notice:

By submitting your answer files, you are agreeing that you have completed this test on your own and you did not receive or give aid to other students in this course.

You may print out the test paper, but the distribution of the test material to others is strictly prohibited.

Set up of the project Availability for project work: Regular working hours, except Friday (only morning) Vacation: Nov 4, 2022 (no work) Project start date: Oct 17, 2022 Auto Schedule Save your work right away! Name your file as Your last name_your first name_test.

1. Open a blank Project and set up as indicated above and add the following tasks.

Identify existing skills 10 days Identify needed skills 10 days Develop training documentation 1 wk Develop contract 2 wks Hire trainers 3 days Secure lab space 5 days Sign lab contract 0 days Conduct Training 2 wks 2. Add the Task Conduct Interviews below Develop Contract and give it a duration of 3

days.

3. Change the duration of the Task Develop training documentation from 1 week to 10 days.

4. Add a Milestone called Documentation complete below the task Develop training

documentation. 5. Add the task Write training scripts below Identify needed skills and give it a duration

of 10 days. 6. Change Hire trainers from a Task to a Milestone.

7. Create a Work Breakdown Structure (WBS) with the following Summary Tasks:

• Documentation (includes all Tasks down to and including the first Milestone)

• Trainers (includes all Tasks below the first Milestone and including the second Milestone)

• Lab (all remaining Tasks)

8. Add Finish-to-Start Dependencies (FS) between all tasks (not summary task) in order, except Identify existing skills and Identify needed skills which should start at the same time.

9. Add the summary tasks to the time line. 10. Add WBS codes using Uppercase Letters (Lowercase letters for second level) and

make them visible in a column to the left of your Task Names. 11. Add the following work resources to the project:

a. William Conner with Maximum Units 100%, a Standard Rate of $100.00/hour and an Overtime Rate of $120.00/hour Prorated

b. Lu Chin with Maximum Units 100%, a Standard Rate of $75.00/hour and an Overtime Rate of $100.00/hour Prorated

c. Pamela Lopez with Maximum Units 100%, a Standard Rate of $75.00/hour and an Overtime Rate of $100.00/hour Prorated

12. Add the following material resource to the project: Manuals (material) costing $30.00 each

13. Give Pamela Lopez a week of holiday from Monday, November 21, 2022 through

Friday, November 25, 2022.

14. Assign William Conner to tasks 2, 3, 4, 5, 8 and 9. 15. Now you have an over allocation situation. Pam will now be responsible for task 3

(Identify needed skills). 16. Task 12 (Secure Lab Space) will be done by William and Lu. By assigning 2 people,

you are hoping to get this done in half the time. Assign William first. Then assign Lu. 17. Task 14 will be done by Pam. 18. For Task 14 (Conduct Training) change the duration to 12 elapsed days. 19. You now have an over allocation situation. Explain why you have this using the note

for task 14.

20. Assign 100 manuals to Task 14 (Conduct Training). 21. Assign a fixed cost of $500 for a room rental to Task 14 (Conduct Training). 22. Add a Project Summary Task bar. You can name it any. 23. You notice that the project would not finish in year 2022. In order to shorten the

completion date, you (salaried employee-therefore no cost) decide to help out. You will do this by helping out William only for those tasks that he is working alone. Make sure to change the tasks to be effort driven.

24. Add a 2 hour weekly meeting first thing in the morning on every Wednesday

throughout the entire project. Add it at the end and name “Weekly Meeting”. 25. How much is this project costing us? Write down the cost using “notes” on task 13. 26. When will the project be completed. Write it on a blank line. 27. Write your name in the header. Centre justify. Submit your work by email