PROCESS SCHEDULING: PERT-CPM

vlaudy11a
Module4.docx

Module 4 - Case

PROCESS SCHEDULING: PERT-CPM

Case Assignment

Part I

Calculate the expected time (hours, days, weeks, or whatever) for the following tasks. Report the time to the next highest whole number.

Task

Optimistic (shortest) Time

Most Likely Time

Pessimistic (longest) Time

Expected Time (answer)

A

3

5

7

B

10

15

20

C

4

5

6

D

27

45

90

E

8

9

12

F

81

93

98

Part II

Each of these CPM diagrams corresponds to one of the task lists given below. Match them. Ex. A:#, B:#, etc.

Symbols:

START 

END

A.

B.

C.

D.

E.

Part III

Part IV

Estimated and crash costs for each task are shown in the table below.

Answer the questions below the table.

Version 1

Original Estimates

Crash Estimates

Crash Differentials

Task

 

(T)

CP

 

*

Est. Time,

weeks

(ET)

Est. cost,

$1000,

(EC)

Crash

Time,

weeks

(CT)

Crash

Cost,

$1000

(CC)

Time

saved

 

(ET-CT)

Extra

cost

 

(CC-EC)

A

*

5

10

4

12

B

*

7

15

5

17

C

5

8

3

12

D

*

6

6

5

8

E

*

9

12

8

15

F

4

16

2

20

G

*

5

20

2

21

(End)

-

CP=Critical Path. If task is on CP, then *; otherwise blank.

1 Fill in the blank cells under Crash Differentials.

2 Instead of the scheduled 7 weeks, Task B took 9 weeks. Which task or tasks should be crashed to make up the lost time, at minimum cost? Explain.

Assignment Expectations

1 There are no page limits. Write what you need to write, neither more nor less. Make each sentence count! (Having said that; it’s unlikely that one page would be enough, and very likely that eight pages would be too much.)

2 Ensure that your answer reflects your detailed understanding of the theory and techniques taught in this module.

References and citations are required. This requirement can be satisfied by citing the module Home page.