Microsoft Project Assignment
Microsoft Project Assignment
1. Open Lab2.mpp file and update it with the following tasks information.
|
Task Name |
Duration |
WBS |
|
Preparation |
|
A |
|
Determine The Location of The Party and Make Reservation |
2d |
A-01 |
|
Guest Invitation |
2d |
A-02 |
|
Hiring Performers |
3d |
A-03 |
|
Collect Guest Confirmation |
2d |
A-04 |
|
Purchase Ornament |
3d |
A-05 |
|
Order Food |
2d |
A-06 |
|
Purchase Tableware and Prizes |
1d |
A-07 |
|
Preparation Complete |
0d |
A-08 |
|
Event |
|
B |
|
Decoration |
3hrs |
B-01 |
|
Welcome Guests |
1hr |
B-02 |
|
Greeting Speech |
15mins |
B-03 |
|
Party |
3hrs |
B-04 |
|
Live Band Show |
1hr |
B-05 |
|
Games and Raffles |
1hr |
B-06 |
|
Party Complete |
0d |
B-07 |
|
After Event |
|
C |
|
See Guests Out |
1hr |
C-01 |
|
Cleaning |
2hrs |
C-02 |
|
Write Thank-you Notes to Guests |
1d |
C-03 |
2. ( A-06 )Enter the following FS dependencies, referring tasks by its WBS code
( Lag: 2 d ) ( A-04 ) ( C-03 ) ( C-02 ) ( C-01 ) ( B-07 ) ( B-03 ) ( B-04 ) ( B-05 ) ( B-06 ) ( B-02 ) ( B-01 ) ( A-08 ) ( A-07 ) ( A-05 ) ( A-01 ) ( A-03 ) ( A-02 )
3. Schedule “Event” to “Start no earlier than” 10/26/2017
4. Schedule “Order Food” to “Finish no later than” 10/24/2017
5. Set deadline of “Preparation Complete’ to 10/24/2017
6. Schedule “Purchase Tableware and Prizes” to “Finish no later than” 10/22/2017
7. Show Critical Path
a. For Text area, show critical tasks with font “Times New Roman” and “red” color.
b. For Gantt area, show critical tasks and.
8. Mark “Preparation Complete” and “Party Complete” as milestones
9. Save the file as MyLab2.mpp
10. Close the file