OM 311

Aisha123
MGT311Assignment3.docx

https://www.seu.edu.sa/sites/ar/SitePages/images/logo.png
007A

College of Administrative and Financial Sciences

Assignment 3

Deadline: 04/17/2021 @ 23:59

Academic Year: 2020-21

Course Name: Introduction to Operations Management

Student’s Name:

Course Code: MGT311

Student’s ID Number:

Semester: II

CRN:

For Instructor’s Use only

Instructor’s Name:

Students’ Grade: Marks Obtained/Out of

Level of Marks: High/Middle/Low

Instructions – PLEASE READ THEM CAREFULLY

· The Assignment must be submitted on Blackboard (WORD format only) via allocated folder.

· Assignments submitted through email will not be accepted.

· Students are advised to make their work clear and well presented, marks may be reduced for poor presentation. This includes filling your information on the cover page.

· Students must mention question number clearly in their answer.

· Late submission will NOT be accepted.

· Avoid plagiarism, the work should be in your own words, copying from students or other resources without proper referencing will result in ZERO marks. No exceptions.

· All answered must be typed using Times New Roman (size 12, double-spaced) font. No pictures containing text will be accepted and will be considered plagiarism).

· Submissions without this cover page will NOT be accepted.

Learning Outcome:

Demonstrate process-flow analysis, process design solutions, operations strategies, Inventory Control System and customer services in the business operation.

Assignment Question(s): (Marks 5)

A public accounting firm requires the following activities for an audit:

Activity

Immediate Predecessor

Activity time

A

-

3

B

A

2

C

-

5

D

B, C

2

E

A

4

F

B, C

6

G

E, D

5

a) Draw a network for this project? (Marks 2.0)

b) Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 2.0)

c) What are the critical path? (Marks 1.0)

a-

b-

step 1

find early start, and early finish from the start of the project for each activity

Activity

Duration, D

Early start, ES=Max of early finish of preceding activities

Early finish, EF = ES + D

A

3

0

3

B

2

3

5

C

5

0

5

D

2

5

7

E

4

3

7

F

6

5

11

G

5

7

12

step 2

Find Maximum EF and keep it as the LF of last activities

step 3

calculate LS for each activity after calculating its EF's.

Activity

Duration, D

Early start, ES=Max of early finish of preceding activities

Early finish, EF = ES + D

Late finish, LF= Min of LS of successor activities

Late start, LS= LF - D

Total slack= LF-EF

A

3

0

3

3

0

0

B

2

3

5

5

3

0

C

5

0

5

5

0

0

D

2

5

7

7

5

0

E

4

3

7

7

3

0

F

6

5

11

12

6

1

G

5

7

12

12

7

0

c-

Critical path with 0 slack are AEG, ABDG and CDG